Study guide

13.1 Roofing Systems

Arizona General Contractor Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Introduction & Exam Overview

1.1 Current Exam Facts 1.2 The Arizona Contractor Licensing Path 1.3 How to Use This Guide & Study Plan

2 Chapter 2: Arizona ROC & Licensing Law

2.1 The Arizona Registrar of Contractors 2.2 License Classifications 2.3 Qualifying Party & Experience Requirements 2.4 Application, Fees, Bond & Background Check 2.5 License Bonds, Cash Deposits & Bond Claims 2.6 Unlicensed Contracting: Penalties & Lost Remedies 2.7 Advertising Rules, Contract Disclosures & Workmanship Standards

3 Chapter 3: The Exams — SRE, Trade & NASCLA

3.1 The Statutes & Rules Exam (SRE) 3.2 The PSI Trade Exam 3.3 The NASCLA Commercial General Building Exam Option

4 Chapter 4: License Maintenance, Recovery Fund & Discipline

4.1 License Renewal & Continuing Education 4.2 The Residential Contractors' Recovery Fund 4.3 ROC Disciplinary Actions & Penalties

5 Chapter 5: Contract Law & Disputes

5.1 Arizona Contract Fundamentals 5.2 Construction Contract Terms & Provisions 5.3 Change Orders & Modifications 5.4 Dispute Resolution & ROC Complaints 5.5 The Arizona Prompt Payment Act

6 Chapter 6: Liens, Bonds & Insurance

6.1 Arizona Mechanics' Lien Law Overview 6.2 Lien Notices, Recording & Deadlines 6.3 Contract Bonds: Bid, Performance & Payment 6.4 Insurance Requirements

7 Chapter 7: Financial Management & Taxes

7.1 Accounting & Financial Statements 7.2 Estimating, Bidding & Markup 7.3 Taxes & Payroll

8 Chapter 8: Project Management

8.1 Scheduling & the Critical Path Method 8.2 Supervision, Subcontractors & Quality Control 8.3 Project Documentation & Closeout

9 Chapter 9: Safety & OSHA

9.1 OSHA Construction Standards Overview 9.2 Fall Protection, Scaffolds & Ladders 9.3 Excavation, Trenching & Electrical Safety 9.4 Heat Illness Prevention & Arizona Job-Site Hazards

10 Chapter 10: Building Codes, Permits & Plan Reading

10.1 IRC 2018 & IBC 2018 Fundamentals 10.2 Permits, Plan Review & Inspections 10.3 Energy Code & Accessibility 10.4 Reading Construction Drawings & Specifications 10.5 Means of Egress & Fire-Resistance-Rated Construction

11 Chapter 11: Sitework, Concrete & Masonry

11.1 Sitework: Surveying, Excavation & Grading 11.2 Concrete: Formwork, Reinforcement & Placing 11.3 Masonry: Brick, Block & Mortar 11.4 Soils, Compaction & Earthwork Testing 11.5 Concrete Materials & Mix Design 11.6 Concrete Curing, Joints, Testing & Defects 11.7 Masonry Reinforcement, Grouting & Wall Systems

12 Chapter 12: Carpentry, Metals & Building Envelope

12.1 Carpentry & Framing 12.2 Metals & Metal Framing 12.3 Thermal & Moisture Protection 12.4 Doors, Windows & Finishes 12.5 Engineered Wood, Trusses & Connectors 12.6 Structural Steel Erection & Connections 12.7 Steel Joists, Girders & Metal Deck

13 Chapter 13: Roofing, Waterproofing & Interior Finishes

13.1 Roofing Systems 13.2 Waterproofing, Flashing & Sealants 13.3 Interior Finishes: Gypsum, Stucco, Flooring & Paint

14 Chapter 14: Building Systems for the General Contractor

14.1 Mechanical & Plumbing Systems 14.2 Electrical Systems & Temporary Power

13.1 Roofing Systems

Key Takeaways Explain This Topic AI

Low-slope roofing includes built-up, modified bitumen, and single-ply TPO, PVC, and EPDM membranes, attached mechanically, fully adhered, or ballasted

Asphalt shingles generally require a minimum 2:12 slope, with double underlayment required between 2:12 and 4:12

Positive drainage is required on low-slope roofs; standing water beyond 48 hours after rainfall indicates a slope or drain defect

Tile roofs in Arizona are watertight because of the underlayment, not the tile — the tile is a wear and shading surface

Manufacturer installation instructions become the enforceable standard, and a departure usually voids both the warranty and code compliance

Last updated: August 2026

Roofing Is Where Warranty Claims Live

Quick Answer: Thermal and Moisture Protection carries 10 of 100 items on the AZ ROC commercial outline and 12 of 100 on the residential outline. Roofing questions concentrate on minimum slope , underlayment , attachment , and flashing , and the governing document in the field is usually the manufacturer's installation instructions .

Roofs generate more complaints than any other single building element, and AZ ROC's workmanship standards treat leaks, exposed fasteners, and missing flashing at penetrations as defects. In Arizona the failure modes are not the ones a contractor from a wet climate expects: the enemies are ultraviolet degradation , thermal cycling , and monsoon wind uplift and wind-driven rain , not months of standing moisture.

Low-Slope Systems

Low-slope roofs (roughly ¼:12 to 2:12) rely on a continuous membrane rather than shedding water by gravity alone.

System Description Notes

BUR — built-up roof Multiple plies of felt in bitumen, usually with a gravel or coating surfacing Durable, heavy, labor-intensive

Modified bitumen Factory-reinforced sheets, torch-, mop-, cold-adhesive-, or self-adhered Common on smaller commercial roofs

TPO — thermoplastic polyolefin Single-ply, heat-welded seams, typically white Very common; reflective, good for Arizona cooling loads

  • PVC Single-ply, heat-welded, chemical resistant Restaurants, industrial with grease exhaust
  • EPDM Single-ply rubber, seamed with tape or adhesive Long service history; typically black

SPF — sprayed polyurethane foam Foam sprayed in place plus a protective coating Popular in Arizona; seamless, self-flashing, requires periodic recoating

Attachment How it works

Mechanically attached Fasteners and plates through the membrane into the deck; fastest, but every fastener is a potential leak path if misdriven

  • Fully adhered Membrane bonded to the substrate; best wind performance and smoothest appearance
  • Ballasted Loose-laid membrane held by stone or pavers; least common on new work, and wind-restricted

Two requirements govern every low-slope roof:

Positive drainage. The IBC requires roofs to be designed and built so water drains. Water still standing more than about 48 hours after rainfall points to inadequate slope, a blocked or high drain, or deck deflection — and it is a defect, not a nuisance.

Secondary (overflow) drainage. Where a parapet can trap water, overflow scuppers or secondary drains are required so a plugged primary drain does not load the roof with water. In monsoon country this is not theoretical.

Steep-Slope Systems

  • Covering Minimum slope (typical) Notes
  • Asphalt shingles 2:12 Double underlayment required from 2:12 to less than 4:12; single layer at 4:12 and above

Concrete or clay tile 2½:12 with a code-compliant underlayment assembly Ubiquitous in Arizona; heavy — verify structural capacity on re-roofs

  • Metal panel, standing seam Varies by profile; commonly ¼:12 to 3:12 Follow the manufacturer's listing
  • Wood shakes and shingles 3:12 to 4:12 Rare in Arizona; wildfire restrictions apply

The tile roof point every Arizona contractor should know: a tile roof is not waterproofed by the tile. The underlayment is the water barrier; the tile is a wear surface that sheds most of the water, shades the underlayment from ultraviolet light, and provides the appearance. That is why tile roofs "fail" at 20 to 30 years even though the tile is intact — the underlayment beneath has embrittled. A re-roof that lifts and re-lays tile over new underlayment is standard Arizona work, and quoting it as a repair when the underlayment is spent is a complaint waiting to happen.

Underlayment and ice barriers. Arizona's low deserts have no ice-dam requirement, but the high country does — Flagstaff, the White Mountains, and other elevations adopt the ice-barrier provisions. Never assume a Phoenix detail transfers to a Show Low project.

Flashing is where roofs actually leak: valleys, headwalls and sidewalls, chimneys and crickets, vent penetrations, curbs, and the drip edge at eaves and rakes. AZ ROC's workmanship standards call out missing flashing at penetrations as a defect in its own right.

Arizona-Specific Conditions

Condition Effect Response

Extreme ultraviolet exposure Degrades exposed membranes, sealants, and underlayment faster than in most climates Reflective surfacing; UV-stable products; recoat SPF on schedule

Large daily thermal swings Cyclic expansion and contraction fatigues seams and fasteners Expansion joints; correct fastener patterns; avoid restraint

Monsoon wind uplift Peels membranes at corners and perimeters Enhanced perimeter and corner fastening per the wind design

Wind-driven rain Pushes water uphill under coverings Correct headlaps and side laps; sealed underlayment at vulnerable areas

Dust and debris Clogs drains and scuppers before a storm Pre-monsoon drain cleaning as a maintenance item

Roof wind design is zoned: corners take the highest uplift, then perimeters , then the field of the roof. Fastening patterns tighten accordingly, and a crew that uses the field pattern everywhere has built a roof that will unzip from a corner in the first serious haboob.

Exam tip: when a question gives a slope and asks what covering or underlayment is permitted, work from the slope. 2:12 is the floor for asphalt shingles, and 2:12 to under 4:12 requires doubled underlayment. Below 2:12, you are in low-slope membrane territory.