11.6 Concrete Curing, Joints, Testing & Defects
Arizona General Contractor Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Introduction & Exam Overview
1.1 Current Exam Facts 1.2 The Arizona Contractor Licensing Path 1.3 How to Use This Guide & Study Plan
2 Chapter 2: Arizona ROC & Licensing Law
2.1 The Arizona Registrar of Contractors 2.2 License Classifications 2.3 Qualifying Party & Experience Requirements 2.4 Application, Fees, Bond & Background Check 2.5 License Bonds, Cash Deposits & Bond Claims 2.6 Unlicensed Contracting: Penalties & Lost Remedies 2.7 Advertising Rules, Contract Disclosures & Workmanship Standards
3 Chapter 3: The Exams — SRE, Trade & NASCLA
3.1 The Statutes & Rules Exam (SRE) 3.2 The PSI Trade Exam 3.3 The NASCLA Commercial General Building Exam Option
4 Chapter 4: License Maintenance, Recovery Fund & Discipline
4.1 License Renewal & Continuing Education 4.2 The Residential Contractors' Recovery Fund 4.3 ROC Disciplinary Actions & Penalties
5 Chapter 5: Contract Law & Disputes
5.1 Arizona Contract Fundamentals 5.2 Construction Contract Terms & Provisions 5.3 Change Orders & Modifications 5.4 Dispute Resolution & ROC Complaints 5.5 The Arizona Prompt Payment Act
6 Chapter 6: Liens, Bonds & Insurance
6.1 Arizona Mechanics' Lien Law Overview 6.2 Lien Notices, Recording & Deadlines 6.3 Contract Bonds: Bid, Performance & Payment 6.4 Insurance Requirements
7 Chapter 7: Financial Management & Taxes
7.1 Accounting & Financial Statements 7.2 Estimating, Bidding & Markup 7.3 Taxes & Payroll
8 Chapter 8: Project Management
8.1 Scheduling & the Critical Path Method 8.2 Supervision, Subcontractors & Quality Control 8.3 Project Documentation & Closeout
9 Chapter 9: Safety & OSHA
9.1 OSHA Construction Standards Overview 9.2 Fall Protection, Scaffolds & Ladders 9.3 Excavation, Trenching & Electrical Safety 9.4 Heat Illness Prevention & Arizona Job-Site Hazards
10 Chapter 10: Building Codes, Permits & Plan Reading
10.1 IRC 2018 & IBC 2018 Fundamentals 10.2 Permits, Plan Review & Inspections 10.3 Energy Code & Accessibility 10.4 Reading Construction Drawings & Specifications 10.5 Means of Egress & Fire-Resistance-Rated Construction
11 Chapter 11: Sitework, Concrete & Masonry
11.1 Sitework: Surveying, Excavation & Grading 11.2 Concrete: Formwork, Reinforcement & Placing 11.3 Masonry: Brick, Block & Mortar 11.4 Soils, Compaction & Earthwork Testing 11.5 Concrete Materials & Mix Design 11.6 Concrete Curing, Joints, Testing & Defects 11.7 Masonry Reinforcement, Grouting & Wall Systems
12 Chapter 12: Carpentry, Metals & Building Envelope
12.1 Carpentry & Framing 12.2 Metals & Metal Framing 12.3 Thermal & Moisture Protection 12.4 Doors, Windows & Finishes 12.5 Engineered Wood, Trusses & Connectors 12.6 Structural Steel Erection & Connections 12.7 Steel Joists, Girders & Metal Deck
13 Chapter 13: Roofing, Waterproofing & Interior Finishes
13.1 Roofing Systems 13.2 Waterproofing, Flashing & Sealants 13.3 Interior Finishes: Gypsum, Stucco, Flooring & Paint
14 Chapter 14: Building Systems for the General Contractor
14.1 Mechanical & Plumbing Systems 14.2 Electrical Systems & Temporary Power
11.6 Concrete Curing, Joints, Testing & Defects
Key Takeaways Explain This Topic AI
Curing maintains moisture and temperature so hydration continues; specified compressive strength is referenced to 28-day cylinder breaks
Control joints must be cut to at least one-quarter of the slab depth and are commonly spaced in feet at roughly two to three times the slab thickness in inches
Standard-cured cylinders test the concrete as delivered; field-cured cylinders test the in-place curing and protection
A slump test measures consistency, not strength — a passing slump says nothing about compressive strength
Scaling, crazing, dusting, delamination, and plastic shrinkage cracking each trace to a specific finishing or curing error
Last updated: August 2026
Hydration Does Not Stop at the Pour
Quick Answer: Curing is maintaining adequate moisture and temperature so cement hydration continues after placement. Concrete that dries out early never reaches its design strength no matter how good the mix was. Minimum curing is commonly 7 days for normal cement and about 3 days where Type III high-early-strength cement is used.
Concrete does not "dry" — it hydrates. Water is a reactant. Concrete kept continuously moist keeps gaining strength for months; concrete allowed to dry at day two stops permanently at whatever strength it had reached. In Arizona's low humidity, that difference can be 30% or more of design strength, and it is invisible until the cylinders come back.
Curing Methods and Duration
- Method How it works Notes
- Ponding / immersion Standing water on the surface Best control; practical only on flat, contained slabs
- Continuous fog or sprinkling Keeps the surface wet Water use is high; must not be allowed to cycle wet/dry
- Wet burlap or cotton mats Absorbent covering kept saturated Must never be allowed to dry out
- Plastic sheeting Traps moisture Can cause surface discoloration; seams must be lapped and sealed
Curing compound Membrane sprayed on the surface Most common on large slabs; must be applied at the specified coverage rate immediately after finishing
Insulating blankets Retains heat Cold-weather work at higher Arizona elevations
- Condition Typical minimum curing
- Normal Type I/II concrete 7 days
- Type III high-early-strength 3 days
- High-performance, low w/c mixes 7 days or more, with tighter moisture control
Warning: a curing compound sprayed too thin, or applied hours late after the surface has already dried, does not cure — it just makes the slab look wet. Coverage rate and timing are both specification items.
Joints: Three Types, Three Jobs
Concrete shrinks as it dries and moves as it changes temperature. Jointing controls where the resulting cracks go.
Joint Purpose Detail
Control (contraction) joint Creates a plane of weakness so shrinkage cracks form in a straight, planned line Sawcut or tooled to at least ¼ of slab depth (¼ T)
Construction joint Stops a placement where work ends for the day Bulkhead with keyway or dowels; a planned cold joint
Isolation (expansion) joint Separates the slab from columns, walls, and other fixed elements so they can move independently Full-depth compressible filler; no reinforcement crossing
Spacing rules of thumb. Control joint spacing in feet is commonly two to three times the slab thickness in inches: a 4-inch slab gets joints roughly every 8 to 12 feet, a 6-inch slab roughly every 12 to 18 feet. Panels should be kept close to square — an aspect ratio beyond about 1.5 to 1 invites a crack across the middle of the panel regardless of the joints at its edges.
Sawcut timing is the other half. Cut too early and the saw ravels the edge; cut too late and the slab has already cracked on its own. The window for conventional wet sawing is roughly 4 to 12 hours after placement depending on temperature and mix, and early-entry dry saws move that window earlier. In July in Phoenix, the window closes fast — crews that plan to cut "first thing tomorrow" find random cracks waiting for them.
Testing: What Each Test Actually Proves
- Test Standard Measures Does not measure
- Slump ASTM C143 Consistency / workability Strength, w/c ratio, air content
- Air content ASTM C231 (pressure) / C173 (volumetric) Entrained plus entrapped air Strength
- Temperature ASTM C1064 Concrete temperature at delivery —
- Unit weight / yield ASTM C138 Density and delivered volume Strength
- Cylinder casting ASTM C31 Specimen preparation and curing —
- Compressive strength ASTM C39 Compressive strength at test age Durability, finish quality
Slump is the one candidates over-read. A 4-inch slump load and a 4-inch slump load can have entirely different strengths, because a superplasticized 0.42 mix and a watered-up 0.58 mix can arrive at the same consistency. Slump verifies that the load matches what was ordered; it is not a strength test.
Cylinders are the acceptance test. Standard practice is a set cast per specified volume or per day's placement, with breaks typically at 7 and 28 days. Two curing regimes answer two different questions:
Standard-cured (lab-cured) cylinders are stored under controlled moisture and temperature. They test the concrete as delivered and are the basis for accepting or rejecting the mix.
Field-cured cylinders sit at the jobsite under the same conditions as the structure. They test the adequacy of curing and protection in place , and are used to decide when forms may be stripped or a slab may be loaded.
That distinction is a favorite exam item. If the field-cured cylinders break low but the standard-cured cylinders pass, the mix was fine and the curing failed — which is a contractor problem, not a supplier problem.
Worked example. A specification calls for 4,000 psi at 28 days. Cylinders break at 2,900 psi at 7 days and 4,150 psi at 28 days. The concrete complies: 7-day strength typically runs roughly 65–70% of 28-day strength, so 2,900 psi at 7 days was on track, and the 28-day result is the acceptance criterion.
Reading Defects Backwards to Their Cause
Defect Appearance Usual cause
Plastic shrinkage cracking Short, random, parallel cracks appearing within hours Surface evaporation outrunning bleed water — hot, dry, windy conditions
Crazing Fine, shallow, map-like network Surface dried too fast; overworking or wetting the surface during finishing
Dusting Powdery surface that will not stop shedding Finishing while bleed water was still present; working water into the surface; poor curing
Scaling Surface flaking off in patches Freeze-thaw damage from inadequate air entrainment; deicing chemicals
Delamination Hollow-sounding, separated surface layer Sealing the surface with a steel trowel too early, trapping bleed water and air beneath
Honeycombing Voids exposing coarse aggregate on formed faces Inadequate consolidation; segregation; oversized aggregate for the form
Random cracking across panels Cracks ignoring the joints Joints cut too late, spaced too far apart, or too shallow
Notice how many of these trace to finishing too early . Bleed water must rise and evaporate before final floating and troweling; a crew that closes the surface while water is still underneath produces dusting or delamination almost every time. This is also why exterior air-entrained flatwork gets a broom or float finish rather than a hard steel trowel.
Exam tip: the exam presents a defect and asks for the cause. Sort by timing. Cracks in the first hours point to evaporation. Surface texture failures point to finishing. Flaking in service points to air entrainment. Cracks ignoring the joint pattern point to jointing depth, spacing, or timing.