6.2 Lien Notices, Recording & Deadlines

Arizona General Contractor Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Introduction & Exam Overview

1.1 Current Exam Facts 1.2 The Arizona Contractor Licensing Path 1.3 How to Use This Guide & Study Plan

2 Chapter 2: Arizona ROC & Licensing Law

2.1 The Arizona Registrar of Contractors 2.2 License Classifications 2.3 Qualifying Party & Experience Requirements 2.4 Application, Fees, Bond & Background Check 2.5 License Bonds, Cash Deposits & Bond Claims 2.6 Unlicensed Contracting: Penalties & Lost Remedies 2.7 Advertising Rules, Contract Disclosures & Workmanship Standards

3 Chapter 3: The Exams — SRE, Trade & NASCLA

3.1 The Statutes & Rules Exam (SRE) 3.2 The PSI Trade Exam 3.3 The NASCLA Commercial General Building Exam Option

4 Chapter 4: License Maintenance, Recovery Fund & Discipline

4.1 License Renewal & Continuing Education 4.2 The Residential Contractors' Recovery Fund 4.3 ROC Disciplinary Actions & Penalties

5 Chapter 5: Contract Law & Disputes

5.1 Arizona Contract Fundamentals 5.2 Construction Contract Terms & Provisions 5.3 Change Orders & Modifications 5.4 Dispute Resolution & ROC Complaints 5.5 The Arizona Prompt Payment Act

6 Chapter 6: Liens, Bonds & Insurance

6.1 Arizona Mechanics' Lien Law Overview 6.2 Lien Notices, Recording & Deadlines 6.3 Contract Bonds: Bid, Performance & Payment 6.4 Insurance Requirements

7 Chapter 7: Financial Management & Taxes

7.1 Accounting & Financial Statements 7.2 Estimating, Bidding & Markup 7.3 Taxes & Payroll

8 Chapter 8: Project Management

8.1 Scheduling & the Critical Path Method 8.2 Supervision, Subcontractors & Quality Control 8.3 Project Documentation & Closeout

9 Chapter 9: Safety & OSHA

9.1 OSHA Construction Standards Overview 9.2 Fall Protection, Scaffolds & Ladders 9.3 Excavation, Trenching & Electrical Safety 9.4 Heat Illness Prevention & Arizona Job-Site Hazards

10 Chapter 10: Building Codes, Permits & Plan Reading

10.1 IRC 2018 & IBC 2018 Fundamentals 10.2 Permits, Plan Review & Inspections 10.3 Energy Code & Accessibility 10.4 Reading Construction Drawings & Specifications 10.5 Means of Egress & Fire-Resistance-Rated Construction

11 Chapter 11: Sitework, Concrete & Masonry

11.1 Sitework: Surveying, Excavation & Grading 11.2 Concrete: Formwork, Reinforcement & Placing 11.3 Masonry: Brick, Block & Mortar 11.4 Soils, Compaction & Earthwork Testing 11.5 Concrete Materials & Mix Design 11.6 Concrete Curing, Joints, Testing & Defects 11.7 Masonry Reinforcement, Grouting & Wall Systems

12 Chapter 12: Carpentry, Metals & Building Envelope

12.1 Carpentry & Framing 12.2 Metals & Metal Framing 12.3 Thermal & Moisture Protection 12.4 Doors, Windows & Finishes 12.5 Engineered Wood, Trusses & Connectors 12.6 Structural Steel Erection & Connections 12.7 Steel Joists, Girders & Metal Deck

13 Chapter 13: Roofing, Waterproofing & Interior Finishes

13.1 Roofing Systems 13.2 Waterproofing, Flashing & Sealants 13.3 Interior Finishes: Gypsum, Stucco, Flooring & Paint

14 Chapter 14: Building Systems for the General Contractor

14.1 Mechanical & Plumbing Systems 14.2 Electrical Systems & Temporary Power

6.2 Lien Notices, Recording & Deadlines

Key Takeaways Explain This Topic AI

Serve the preliminary 20-day notice under A.R.S. § 33-992.01 on the owner, the general contractor, and any construction lender within 20 days of first furnishing labor or materials

Record the lien within 120 days after completion — or within 60 days after a recorded notice of completion, whichever comes first (A.R.S. § 33-993)

File the foreclosure suit and record a lis pendens within 6 months of recording the lien (A.R.S. § 33-998 and § 12-1191) or the lien is extinguished

A.R.S. § 33-1002 bars any lien on an owner-occupant's dwelling except by a party holding a written contract signed directly with the owner-occupant

Serving the 20-day notice late does not forfeit lien rights entirely — it limits them to work furnished within the 20 days before service

Last updated: August 2026

The Three-Step Lien Process

Quick Answer: To perfect an Arizona mechanics' lien, a claimant must (1) serve a preliminary 20-day notice under A.R.S. § 33-992.01 within 20 days of first furnishing labor or materials, (2) record the lien in the county recorder's office within 120 days after completion — or within 60 days after a notice of completion is recorded, whichever comes first — under § 33-993, and (3) file suit to foreclose within 6 months of recording under § 33-998 (and record a lis pendens within that same 6-month window per § 12-1191).

Perfecting a mechanics' lien in Arizona is a sequential, deadline-driven process. Missing any step or deadline can extinguish the lien right entirely. The three steps below are tested heavily on the Statutes & Rules Exam (SRE) .

Step 1 — Preliminary 20-Day Notice (§ 33-992.01)

The preliminary 20-day notice is the prerequisite that preserves lien rights for most claimants other than the general contractor (who has a direct contract with the owner). Under A.R.S. § 33-992.01 , a subcontractor, material supplier, equipment lessor, or laborer must serve a written notice on three parties:

The property owner (or the owner's agent).

The general contractor (the prime contractor with the direct owner contract).

The construction lender , if any (the lender financing the improvement).

The notice must be served within 20 days of the claimant first furnishing labor, professional services, or materials to the project. If the claimant fails to serve the notice within that 20-day window, the claimant may still serve it later, but lien rights extend back only 20 days before service — meaning work or materials furnished before the late notice may be uncompensated under the lien. Serving the notice early is the safe practice.

Who does NOT need a 20-day notice? A general contractor (prime contractor) with a direct contractual relationship with the owner generally is not required to serve a preliminary 20-day notice, because the owner already knows of the GC's involvement.

Step 2 — Recording the Lien (§ 33-993)

After the work is complete, the claimant must record the actual mechanics' lien. Under A.R.S. § 33-993 , the lien must be recorded in the county recorder's office of the county where the improved property is located, within 120 days after completion of the building, structure, or improvement — or, if the owner has recorded a notice of completion, within 60 days after that recordation. The two deadlines are alternatives and the earlier one controls, so a recorded notice of completion can cut your window by two months without any further warning to you. Watch the county recorder's index on projects that are winding down. The recorded lien must contain:

The name and address of the claimant.

The name of the owner or reputed owner.

A description of the property to be encumbered (typically the legal description and assessor's parcel number).

The nature of the labor, professional services, or materials furnished.

The amount for which the lien is claimed.

The date of first furnishing of labor or materials.

"Completion" of the project has a statutory meaning: it generally occurs when the work is fully finished, or when the owner occupies or uses the improvement, or when a notice of completion is recorded — whichever triggers the statutory definition. A claimant should not wait until the last week of the 120-day window; recording promptly protects priority and avoids missing the deadline.

Step 3 — Foreclosure Suit (§ 33-998)

Recording the lien does not get the claimant paid — it only creates the encumbrance. To convert the lien into money, the claimant must file a suit to foreclose the lien. Under A.R.S. § 33-998 , the foreclosure suit must be brought within 6 months of the date the lien was recorded , and a notice of pendency of action (lis pendens) must be recorded in the county recorder's office within that same 6-month window pursuant to A.R.S. § 12-1191 . If no foreclosure suit is filed (and lis pendens recorded) within that 6-month period, the lien is automatically extinguished and unenforceable. The 6-month clock runs from the date the lien was recorded, not from project completion.

The Owner-Occupant Bar (§ 33-1002) — Arizona's Biggest Lien Exception

On residential work, the notice-and-recording sequence above can be irrelevant, because A.R.S. § 33-1002(B) bars the lien outright : "No lien provided for in this article shall be allowed or recorded by the person claiming a lien against the dwelling of a person who became an owner-occupant prior to the construction, alteration, repair or improvement, except by a person having executed in writing a contract directly with the owner-occupant."

Read that carefully. On a remodel or repair for someone who already owned and occupied the home before the work began, only a party with a written contract signed directly with the owner-occupant can lien. Subcontractors, material suppliers, and equipment lessors — the very parties the 20-day notice exists to protect — have no lien rights at all on that dwelling, no matter how perfectly they served the notice. Their remedies are the contract with the general contractor, the general's payment bond if one exists, and, for an owner-occupant claimant, the Residential Contractors' Recovery Fund.

An owner-occupant under § 33-1002(A) is a natural person who (a) held recorded legal or equitable title to the dwelling before the work commenced, and (b) resides or intends to reside there at least 30 days during the 12-month period immediately following completion , without intending to sell or lease it.

Critical trap: the "12 months" in § 33-1002 is part of the owner-occupant definition , not a deadline. It is not the foreclosure period. Exams use that figure as a distractor against the real 6 months from recording in § 33-998. Keep the three numbers straight: 20 days (notice), 120/60 days (recording), 6 months (foreclosure) — and 12 months is not a deadline at all.

Lien Waivers (§ 33-999)

A lien waiver is a written instrument by which a lien claimant gives up lien rights, typically in exchange for payment. Arizona recognizes several waiver types:

Waiver type What it does When commonly used

Conditional waiver on progress payment Waives lien rights for amounts paid through a date, only if the payment clears With each progress draw

Unconditional waiver on progress payment Waives lien rights for amounts paid through a date, regardless of whether the payment clears After a progress payment has cleared

Conditional waiver on final payment Waives all remaining lien rights only if final payment clears With final payment

Unconditional waiver on final payment Waives all remaining lien rights, regardless of payment clearing After final payment has cleared and project is closed

Caution: an unconditional waiver is dangerous if the check has not cleared. Contractors and suppliers should generally sign conditional waivers until funds are in hand.

  • Timeline Diagram Day 0: First furnish labor/materials
  • |
  • v
  • Within 20 days: Serve preliminary 20-day notice (§ 33-992.01)
  • on owner, GC, and construction lender
  • |
  • v
  • Project completion
  • |
  • v
  • Within 120 days after completion — or 60 days
  • after a recorded notice of completion, whichever
  • is earlier: Record mechanics' lien (§ 33-993)
  • |
  • v
  • Within 6 months of recording: File foreclosure suit (§ 33-998)
  • and record lis pendens (§ 12-1191)
  • Deadline Summary Table
  • Deadline Statute Action
  • 20 days from first furnishing § 33-992.01 Serve preliminary 20-day notice

120 days after completion or 60 days after a recorded notice of completion, whichever is earlier § 33-993 Record mechanics' lien

6 months from recording § 33-998 File foreclosure suit + record lis pendens (§ 12-1191)

No deadline — an absolute bar § 33-1002 Subs and suppliers cannot lien an owner-occupant's dwelling without a direct written contract

Exam tip: the SRE tests the 20-day notice, the 120-day recording deadline, and the 6-month foreclosure deadline as a set. Memorize all three as a single sequence — and memorize which statute governs which step.