19.2 Commissioning & Decommissioning

Queensland Electrical Licence Capstone Assessment Exam

Track your progress as you read

Finished sections get a check mark.

1 Introduction & Capstone Overview

1.1 Current Capstone Exam Facts 1.2 Capstone Written & Practical Format 1.3 Queensland ESO Licence Pathway

2 AS/NZS 3000 Fundamentals

2.1 Scope & Fundamental Principles 2.2 Nominal Voltages & System Classifications 2.3 Conductor Identification & Colour Coding 2.4 Protection Against Electric Shock

3 Isolation, Switching & Special Locations

3.1 Isolation & Switching 3.2 Special Locations (Bathrooms, Pools & More) 3.3 Installation Defects & Rectification

4 Cable Selection Basics (AS/NZS 3008)

4.1 Current-Carrying Capacity & Installation Methods 4.2 Reference Temperatures & Insulation Types 4.3 Grouping & Thermal Derating Factors 4.4 Cable Short-Circuit Capacity

5 Voltage Drop & Selection Order

5.1 Voltage Drop (mV/A·m) & the 5% Limit 5.2 Order of Cable-Selection Checks 5.3 Worked Cable Selection Examples

6 Maximum Demand Calculations

6.1 Diversity & Appendix C Overview 6.2 Domestic Table C1 Demand Factors 6.3 Commercial Demand & Mains/Main-Switch Sizing

7 Circuit Protection Coordination

7.1 Overload & Short-Circuit Protection 7.2 The Ib ≤ In ≤ Iz Coordination Rule 7.3 Circuit-Breaker Curves & Breaking Capacity 7.4 Discrimination & Selectivity

8 RCDs, Division of Circuits & SELV/PELV

8.1 RCD Types & 30 mA Additional Protection 8.2 Division of Circuits 8.3 SELV & PELV Systems

9 Earthing & the MEN System

9.1 MEN System Principles & Fault Return Path 9.2 The MEN Link at the Main Switchboard 9.3 Main Earthing Conductor Sizing (Table 5.1) 9.4 Equipotential Bonding

10 Electrodes, Adiabatic & Prospective Fault Current

10.1 Earth Electrodes & Arrangements 10.2 The Adiabatic Equation for Protective Conductors 10.3 Prospective Fault Current

11 Earth-Fault-Loop Impedance & Disconnection

11.1 Earth-Fault-Loop Impedance (Zs = Ze + R1 + R2) 11.2 Disconnection Times (0.4 s & 5 s) 11.3 Breaking Capacity Coordination with PFC

12 Consumer Mains & Submains

12.1 Point of Supply Definitions 12.2 Consumer Mains Sizing & Installation 12.3 Submains Definitions & Sizing 12.4 Neutral & Earth Separation Downstream

13 QLD Electrical Safety Legislation

13.1 Electrical Safety Act 2002 & the ESO 13.2 Licensing Classes & Worker Duties 13.3 Certificates of Testing & Compliance 13.4 Construction Sites (AS/NZS 3012)

14 Safe Work & Critical Theory

14.1 Safe Isolation & Lock-Out/Tag-Out 14.2 Energised Electrical Work Controls 14.3 Effects of Electric Current (Critical EPC Theory)

15 Testing & Verification

15.1 AS/NZS 3000 Section 8 Test Sequence 15.2 Earth Continuity & Polarity 15.3 Insulation Resistance (1 MΩ at 500 V DC) 15.4 RCD Testing & Loop-Impedance Verification 15.5 AS/NZS 3017 Verification, Reporting & Documentation

16 DC, AC & Three-Phase Circuit Theory

16.1 DC Circuits, Ohm’s Law & Power 16.2 AC Generation, RMS Values & Phase 16.3 Three-Phase Systems & Phase Sequence

17 Motors, Transformers & Switchboards

17.1 Motor Selection, Enclosures & Starting Methods 17.2 Motor Overload & Short-Circuit Protection 17.3 Transformer Key Safety Issues 17.4 Switchboard Location, Arrangement & Form Types

18 Wiring Systems, Aerials & Hazardous Areas

18.1 Cable Installation & Termination Requirements 18.2 Final Subcircuits Into Switchboards 18.3 Aerial Conductors & Underground Wiring 18.4 Hazardous Areas & Classified Zones

19 Drawings, Commissioning & Fault Rectification

19.1 Reading, Sketching & Interpreting Electrical Diagrams 19.2 Commissioning & Decommissioning 19.3 Diagnosing & Rectifying Faults

20 Workplace Safety, Rescue & High Voltage

20.1 Statutory WHS Duties, Supervision & Duty of Care 20.2 Asbestos, Silica & Hazardous Gases 20.3 Workplace Safety Checks & Hazard Control 20.4 Rescue From Live Electrical Conductors 20.5 Electric Shock First Aid & CPR 20.6 High Voltage Dangers & Distribution Systems

19.2 Commissioning & Decommissioning

Key Takeaways Explain This Topic AI

EPC 50 is a critical capability covering commissioning and decommissioning using a systems approach

Commissioning follows verification: only after Section 8 tests pass do you energise, check circuit voltages and phase rotation, then load up systematically

Systematic loading up means energising in stages and confirming behaviour at each stage rather than switching everything on at once

Decommissioning starts with identifying all circuits and assessing the impact on other equipment before anything is switched off

Unused cable must be safely removed or terminated and made safe — a live abandoned conductor left in a ceiling is a serious defect

Last updated: August 2026

Commissioning & Decommissioning

Quick Answer: Commissioning is the controlled process of bringing a verified installation into service: energise, check circuit voltages, check phase rotation and polarity, load up systematically , confirm the installation functions correctly and check instrument and control parameters. Decommissioning is the reverse discipline: identify every circuit, assess the impact on other equipment, isolate, tag, test, secure and earth where required, then safely remove or terminate unused cable.

A Systems Approach

"Systems approach" is the phrase in the capability, and it is the whole point. You are not switching on a light; you are bringing a system into service in a controlled sequence where each step confirms the previous one before adding energy or load.

The three phases:

Verification (Chapter 15) — proving the installation is safe to connect.

Commissioning — bringing it into service in stages and confirming it behaves as designed.

Handover — documentation, certificates, schedules, as-installed drawings and operator instruction.

Commissioning never substitutes for verification. If Section 8 testing has not passed, there is nothing to commission.

  • The Commissioning Sequence
  • 1. Pre-energisation confirmation

Verification tests complete and results recorded.

All covers, escutcheons and barriers fitted; no exposed live parts.

All circuits labelled and the board schedule complete.

Personnel notified and the area controlled — nobody working downstream.

Distributor or supply authority requirements satisfied where connection depends on them.

2. Circuit voltage testing

Energise progressively and confirm at each board:

Line to neutral on each phase — expect approximately 230 V.

Line to line — expect approximately 400 V.

Line to earth, confirming the earthing reference is present.

Unequal or missing voltages point to a lost phase, a loose connection or a wrongly landed conductor. Investigate before proceeding; do not "load it and see".

3. Phase rotation and polarity checks

Confirm rotation with an indicator at each board and at every point feeding rotating plant (Section 16.3).

Confirm polarity at outlets and equipment — active to active, neutral to neutral, earth to earth.

Confirm rotation is consistent across boards, not merely correct at one.

4. Systematic loading up

Do not close every device at once. Load the installation in stages:

Energise the main switchboard and confirm.

Energise each submain and confirm at the distribution board.

Energise circuits group by group, confirming current and voltage as load is added.

Start rotating plant individually, observing starting current and confirming direction before coupling where practicable.

Watch for voltage dip, unexpected tripping, unbalanced loading and unusual noise or smell at each stage.

Staged loading is what allows you to attribute a problem to the step that caused it. Energising everything simultaneously turns a five-minute diagnosis into a half-day.

5. Correct installation functioning

Confirm each circuit does what its label says.

Confirm switching, control, emergency stops and interlocks operate as designed.

Confirm RCDs trip on test and on the instrument, and that they reset.

Confirm lighting control, time clocks and sensors behave as specified.

6. Instrument and control parameter checks

Set and record overload relay settings, trip classes, drive parameters and protection settings.

Confirm metering reads correctly and CT ratios match the meter configuration.

Record every setpoint — an undocumented setting is one nobody can restore after a fault.

7. Dangers of mechanical damage

Throughout commissioning, watch for cables and equipment damaged by other trades: plasterers, tilers and ceiling fixers regularly damage cables after the electrician's rough-in. Re-inspect accessible routes before final energisation.

The Decommissioning Sequence

Decommissioning is where an unhurried electrician stays safe and a rushed one energises a conductor they thought was dead.

1. Identification of all circuits

Establish exactly what is being removed and everything it feeds. Use drawings, schedules and physical tracing. Assume records are incomplete until proved otherwise.

2. Impact on other equipment

Ask what else depends on this supply: shared neutrals, control interlocks, fire and security systems, emergency lighting, refrigeration, IT equipment on the same board. Removing a circuit that shares a neutral with a live circuit is a shock hazard and a functional failure.

3. Isolation

Isolate all sources, including any secondary or backup supply — generators, UPS, solar inverters and battery systems. Apply the full identify–isolate–lock–tag–prove sequence from Chapter 14.

4. Tagging

Tag at the point of isolation with who applied it, when and why. Personal locks stay with the person who applied them.

5. Testing

Prove dead at the point of work with a proving unit before and after. On a decommissioning job the conductor you are about to cut is the one that must be proved.

6. Securing and earthing where required

For high-energy or high-voltage systems, apply earths as the procedure requires so induced or stored energy cannot re-energise the conductor. Capacitor banks and drive DC buses must be discharged and confirmed.

7. Safe removal and termination of unused cable

Withdraw the cable completely where practicable.

Where a cable cannot be withdrawn, disconnect it at the source, terminate the conductors safely in an accessible enclosure, and label it clearly as disconnected and dead.

Never leave an unterminated conductor that could be re-energised. An abandoned live conductor in a ceiling space is a serious defect and has killed people.

Update drawings and the board schedule, and remove the redundant circuit label so nobody thinks it still exists.