Study guide

16.2 New Construction Inspection, Pressure Testing & Utility Locating

Arizona Water/Wastewater Operator Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Arizona Regulatory Framework & ADEQ Certification

1.1 ADEQ Operator Certification Rules & Grade Structure 1.2 Facility Classification & Operator in Direct Responsible Charge (ODRC) 1.3 Arizona Aquifer Protection Permit (APP) Program & BADCT 1.4 AZPDES Surface Water Discharges & Arizona Reclaimed Water Standards 1.5 The WPI Need-to-Know Criteria: What Is Actually on Your Exam

2 Chapter 2: Federal Drinking Water & Clean Water Act Compliance

2.1 Safe Drinking Water Act (SDWA) Primary & Secondary MCLs 2.2 Surface Water Treatment Rules & Revised Total Coliform Rule (RTCR) 2.3 Stage 1 & Stage 2 Disinfectants/Disinfection Byproducts Rules (D/DBPR)

3 Chapter 3: Source Water Assessment, Wells & Watershed Protection

3.1 Groundwater Sources, Well Components & Water Level Measurement 3.2 Surface Water Sources, Intakes & Reservoir Management 3.3 Watershed Management, Contamination Sources & Public Education 3.4 Pretreatment: Aeration, Presedimentation & Algae Control

4 Chapter 4: Source Water Quality, Coagulation & Flocculation

4.1 Arizona Source Water Quality & Arid Climate Challenges 4.2 Coagulation Chemistry, Coagulants & Jar Testing 4.3 Flocculation Basin Design & Process Control 4.4 Sedimentation Basins, Clarifiers & Solids Contact Units

5 Chapter 5: Filtration Systems & Advanced Separation

5.1 Granular Media Filtration Principles & Media Types 5.2 Filter Backwash Operations, Ripening & Filter-to-Waste 5.3 Membrane Filtration & Reverse Osmosis Desalination 5.4 Ion Exchange Softening, Arsenic Removal & GAC Adsorption

6 Chapter 6: Drinking Water Disinfection & Chemical Oxidation

6.1 Chlorine Chemistry & Break-Point Chlorination 6.2 The CT Disinfection Concept & Basin Hydraulics 6.3 Alternative Disinfectants: Chloramines, Ozone, UV & Chlorine Dioxide

7 Chapter 7: Specialized Drinking Water Treatment & Chemical Conditioning

7.1 Iron & Manganese Removal 7.2 Fluoridation: Chemicals, Dosage & Safety 7.3 Corrosion Control, Saturation Indices & the Lead and Copper Rule 7.4 Water Treatment Plant Residuals Handling & Disposal

8 Chapter 8: Water Treatment Plant Equipment Operation & Maintenance

8.1 Raw Water Intake, Screening & Pumping Equipment 8.2 Chemical Feed Equipment, Storage & Metering 8.3 Instrumentation, Online Analyzers, SCADA & Calibration 8.4 Valves, Motors, Auxiliary Systems & Maintenance Programs

9 Chapter 9: Wastewater Preliminary, Primary & Biological Treatment Principles

9.1 Wastewater Characteristics & Preliminary Treatment 9.2 Primary Clarification Design & Settling Mechanics 9.3 Biological Treatment Kinetics & Microbiology

10 Chapter 10: Activated Sludge Processes & Nutrient Removal

10.1 Activated Sludge Configurations & Operational Mass Balance 10.2 Process Control Parameters, Settleability & Troubleshooting 10.3 Biological Nutrient Removal: Nitrification, Denitrification & Phosphorus Removal

11 Chapter 11: Fixed-Film, Lagoon & Advanced Secondary Processes

11.1 Trickling Filters & Attached Growth Fundamentals 11.2 Rotating Biological Contactors & Hybrid Processes 11.3 Stabilization Ponds & Lagoon Systems 11.4 Membrane Bioreactors

12 Chapter 12: Tertiary Treatment, Wastewater Disinfection & Effluent Management

12.1 Tertiary Filtration & Advanced Effluent Polishing 12.2 Wastewater Chlorination & Dechlorination 12.3 Ultraviolet & Ozone Disinfection of Wastewater 12.4 Effluent Disposal, Reclaimed Water Reuse & Permit Compliance

13 Chapter 13: Residuals Management & Sludge Processing

13.1 Sludge Thickening & Digestion Processes 13.2 Sludge Dewatering Technologies & Drying Beds 13.3 EPA Part 503 Biosolids Rules & Arizona Beneficial Use

14 Chapter 14: Wastewater Plant Equipment Operation & Maintenance

14.1 Preliminary & Primary Treatment Equipment 14.2 Aeration Systems, Blowers, Diffusers & Dissolved Oxygen Control 14.3 Wastewater Pumps, Mixers & Chemical Dosing Equipment 14.4 Electrical Systems, Online Analyzers & Auxiliary Power

15 Chapter 15: Water Distribution Infrastructure & Hydraulic Management

15.1 Water Main Materials, Fittings & Appurtenances 15.2 Water Storage, Pressure Management & Water Age 15.3 Cross-Connection Control & Backflow Prevention 15.4 Main Maintenance, Unidirectional Flushing & Leak Detection 15.5 Distribution Hydraulics, Head Loss & C-Factor 15.6 System Mapping, GIS, Plans & Distribution SCADA

16 Chapter 16: Water Main Installation, Repair & Disinfection

16.1 Main & Service Line Installation, Tapping & Thrust Restraint 16.2 New Construction Inspection, Pressure Testing & Utility Locating 16.3 Disinfection of Mains, Storage Facilities & Repaired Components 16.4 Booster Stations, Meters & Storage Facility Inspection

17 Chapter 17: Distribution Water Quality Management & Field Testing

17.1 Distribution Chemical Feed, Dosage Adjustment & Booster Chlorination 17.2 Distribution Sampling Programs & Field Analyses 17.3 Chemical Transport, Storage & Handling in Distribution Operations 17.4 Interpreting Water Quality Data, Complaints & Nitrification Control

18 Chapter 18: Wastewater Collection Systems & Lift Stations

18.1 Gravity Sewer Design, Piping Materials & Manholes 18.2 Inflow & Infiltration (I&I) Assessment & Pipeline Rehabilitation 18.3 Wastewater Lift Stations, Pump Types & Force Mains 18.4 Hydrogen Sulfide Corrosion, Odor Control & Line Cleaning 18.5 Excavation, Heavy Equipment & Surface Restoration

19 Chapter 19: Collection System Cleaning, Inspection & Rehabilitation

19.1 Hydraulic Cleaning, Rodding & Blockage Removal 19.2 CCTV Inspection, Condition Assessment & FOG Control 19.3 Trenchless Rehabilitation: CIPP, Pipe Bursting & Lining 19.4 SSO Response, Flow Monitoring & Capacity Assurance

20 Chapter 20: Laboratory Testing, Quality Control & Monitoring

20.1 Drinking Water Analytical Methods & Compliance Testing 20.2 Wastewater Laboratory Analytics & Process Control Tests 20.3 Sampling Protocols, Chain of Custody & Laboratory QA/QC 20.4 Emerging Contaminants, PFAS & Advanced Analytical Methods

21 Chapter 21: Utility Safety Programs & Emergency Preparedness

21.1 Lockout/Tagout, Electrical Safety & Arc Flash 21.2 Personal Protective Equipment, Fall Protection & Bloodborne Pathogens 21.3 Traffic Control & Work Zone Safety 21.4 Emergency Response Planning & Disaster Recovery 21.5 Heat Illness Prevention, Respiratory Protection & Hearing Conservation

22 Chapter 22: Security, Administration & Utility Management

22.1 Facility Security, Vulnerability Assessment & Cybersecurity 22.2 Recordkeeping, Standard Operating Procedures & Regulatory Reporting 22.3 Budgets, Procurement, Cost Analysis & Capital Improvement Planning 22.4 Asset Management, Energy Optimization & Water Loss Control 22.5 Supervision, Training, Customer Service & Public Communication

23 Chapter 23: Applied Operator Mathematics, Pumping Hydraulics & Utility Safety

23.1 Chemical Feed Calculations & Dosage Problem Solving 23.2 Geometric Volumes, Hydraulic Loading & Detention Time Math 23.3 Pumping Mechanics, System Head & Horsepower Calculations 23.4 Plant Safety: Confined Spaces, Chemical Hazards & OSHA Standards 23.5 Unit Conversions & Using the Supplied Formula/Conversion Table 23.6 Percent Removal, Process Efficiency & Solution Blending

16.2 New Construction Inspection, Pressure Testing & Utility Locating

Key Takeaways Explain This Topic AI

Hydrostatic pressure testing verifies joint integrity at a pressure above working pressure, and allowable leakage is calculated from pipe length, diameter, and test pressure rather than assumed to be zero.

One-call notification before excavation is a legal requirement, and the marking color code is a national standard that operators must know.

White is the pre-marking color used by the excavator to define the dig area before locates are requested.

Tracer wire or detectable tape is required with non-metallic pipe, because PVC and HDPE cannot be found with electromagnetic locating equipment.

Potholing or hydro-excavation to visually confirm a utility is the only way to positively verify location before mechanical excavation near a marked line.

Last updated: September 2026

16.2 New Construction Inspection, Pressure Testing & Utility Locating

Two distinct duties appear together in the Need-to-Know Criteria: inspecting what contractors install and locating what is already buried . Both protect the system and, in the second case, protect people.

Construction Inspection

The utility inspector's job is to confirm that what gets buried matches the specification, because once backfilled nothing can be verified without re-excavation.

Stage Inspection points

Materials delivered Correct pipe class, material, and diameter; gaskets and fittings; damage in transit; certification

  • Trench Depth of cover, width, stable foundation, shoring in place, dewatering
  • Bedding Correct material and thickness; bell holes excavated; no rocks under the pipe
  • Pipe laying Joints fully seated and within allowable deflection; pipe clean inside; ends plugged overnight
  • Haunching Material actually worked under the haunches — verify, do not assume

Thrust restraint Blocks bearing on undisturbed soil, correct bearing area, joints not encased; restraint glands torqued

Appurtenances Valve boxes plumb and to grade; hydrants at correct height and orientation; tracer wire continuous

  • Backfill Correct material, lift thickness, compaction testing
  • Testing Pressure and leakage test, disinfection, bacteriological clearance
  • Records Redlines and as-builts submitted before acceptance

Note

Pipe ends must be plugged whenever work stops. An open main overnight admits rodents, debris, and contaminated stormwater, and this is one of the most common causes of a new main failing its bacteriological clearance and requiring re-disinfection.

Hydrostatic Pressure and Leakage Testing

New mains are tested before disinfection and before being placed in service.

Procedure:

Backfill sufficiently to restrain the pipe, leaving joints exposed where practical.

Fill slowly and expel all air through hydrants and air valves — trapped air makes the test unreliable and is a serious hazard if the line fails.

Raise to the specified test pressure, commonly 150 psi or 1.5 times working pressure .

Hold for the specified duration, typically 2 hours .

Measure the make-up water required to restore test pressure.

Allowable leakage is not zero. Gasketed joints seep slightly, and the standard formula recognizes that: L = S × D × P 148 , 000 L = \frac{S \times D \times \sqrt{P}}{148,000} L = 148 , 000 S × D × P ​ ​

where L is allowable leakage in gallons per hour, S is the number of joints, D is nominal diameter in inches, and P is test pressure in psi.

Worked example. 1,200 ft of 8-inch main in 20-ft lengths gives 60 joints, tested at 150 psi. L = 60 × 8 × 150 148 , 000 = 60 × 8 × 12.25 148 , 000 = 5 , 880 148 , 000 = 0.040 gal/hr L = \frac{60 \times 8 \times \sqrt{150}}{148,000} = \frac{60 \times 8 \times 12.25}{148,000} = \frac{5,880}{148,000} = 0.040\text{ gal/hr} L = 148 , 000 60 × 8 × 150 ​ ​ = 148 , 000 60 × 8 × 12.25 ​ = 148 , 000 5 , 880 ​ = 0.040 gal/hr

If make-up water exceeds the allowable figure, the contractor must locate and repair the leak and retest. Failing a pressure test after backfill is expensive, which is the incentive for careful joint assembly.

Underground Utility Locating

Striking a buried utility injures and kills people every year. Locating is a legal obligation, not a courtesy.

The One-Call System

Before excavating, the excavator must notify the one-call center by dialing 811 (Arizona Blue Stake) within the statutory notice period, generally at least two working days before digging. Member utilities then mark their facilities in the requested area. Marks are valid for a defined period and must be re-requested if they expire or are destroyed .

The National Color Code

  • Color Facility
  • White Proposed excavation — pre-marked by the excavator
  • Pink Temporary survey markings
  • Red Electric power lines, cables, conduit, lighting
  • Yellow Gas, oil, steam, petroleum , or other flammable material
  • Orange Communications, alarm, signal lines, cable, conduit
  • Blue Potable water
  • Purple Reclaimed water , irrigation, slurry
  • Green Sewers and drain lines

Important

Memorize this table. Blue is potable water, green is sewer, purple is reclaimed water, yellow is gas, red is electric. The color code appears on essentially every distribution and collection exam. Note that white is used by the excavator to outline the dig area before locates are requested — it is not a utility color, and confusing it with a facility marking is a common error.

Locating Methods

  • Method Works on Limitation
  • Electromagnetic (direct connect) Metallic pipe, tracer wire Requires an accessible connection point
  • Electromagnetic (inductive) Metallic pipe Less precise; couples to nearby metal
  • Sonde / transmitter Non-metallic pipe with access Requires insertion into the line
  • Ground penetrating radar Any material Performance varies with soil; clay and high moisture degrade it
  • Acoustic Pressurized water lines Best for leak location
  • Magnetic locator Valve boxes, iron, steel Finds ferrous objects only

Non-metallic pipe is the core difficulty. PVC and HDPE are invisible to electromagnetic locators, which is why tracer wire or detectable marking tape must be installed with every non-metallic main and service. Tracer wire is only useful if it is continuous, properly spliced, and brought up to an accessible test station or valve box — a broken or unterminated tracer wire is functionally the same as none.

Potholing

Marks show an approximate horizontal position, generally within a defined tolerance zone, and say nothing reliable about depth. Potholing — carefully exposing the utility, most safely by vacuum or hydro-excavation — is the only way to positively verify location and depth.

Standard practice is that mechanical excavation is prohibited within the tolerance zone on either side of a mark; work within that zone must be done by hand digging or vacuum excavation until the facility is exposed. Striking a marked line because a backhoe was used inside the tolerance zone is not an accident; it is a procedural failure.