Study guide

11.1 Sitework: Surveying, Excavation & Grading

Arizona General Contractor Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Introduction & Exam Overview

1.1 Current Exam Facts 1.2 The Arizona Contractor Licensing Path 1.3 How to Use This Guide & Study Plan

2 Chapter 2: Arizona ROC & Licensing Law

2.1 The Arizona Registrar of Contractors 2.2 License Classifications 2.3 Qualifying Party & Experience Requirements 2.4 Application, Fees, Bond & Background Check 2.5 License Bonds, Cash Deposits & Bond Claims 2.6 Unlicensed Contracting: Penalties & Lost Remedies 2.7 Advertising Rules, Contract Disclosures & Workmanship Standards

3 Chapter 3: The Exams — SRE, Trade & NASCLA

3.1 The Statutes & Rules Exam (SRE) 3.2 The PSI Trade Exam 3.3 The NASCLA Commercial General Building Exam Option

4 Chapter 4: License Maintenance, Recovery Fund & Discipline

4.1 License Renewal & Continuing Education 4.2 The Residential Contractors' Recovery Fund 4.3 ROC Disciplinary Actions & Penalties

5 Chapter 5: Contract Law & Disputes

5.1 Arizona Contract Fundamentals 5.2 Construction Contract Terms & Provisions 5.3 Change Orders & Modifications 5.4 Dispute Resolution & ROC Complaints 5.5 The Arizona Prompt Payment Act

6 Chapter 6: Liens, Bonds & Insurance

6.1 Arizona Mechanics' Lien Law Overview 6.2 Lien Notices, Recording & Deadlines 6.3 Contract Bonds: Bid, Performance & Payment 6.4 Insurance Requirements

7 Chapter 7: Financial Management & Taxes

7.1 Accounting & Financial Statements 7.2 Estimating, Bidding & Markup 7.3 Taxes & Payroll

8 Chapter 8: Project Management

8.1 Scheduling & the Critical Path Method 8.2 Supervision, Subcontractors & Quality Control 8.3 Project Documentation & Closeout

9 Chapter 9: Safety & OSHA

9.1 OSHA Construction Standards Overview 9.2 Fall Protection, Scaffolds & Ladders 9.3 Excavation, Trenching & Electrical Safety 9.4 Heat Illness Prevention & Arizona Job-Site Hazards

10 Chapter 10: Building Codes, Permits & Plan Reading

10.1 IRC 2018 & IBC 2018 Fundamentals 10.2 Permits, Plan Review & Inspections 10.3 Energy Code & Accessibility 10.4 Reading Construction Drawings & Specifications 10.5 Means of Egress & Fire-Resistance-Rated Construction

11 Chapter 11: Sitework, Concrete & Masonry

11.1 Sitework: Surveying, Excavation & Grading 11.2 Concrete: Formwork, Reinforcement & Placing 11.3 Masonry: Brick, Block & Mortar 11.4 Soils, Compaction & Earthwork Testing 11.5 Concrete Materials & Mix Design 11.6 Concrete Curing, Joints, Testing & Defects 11.7 Masonry Reinforcement, Grouting & Wall Systems

12 Chapter 12: Carpentry, Metals & Building Envelope

12.1 Carpentry & Framing 12.2 Metals & Metal Framing 12.3 Thermal & Moisture Protection 12.4 Doors, Windows & Finishes 12.5 Engineered Wood, Trusses & Connectors 12.6 Structural Steel Erection & Connections 12.7 Steel Joists, Girders & Metal Deck

13 Chapter 13: Roofing, Waterproofing & Interior Finishes

13.1 Roofing Systems 13.2 Waterproofing, Flashing & Sealants 13.3 Interior Finishes: Gypsum, Stucco, Flooring & Paint

14 Chapter 14: Building Systems for the General Contractor

14.1 Mechanical & Plumbing Systems 14.2 Electrical Systems & Temporary Power

11.1 Sitework: Surveying, Excavation & Grading

Key Takeaways Explain This Topic AI

The B-1/B-2 commercial general building trade exam devotes 9 of 100 items to Sitework.

OSHA 29 CFR 1926 Subpart P requires a competent person to inspect every excavation daily and after rain; trenches 5 feet or deeper require sloping, shoring, or shielding.

Type A soils are the most stable (cohesive, unconfined compressive strength at least 1.5 tsf); Type C is the least stable (gravel, sand, submerged soil) and drives the flattest sloping ratio.

Benchmarks preserve vertical control throughout the job and must be protected from disturbance; batter boards transfer layout lines above grade once excavation begins.

Compaction lifts are generally limited to 8 inches loose depth for cohesive soils and must be verified by field density testing against a Proctor maximum.

Last updated: August 2026

Site Layout and Surveying

Before any earth is moved, the building must be located on the lot accurately. Surveying establishes both horizontal position and vertical elevation. Two reference systems anchor the work:

Benchmarks — permanent, surveyed points of known elevation. The contractor establishes at least one onsite benchmark and protects it from disturbance for the life of the project. All vertical measurements (finish floor, grading, utilities) trace back to this benchmark.

Batter boards — temporary horizontal frames set back from the building corners, usually 3–4 feet above grade. Once footings are excavated, corner stakes are lost, so layout strings are transferred to batter boards to preserve the building line. The strings can be re-plumbed and re-measured at any time.

Setbacks are the minimum horizontal distances from property lines to the building, set by the local jurisdiction's zoning ordinance and the 2018 IBC (International Building Code) for fire separation distance. Setbacks must be verified before excavation; a misplaced footing is expensive to fix.

Quick Answer: Establish a protected benchmark for vertical control and batter boards for horizontal layout before excavating; verify setbacks against zoning and the 2018 IBC.

Excavation and Grading

Excavation removes soil to create the building footprint, footings, and utility trenches. Grading reshapes the ground surface for drainage and access. Two rough grades are common: rough grade (bulk earthwork to within 6 inches of final) and fine grade (finished elevation before placing base or slabs).

The building pad must be elevated so that surface water drains away from the foundation. The 2018 IBC requires positive drainage away from the foundation — surface water must be directed away from the building, typically with a slope of at least 1/2 inch per foot for the first 10 feet away from the foundation wall.

Soil Types and Bearing Capacity

Soil-bearing capacity determines footing width and depth. The 2018 IBC Table 1806.2 lists presumptive bearing values for common soil classes:

  • Soil Type Description Presumptive Bearing (psf)
  • Crystalline bedrock Sound, hard rock 12,000
  • Sedimentary rock Sandstone, limestone 4,000–6,000
  • Sandy gravel / gravel Coarse, well-graded 3,000–4,000
  • Sand Coarse to fine 2,000–3,000
  • Clay Silty to sandy clay 1,500–2,000
  • Organic silt / peat Unstable, compressible Not suitable — remove or engineer

When the bearing capacity is questionable or the soil is not in the IBC table, a geotechnical investigation with borings and lab testing is required.

Compaction

Compaction increases soil density and reduces future settlement. Fill placed under floors or slabs must be compacted to at least 90% of the maximum dry density determined by the Proctor test (ASTM International D698 standard, or D1557 modified). Lifts are generally limited to 8 inches loose depth for cohesive soils and 12 inches for granular soils. Each lift is tested before the next is placed. Field density is checked with a nuclear gauge or sand cone.

Trenching for Utilities

Utility trenches carry water, sewer, gas, electric, and communication lines. Trench bottom must be firm and uniform; soft spots are over-excavated and backfilled with compacted granular material. Bedding (sand or crushed stone) cushions the pipe. Minimum cover depths are specified by code and utility — typically 12 inches for electric and 18–24 inches for water and gas, but local jurisdictions may require more.

Excavation Safety: OSHA 29 CFR 1926 Subpart P

Trenching is one of construction's deadliest operations. OSHA (Occupational Safety and Health Administration) 29 CFR Part 1926 Subpart P governs excavations and requires:

Competent person — someone capable of identifying existing and predictable hazards and authorized to stop work. The competent person inspects every excavation daily and after every rainstorm or hazard-increasing event.

Protection for trenches 5 feet or deeper — one of three systems:

Sloping — cutting the trench walls back at a safe angle. Maximum allowable slopes: 0.75H:1V (53°) for Type A; 1H:1V (45°) for Type B; 1.5H:1V (34°) for Type C.

Shoring — a support system such as hydraulic cylinders, screw jacks, or timber shoring that braces the trench walls.

Shielding — a trench box that protects workers from cave-ins but does not prevent wall collapse.

Spoils, equipment, and material must be kept at least 2 feet from the trench edge to prevent surcharge loads from collapsing the wall.

Egress — a ladder, ramp, or stairway within 25 feet of every worker in trenches 4 feet or deeper.

OSHA Soil Classification for Excavations

  • Type Description Unconfined Compressive Strength Max Slope (H:V)
  • A Cohesive, stable (clay, hardpan, loam above water table) At least 1.5 tsf 0.75H:1V (53°)
  • B Less cohesive (angular gravel, silt, disturbed Type A) 0.5–1.5 tsf 1H:1V (45°)
  • C Unstable (gravel, sand, submerged soil, rock) Below 0.5 tsf 1.5H:1V (34°)

Quick Answer: A trench 5 feet or deeper requires sloping, shoring, or shielding, and a competent person must inspect it daily and after rain.

Erosion Control and Site Drainage

Erosion control keeps sediment on site. A Stormwater Pollution Prevention Plan (SWPPP) is required for projects disturbing one acre or more under the EPA Construction General Permit. Common best management practices (BMPs) include silt fence, inlet protection, stabilized construction entrances, and temporary seeding. Site drainage manages both surface and subsurface water. Surface drainage uses grading to direct runoff away from the foundation. Subsurface drainage uses footing drains (perforated pipe at footing level, surrounded by washed stone and filter fabric) to carry groundwater away from the foundation wall.

  • Trench Protection Systems Comparison TRENCH PROTECTION SYSTEMS -- OSHA 29 CFR 1926 Subpart P
  • Required for trenches 5 feet or deeper

SLOPING SHORING SHIELDING

  • /| |==| |==|
  • / | | | | |
  • / | |==| | |
  • / | | | |==|
  • ---+------- |--+------- |--+-------
  • | trench | | trench | | trench
  • | floor | | floor | | floor
  • Type A: 0.75H:1V (53°) Hydraulic or Trench box
  • Type B: 1H:1V (45°) timber shoring (protects workers;
  • Type C: 1.5H:1V (34°) braces walls walls may still fail)
  • Spoils/equipment: 2+ ft from trench edge
  • Egress: ladder within 25 ft of every worker (trenches 4+ ft deep)