Study guide

19.2 CCTV Inspection, Condition Assessment & FOG Control

Arizona Water/Wastewater Operator Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Arizona Regulatory Framework & ADEQ Certification

1.1 ADEQ Operator Certification Rules & Grade Structure 1.2 Facility Classification & Operator in Direct Responsible Charge (ODRC) 1.3 Arizona Aquifer Protection Permit (APP) Program & BADCT 1.4 AZPDES Surface Water Discharges & Arizona Reclaimed Water Standards 1.5 The WPI Need-to-Know Criteria: What Is Actually on Your Exam

2 Chapter 2: Federal Drinking Water & Clean Water Act Compliance

2.1 Safe Drinking Water Act (SDWA) Primary & Secondary MCLs 2.2 Surface Water Treatment Rules & Revised Total Coliform Rule (RTCR) 2.3 Stage 1 & Stage 2 Disinfectants/Disinfection Byproducts Rules (D/DBPR)

3 Chapter 3: Source Water Assessment, Wells & Watershed Protection

3.1 Groundwater Sources, Well Components & Water Level Measurement 3.2 Surface Water Sources, Intakes & Reservoir Management 3.3 Watershed Management, Contamination Sources & Public Education 3.4 Pretreatment: Aeration, Presedimentation & Algae Control

4 Chapter 4: Source Water Quality, Coagulation & Flocculation

4.1 Arizona Source Water Quality & Arid Climate Challenges 4.2 Coagulation Chemistry, Coagulants & Jar Testing 4.3 Flocculation Basin Design & Process Control 4.4 Sedimentation Basins, Clarifiers & Solids Contact Units

5 Chapter 5: Filtration Systems & Advanced Separation

5.1 Granular Media Filtration Principles & Media Types 5.2 Filter Backwash Operations, Ripening & Filter-to-Waste 5.3 Membrane Filtration & Reverse Osmosis Desalination 5.4 Ion Exchange Softening, Arsenic Removal & GAC Adsorption

6 Chapter 6: Drinking Water Disinfection & Chemical Oxidation

6.1 Chlorine Chemistry & Break-Point Chlorination 6.2 The CT Disinfection Concept & Basin Hydraulics 6.3 Alternative Disinfectants: Chloramines, Ozone, UV & Chlorine Dioxide

7 Chapter 7: Specialized Drinking Water Treatment & Chemical Conditioning

7.1 Iron & Manganese Removal 7.2 Fluoridation: Chemicals, Dosage & Safety 7.3 Corrosion Control, Saturation Indices & the Lead and Copper Rule 7.4 Water Treatment Plant Residuals Handling & Disposal

8 Chapter 8: Water Treatment Plant Equipment Operation & Maintenance

8.1 Raw Water Intake, Screening & Pumping Equipment 8.2 Chemical Feed Equipment, Storage & Metering 8.3 Instrumentation, Online Analyzers, SCADA & Calibration 8.4 Valves, Motors, Auxiliary Systems & Maintenance Programs

9 Chapter 9: Wastewater Preliminary, Primary & Biological Treatment Principles

9.1 Wastewater Characteristics & Preliminary Treatment 9.2 Primary Clarification Design & Settling Mechanics 9.3 Biological Treatment Kinetics & Microbiology

10 Chapter 10: Activated Sludge Processes & Nutrient Removal

10.1 Activated Sludge Configurations & Operational Mass Balance 10.2 Process Control Parameters, Settleability & Troubleshooting 10.3 Biological Nutrient Removal: Nitrification, Denitrification & Phosphorus Removal

11 Chapter 11: Fixed-Film, Lagoon & Advanced Secondary Processes

11.1 Trickling Filters & Attached Growth Fundamentals 11.2 Rotating Biological Contactors & Hybrid Processes 11.3 Stabilization Ponds & Lagoon Systems 11.4 Membrane Bioreactors

12 Chapter 12: Tertiary Treatment, Wastewater Disinfection & Effluent Management

12.1 Tertiary Filtration & Advanced Effluent Polishing 12.2 Wastewater Chlorination & Dechlorination 12.3 Ultraviolet & Ozone Disinfection of Wastewater 12.4 Effluent Disposal, Reclaimed Water Reuse & Permit Compliance

13 Chapter 13: Residuals Management & Sludge Processing

13.1 Sludge Thickening & Digestion Processes 13.2 Sludge Dewatering Technologies & Drying Beds 13.3 EPA Part 503 Biosolids Rules & Arizona Beneficial Use

14 Chapter 14: Wastewater Plant Equipment Operation & Maintenance

14.1 Preliminary & Primary Treatment Equipment 14.2 Aeration Systems, Blowers, Diffusers & Dissolved Oxygen Control 14.3 Wastewater Pumps, Mixers & Chemical Dosing Equipment 14.4 Electrical Systems, Online Analyzers & Auxiliary Power

15 Chapter 15: Water Distribution Infrastructure & Hydraulic Management

15.1 Water Main Materials, Fittings & Appurtenances 15.2 Water Storage, Pressure Management & Water Age 15.3 Cross-Connection Control & Backflow Prevention 15.4 Main Maintenance, Unidirectional Flushing & Leak Detection 15.5 Distribution Hydraulics, Head Loss & C-Factor 15.6 System Mapping, GIS, Plans & Distribution SCADA

16 Chapter 16: Water Main Installation, Repair & Disinfection

16.1 Main & Service Line Installation, Tapping & Thrust Restraint 16.2 New Construction Inspection, Pressure Testing & Utility Locating 16.3 Disinfection of Mains, Storage Facilities & Repaired Components 16.4 Booster Stations, Meters & Storage Facility Inspection

17 Chapter 17: Distribution Water Quality Management & Field Testing

17.1 Distribution Chemical Feed, Dosage Adjustment & Booster Chlorination 17.2 Distribution Sampling Programs & Field Analyses 17.3 Chemical Transport, Storage & Handling in Distribution Operations 17.4 Interpreting Water Quality Data, Complaints & Nitrification Control

18 Chapter 18: Wastewater Collection Systems & Lift Stations

18.1 Gravity Sewer Design, Piping Materials & Manholes 18.2 Inflow & Infiltration (I&I) Assessment & Pipeline Rehabilitation 18.3 Wastewater Lift Stations, Pump Types & Force Mains 18.4 Hydrogen Sulfide Corrosion, Odor Control & Line Cleaning 18.5 Excavation, Heavy Equipment & Surface Restoration

19 Chapter 19: Collection System Cleaning, Inspection & Rehabilitation

19.1 Hydraulic Cleaning, Rodding & Blockage Removal 19.2 CCTV Inspection, Condition Assessment & FOG Control 19.3 Trenchless Rehabilitation: CIPP, Pipe Bursting & Lining 19.4 SSO Response, Flow Monitoring & Capacity Assurance

20 Chapter 20: Laboratory Testing, Quality Control & Monitoring

20.1 Drinking Water Analytical Methods & Compliance Testing 20.2 Wastewater Laboratory Analytics & Process Control Tests 20.3 Sampling Protocols, Chain of Custody & Laboratory QA/QC 20.4 Emerging Contaminants, PFAS & Advanced Analytical Methods

21 Chapter 21: Utility Safety Programs & Emergency Preparedness

21.1 Lockout/Tagout, Electrical Safety & Arc Flash 21.2 Personal Protective Equipment, Fall Protection & Bloodborne Pathogens 21.3 Traffic Control & Work Zone Safety 21.4 Emergency Response Planning & Disaster Recovery 21.5 Heat Illness Prevention, Respiratory Protection & Hearing Conservation

22 Chapter 22: Security, Administration & Utility Management

22.1 Facility Security, Vulnerability Assessment & Cybersecurity 22.2 Recordkeeping, Standard Operating Procedures & Regulatory Reporting 22.3 Budgets, Procurement, Cost Analysis & Capital Improvement Planning 22.4 Asset Management, Energy Optimization & Water Loss Control 22.5 Supervision, Training, Customer Service & Public Communication

23 Chapter 23: Applied Operator Mathematics, Pumping Hydraulics & Utility Safety

23.1 Chemical Feed Calculations & Dosage Problem Solving 23.2 Geometric Volumes, Hydraulic Loading & Detention Time Math 23.3 Pumping Mechanics, System Head & Horsepower Calculations 23.4 Plant Safety: Confined Spaces, Chemical Hazards & OSHA Standards 23.5 Unit Conversions & Using the Supplied Formula/Conversion Table 23.6 Percent Removal, Process Efficiency & Solution Blending

19.2 CCTV Inspection, Condition Assessment & FOG Control

Key Takeaways Explain This Topic AI

PACP provides a standardized defect coding system so that condition ratings are comparable between inspectors, contractors, and years.

Structural defects such as cracks, fractures, and deformation are coded separately from operation and maintenance defects such as roots, deposits, and grease.

Smoke testing finds inflow sources including illegal downspout and area drain connections, while dye testing confirms a specific suspected connection.

Grease interceptors work by retention time and cooling that allow FOG to separate, so an undersized or unmaintained interceptor passes grease straight through.

The 25 percent rule requires a grease interceptor to be pumped when the combined floating grease and settled solids reach one quarter of the working depth.

Last updated: September 2026

19.2 CCTV Inspection, Condition Assessment & FOG Control

You cannot manage what you have not seen. Closed-circuit television inspection converts a buried pipe into a documented, coded, and rankable asset.

CCTV Inspection

A camera is transported through the pipe on a self-propelled tractor (mainline) or a push camera (laterals and small diameter), transmitting video with distance measurement to a recording van.

  • Feature Purpose
  • Pan-and-tilt head Look directly at a defect and up a lateral rather than only straight ahead
  • Zoom Detail on distant defects
  • Footage counter Locates the defect precisely for excavation or spot repair
  • Lateral launch Deploys a secondary camera up a service lateral from the mainline
  • Sonar Profiles the submerged portion in surcharged lines
  • Laser profiling Measures ovality and deformation quantitatively
  • Zoom camera (manhole-deployed) Rapid screening from the manhole without entering the pipe

The line must be cleaned before inspection. A camera driving through grease and debris documents the debris, not the pipe.

PACP Defect Coding

The Pipeline Assessment Certification Program (PACP) , developed by NASSCO, is the industry-standard coding system. Its value is consistency : a defect coded by one certified inspector means the same thing as the same code from a different inspector in a different year, which is what makes condition data usable for trending and for capital planning.

PACP separates defects into two families, and the distinction drives the response:

Category Examples Response

Structural Cracks, fractures, broken pipe, holes, deformation, collapse, joint offsets, surface damage Rehabilitation or replacement

Operation and maintenance (O&M) Roots, deposits (attached, settled), grease, infiltration, obstructions Cleaning, root control, source control

Defects are graded 1 (minor) through 5 (most severe) , and a grade 5 structural defect indicates imminent or actual collapse . Segment scores derived from the individual defect grades allow the utility to rank hundreds of reaches by condition and build a defensible rehabilitation priority list.

Important

The structural versus O&M distinction is the practical point. Cleaning a reach every six months because it fills with roots treats the symptom; the roots are entering through a structural joint defect, and lining the pipe eliminates both. Conversely, rehabilitating a structurally sound pipe that simply accumulates grease from an upstream restaurant wastes capital that source control would have solved.

Smoke Testing

Non-toxic smoke is blown into a sewer segment with a blower at a manhole. Smoke escapes wherever there is an opening to the surface.

What it finds:

  • Illegal inflow connections : roof downspouts, area and yard drains, foundation drains, sump pumps
  • Broken or missing cleanout caps
  • Defective manhole covers and frames
  • Cracked laterals and pipe defects near the surface
  • Dry or missing plumbing traps inside buildings — smoke entering a home indicates a real sewer gas pathway

Practical requirements : notify residents and the fire department in advance, work when the ground is relatively dry (saturated soil blocks smoke), photograph and log every finding with an address, and be prepared to explain to alarmed residents that the smoke is non-toxic.

Limitation : smoke testing finds inflow — direct surface connections — but does not find infiltration , which is groundwater entering through defects below the water table.

Dye Testing

Fluorescent dye is introduced at a specific fixture, downspout, drain, or surface feature, and downstream manholes are observed for the color.

Dye testing confirms one suspected connection , whereas smoke testing screens broadly . The two are complementary: smoke testing generates a list of suspect locations, and dye testing proves the specific connection before the utility asks a property owner to disconnect it.

Other Inspection Methods

Method Application

Acoustic inspection Rapid screening; sound transmitted between manholes indicates whether a blockage is developing. Cheap and fast, used to prioritize CCTV

Manhole inspection Frame and cover, chimney, corbel, barrel, bench and invert, steps, and evidence of surcharge — the "grease ring" high-water mark

  • Visual/surface inspection Depressions, odors, standing water, vegetation anomalies over the alignment
  • Flow monitoring Depth and velocity meters quantifying wet-weather response
  • Drone and multi-sensor platforms Large-diameter and difficult-access inspection

Manhole inspection deserves attention because manholes are a major inflow pathway. A vented or perforated cover in a street that ponds accepts enormous inflow during a storm, and defective frame seals and deteriorated chimneys are among the most cost-effective inflow repairs available.

Fats, Oils, and Grease Control

FOG is the leading cause of sanitary sewer blockages nationally. Warm grease flows freely; as it cools it congeals on the pipe crown and walls, building up until it forms a dam that catches everything else.

Grease Interceptors and Traps

  • Type Location Capacity
  • Under-sink grease trap Inside, near the fixture Small; frequent cleaning
  • In-ground grease interceptor Outside, buried Large; the standard for food service
  • Automatic grease removal unit Inside Mechanically skims

How they work : wastewater enters and slows, giving time for the grease to cool and float and for solids to settle , so that relatively clear water is drawn from the middle and passes on. Everything about their performance depends on retention time .

Why they fail:

  • Undersized for the flow — the water passes through too fast to separate
  • Not maintained — a full interceptor has no separation volume left

Hot water discharge — dishwashers and high-temperature sanitizers keep grease liquid so it passes straight through

  • Emulsifiers — detergents, degreasers, and additives keep grease suspended
  • Garbage disposals — food solids overwhelm the settling volume

Important

The 25 percent rule is the standard maintenance trigger: an interceptor must be pumped when the combined thickness of the floating grease layer and the settled solids layer reaches 25 percent of the total working depth . Beyond that point the effective retention volume has shrunk enough that separation efficiency falls sharply. Many ordinances also impose a maximum interval, commonly 90 days, regardless of measured depth.

Program Elements

An effective FOG program combines an ordinance requiring interceptors at food service establishments, permitting and inspection , manifest tracking of pumping records , enforcement with escalating penalties, public education on residential grease disposal, and targeted cleaning of the sewer reaches downstream of known FOG-generating clusters. Correlating blockage history with food service locations in GIS is how utilities identify where enforcement will pay.