1 Chapter 1: CHST Exam Orientation and Official Source Control
Official Sources and Credential Purpose Eligibility, Application, Fees, and Character Review Exam Format, Scoring, Beta Questions, and Blueprint Pearson VUE Scheduling, Test Day, Results, and Retakes Blueprint-Based Study Plan and Readiness
2 Chapter 2: Hazard and Risk Identification Methods, JHA, and Controls
Hierarchy of Controls and Construction Risk Logic Job Hazard Analysis and Pre-Task Planning Risk Ranking, Severity, Frequency, and Corrective Action Safety Through Design and Construction Means and Methods PPE Selection, Limitations, and Basic Monitoring Instruments Multi-Trade Coordination, Simultaneous Operations, and Interface Risk Field Observation, Documentation, and Control Verification
3 Chapter 3: High-Hazard Construction Operations I - Fall, Electrical, Excavation, Confined Space, Hot Work, Tools, and Concrete
Working at Heights: Ladders, Scaffolds, and Leading Edge Exposures Fall Protection: Arrest, Restraint, and Rescue Planning Excavation and Trenching: Soil, Protection, and Access/Egress Electrical Hazards: Temporary Power, GFCI, and LOTO Awareness Confined Space Recognition, Atmospheric Testing, and Entry Controls Hot Work: Fire Watch, Combustibles, and Permit Controls Hand and Power Tools, Powder-Actuated Tools, and Concrete Work
4 Chapter 4: High-Hazard Construction Operations II - Struck-By, Equipment, Hoisting, Rigging, Cranes, Material Handling, and Storage
Struck-By, Caught-Between, and Line-of-Fire Controls Mechanized Equipment, Mobile Equipment, and Traffic Control Hoisting, Rigging, Sling Inspection, and Load Control Crane Operations, Critical Lifts, Signaling, and Exclusion Zones Material Handling, Storage, Stacking, and Housekeeping Concrete Placement, Formwork, Rebar, and Impalement Controls Simultaneous Operations, Sequencing, and Stop-Work Decisions
5 Chapter 5: Construction Health, Environmental, Chemical, and Ergonomic Exposure Controls
Silica, Asbestos, Lead, Heavy Metals, and Dust Controls Noise, Vibration, Radiation, and Impact Exposure Control Chemical Exposure, GHS, SDS, and HazCom Field Use Heat, Cold, Extreme Climate, and Biological Hazard Controls Ergonomics, Manual Material Handling, and Work Practice Design Exposure Monitoring, PPE Limitations, and Medical Referral Triggers
6 Chapter 6: Emergency Preparedness, Incident Investigation, and Response
Emergency Action Plans, Site Mitigation, and Evacuation Fire Protection, Prevention, Hot Work, and Alarm Response Environmental Contamination, Spill Response, and Notifications Incident Command, Crisis Management, and Emergency Equipment First Aid, Medical Needs, Bloodborne Pathogens, and Universal Precautions Incident Investigation, Near Misses, Root Cause, and Corrective Action Drills, After-Action Reviews, and Return to Operations
7 Chapter 7: Safety Program Development, Implementation, and Sustainment
Site-Specific Safety Plans and Relevant Program Selection Applying Standards, Regulatory Authority, and Role Boundaries Inspections, Audits, Observations, and Corrective Action Tracking Equipment Manuals, Manufacturer Directives, and Field Compliance Risk Management, Data Gathering, Recordkeeping, and Document Control Incident Causation, Post-Incident Reporting, and Follow-Up Trends, Leading Indicators, and Program Sustainment
8 Chapter 8: Leadership, Communication, Training, and Total Worker Health
Safety Leadership, Credibility, and Field Influence Communication Strategy, Crew Briefings, and Conflict Management Training Needs, Task Analysis, and Adult Learning Delivery Toolbox Talks, Competency Verification, and Documentation Consulting Manufacturers, Suppliers, and Subject Matter Experts Confidentiality, Ethics, Document Control, and Current Information Total Worker Health, At-Risk Behavior, and Risk Reduction Activities
9 Chapter 9: Mixed CHST Construction Case Labs
Fall Protection, Scaffold, and Rescue Case Lab Excavation, Confined Space, and Atmospheric Hazard Case Lab Crane, Rigging, Equipment, and Struck-By Case Lab Hot Work, Fire, and HazCom Case Lab Silica, Noise, Heat, and Health Exposure Case Lab Incident Investigation, Program Failure, and Corrective Action Case Lab Superintendent Meeting, Training, and Stop-Work Case Lab
10 Chapter 10: Standards, References, Ethics, and Field Application
OSHA 1926 Navigation and Construction Standard Application Competent Person, Qualified Person, and Authority Boundaries Consensus Standards, Manufacturer Instructions, and Equipment Manuals BCSP Code of Ethics, Confidentiality, and Professional Conduct Exam-Style Reference Use and Best Answer Strategy
11 Chapter 11: Final Review, High-Yield Tables, and CHST Exam-Day Readiness
Blueprint Quick Reference and Domain Triage High-Yield Construction Hazard Control Tables Emergency Program Leadership and Documentation Review Final Week Practice Plan, Error Log, and Pacing Final 48 Hours, Pearson VUE Test Day, and Retake Planning
Hoisting, Rigging, Sling Inspection, and Load Control
Key Takeaways Explain This Topic AI
Rigging safety depends on knowing load weight, center of gravity, sling angle, hardware capacity (WLL), and attachment method.
Sling tension rises sharply as the horizontal angle decreases: factor 1.0 at 90 degrees, 1.155 at 60, 1.414 at 45, and 2.0 at 30 degrees.
Remove damaged or untagged slings and hardware from service immediately under 29 CFR 1926.251; do not derate by guesswork.
Tag lines control rotation but must never be wrapped around a hand or body or place a worker in the fall zone.
Last updated: June 2026
Hoisting, Rigging, Sling Inspection, and Load Control
Rigging is the connection between the lifting equipment and the load, and small errors produce large failures. The governing construction standard is 29 CFR 1926.251 , Rigging equipment for material handling , which requires that rigging be inspected before each shift and as needed during use, and that defective gear be removed from service. The CHST need not be the qualified rigger for every lift, but must recognize when the lift plan, gear condition, or work-area control is unacceptable.
Start With the Load
Before choosing rigging, determine the load weight, shape, center of gravity (CG), lift points, sharp edges, stability, and landing method . Use drawings, shipping papers, manufacturer markings, or scale tickets — guessing is not a plan. The CG matters because a load lifted off its balance point will tilt, roll, or shift suddenly. The hook should sit directly above the CG so the load lifts level.
The load path must be clear from pickup to landing. The landing area must be strong, level, and prepared with cribbing or dunnage where needed. Workers keep hands out from under the load and never place themselves between the load and a fixed object.
Sling Angle Is a Top Exam Topic
The sling angle (measured from horizontal) multiplies the tension in each leg. As the angle decreases, tension climbs even though the load weight is unchanged — a frequent trap question. Maintain angles above 30 degrees from horizontal whenever possible; many programs set 45 to 60 degrees as the working minimum.
- Sling angle (from horizontal) Tension factor per leg Effect
- 90 degrees (vertical) 1.000 Each leg carries its share of the load
- 60 degrees 1.155 About 16 percent more tension per leg
- 45 degrees 1.414 About 41 percent more tension per leg
- 30 degrees 2.000 Tension doubles per leg
Worked example: a 4,000 lb load on a two-leg bridle splits to 2,000 lb per leg in a true vertical pull. At a 30-degree angle each leg now carries 2,000 x 2.0 = 4,000 lb — so a 5,000 lb-rated sling that looked safe at 90 degrees can be overloaded. Correct it with longer slings, a spreader bar, or repositioned lift points.
Sling and Hardware Rejection Criteria
Component Remove from service when CHST concern
Synthetic web sling Cuts, burns, broken stitching, chemical/acid damage, missing tag Rated capacity cannot be verified
Wire rope sling Kinking, birdcaging, crushing, corrosion, heat, or broken wires (10 randomly distributed in one rope lay) Failure may occur under load
Alloy chain sling Stretched, gouged, cracked, distorted, heat-damaged, missing ID Damage is hard to see from a distance
Hook or shackle Bent, cracked, unreadable WLL, throat opening increased, damaged latch Hardware may release or overload
Tag and remove damaged rigging so it cannot be reused — leaving bad gear in the gang box invites later use under schedule pressure. A missing identification tag alone is a removal condition because the working load limit (WLL) can no longer be verified.
Hitch Type, Edges, and Load Control
A vertical hitch gives full rated capacity; a choker hitch reduces capacity (commonly to about 75-80 percent because of the bend at the choke point); a basket hitch can roughly double capacity only if the legs stay vertical and the load cannot slide out. Sharp edges require corner protection or pads, because a 90-degree edge can slice a synthetic sling or sharply reduce wire-rope strength. On multi-leg bridle lifts with a rigid load, do not assume the legs share equally — two legs may carry the entire load while the others only steady it.
Control movement: keep the load low during the initial test lift , pause to confirm balance, and avoid sudden starts and stops. Tag lines may control rotation, but the worker stands clear of the fall zone and never wraps the line around a hand, body, or fixed object. If a tag line creates a trip, fall, or entanglement hazard, use a different control.
Communication and the Exam
Only the designated signal person directs hoist movement — except that anyone may give an emergency stop . The operator does not move on unclear, conflicting, or casual signals. For CHST scenarios, choose the answer that verifies capacity, condition, configuration, and control . Do not accept damaged rigging, unknown load weight, workers under the load, or informal signaling; the right field action is often to pause the lift, get qualified rigging input, replace defective gear, or revise the method.
Design Factors and Qualified vs Competent
Know the vocabulary the exam tests. Slings carry a design factor (sometimes called safety factor) typically of 5 to 1 for new slings, meaning a sling rated at 2,000 lb working load limit was tested to roughly 10,000 lb breaking strength — but that margin is consumed by wear, shock loading, and shallow angles, so it is not a license to overload. A qualified rigger has a recognized degree, certificate, or extensive knowledge and training to solve rigging problems; a competent person can identify hazards and has authority to correct them.