Study guide

Crane, Rigging, Equipment, and Struck-By Case Lab

BCSP CHST Construction Health and Safety Technician Study Guide Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: CHST Exam Orientation and Official Source Control

Official Sources and Credential Purpose Eligibility, Application, Fees, and Character Review Exam Format, Scoring, Beta Questions, and Blueprint Pearson VUE Scheduling, Test Day, Results, and Retakes Blueprint-Based Study Plan and Readiness

2 Chapter 2: Hazard and Risk Identification Methods, JHA, and Controls

Hierarchy of Controls and Construction Risk Logic Job Hazard Analysis and Pre-Task Planning Risk Ranking, Severity, Frequency, and Corrective Action Safety Through Design and Construction Means and Methods PPE Selection, Limitations, and Basic Monitoring Instruments Multi-Trade Coordination, Simultaneous Operations, and Interface Risk Field Observation, Documentation, and Control Verification

3 Chapter 3: High-Hazard Construction Operations I - Fall, Electrical, Excavation, Confined Space, Hot Work, Tools, and Concrete

Working at Heights: Ladders, Scaffolds, and Leading Edge Exposures Fall Protection: Arrest, Restraint, and Rescue Planning Excavation and Trenching: Soil, Protection, and Access/Egress Electrical Hazards: Temporary Power, GFCI, and LOTO Awareness Confined Space Recognition, Atmospheric Testing, and Entry Controls Hot Work: Fire Watch, Combustibles, and Permit Controls Hand and Power Tools, Powder-Actuated Tools, and Concrete Work

4 Chapter 4: High-Hazard Construction Operations II - Struck-By, Equipment, Hoisting, Rigging, Cranes, Material Handling, and Storage

Struck-By, Caught-Between, and Line-of-Fire Controls Mechanized Equipment, Mobile Equipment, and Traffic Control Hoisting, Rigging, Sling Inspection, and Load Control Crane Operations, Critical Lifts, Signaling, and Exclusion Zones Material Handling, Storage, Stacking, and Housekeeping Concrete Placement, Formwork, Rebar, and Impalement Controls Simultaneous Operations, Sequencing, and Stop-Work Decisions

5 Chapter 5: Construction Health, Environmental, Chemical, and Ergonomic Exposure Controls

Silica, Asbestos, Lead, Heavy Metals, and Dust Controls Noise, Vibration, Radiation, and Impact Exposure Control Chemical Exposure, GHS, SDS, and HazCom Field Use Heat, Cold, Extreme Climate, and Biological Hazard Controls Ergonomics, Manual Material Handling, and Work Practice Design Exposure Monitoring, PPE Limitations, and Medical Referral Triggers

6 Chapter 6: Emergency Preparedness, Incident Investigation, and Response

Emergency Action Plans, Site Mitigation, and Evacuation Fire Protection, Prevention, Hot Work, and Alarm Response Environmental Contamination, Spill Response, and Notifications Incident Command, Crisis Management, and Emergency Equipment First Aid, Medical Needs, Bloodborne Pathogens, and Universal Precautions Incident Investigation, Near Misses, Root Cause, and Corrective Action Drills, After-Action Reviews, and Return to Operations

7 Chapter 7: Safety Program Development, Implementation, and Sustainment

Site-Specific Safety Plans and Relevant Program Selection Applying Standards, Regulatory Authority, and Role Boundaries Inspections, Audits, Observations, and Corrective Action Tracking Equipment Manuals, Manufacturer Directives, and Field Compliance Risk Management, Data Gathering, Recordkeeping, and Document Control Incident Causation, Post-Incident Reporting, and Follow-Up Trends, Leading Indicators, and Program Sustainment

8 Chapter 8: Leadership, Communication, Training, and Total Worker Health

Safety Leadership, Credibility, and Field Influence Communication Strategy, Crew Briefings, and Conflict Management Training Needs, Task Analysis, and Adult Learning Delivery Toolbox Talks, Competency Verification, and Documentation Consulting Manufacturers, Suppliers, and Subject Matter Experts Confidentiality, Ethics, Document Control, and Current Information Total Worker Health, At-Risk Behavior, and Risk Reduction Activities

9 Chapter 9: Mixed CHST Construction Case Labs

Fall Protection, Scaffold, and Rescue Case Lab Excavation, Confined Space, and Atmospheric Hazard Case Lab Crane, Rigging, Equipment, and Struck-By Case Lab Hot Work, Fire, and HazCom Case Lab Silica, Noise, Heat, and Health Exposure Case Lab Incident Investigation, Program Failure, and Corrective Action Case Lab Superintendent Meeting, Training, and Stop-Work Case Lab

10 Chapter 10: Standards, References, Ethics, and Field Application

OSHA 1926 Navigation and Construction Standard Application Competent Person, Qualified Person, and Authority Boundaries Consensus Standards, Manufacturer Instructions, and Equipment Manuals BCSP Code of Ethics, Confidentiality, and Professional Conduct Exam-Style Reference Use and Best Answer Strategy

11 Chapter 11: Final Review, High-Yield Tables, and CHST Exam-Day Readiness

Blueprint Quick Reference and Domain Triage High-Yield Construction Hazard Control Tables Emergency Program Leadership and Documentation Review Final Week Practice Plan, Error Log, and Pacing Final 48 Hours, Pearson VUE Test Day, and Retake Planning

Crane, Rigging, Equipment, and Struck-By Case Lab

Key Takeaways Explain This Topic AI

If a crane, load line or load could get within 20 feet of a power line (50 feet for lines over 350 kV up to 1,000 kV, 1926.1409), de-energize and ground it, keep that 20-foot (or 50-foot) distance with encroachment precautions, or keep the Table A distance (10 feet up to 50 kV) with those precautions (29 CFR 1926.1408).

Only one designated signal person directs a lift; the operator must stop for any signal that is unclear or for an emergency stop from anyone.

Slings must carry a legible identification tag; an unreadable or missing tag removes the sling from service until evaluated (1926.251).

Outrigger and crawler loads must bear on ground that can support them; backfilled trenches and voids cause tipover and settlement.

Struck-by is a Focus Four hazard; separating people from suspended loads, swing radius, and equipment paths prevents most incidents.

Last updated: October 2026

  • Crane, Rigging, Equipment, and Struck-By Case Lab
  • Scenario

A mechanical contractor is setting a rooftop air handling unit with a mobile crane. The unit arrived late, so the lift slid into the afternoon while concrete trucks, telehandlers, and roofers stay active nearby. The crane pad sits over a recently backfilled utility trench. The rigging crew has a spreader bar, synthetic slings, and shackles, but one sling tag is unreadable and sharp metal edges show on the load frame. Overhead, a 12 kV distribution line crosses near the boom path. Two supervisors are giving hand signals from different sides of the building.

First Priorities

The CHST should focus on high-energy struck-by, electrocution, and crush exposures. The lift must not proceed until the lift director or responsible competent person confirms the plan. Conflicting signals are an immediate stop — OSHA permits only one designated signal person , and the operator must stop for any unclear signal or for an emergency stop from anyone (1926.1419). A suspended load path over workers or active traffic is unacceptable. The unreadable sling tag and unprotected sharp edges require correction first.

A practical sequence:

Pause the lift and keep the load on the ground.

Establish and enforce swing-radius, load-path, and landing exclusion zones.

Confirm one signal person, a communication method, and stop-signal authority.

Verify load weight, crane configuration, radius, capacity, ground support, line clearance, and weather limits.

Inspect rigging; remove questionable components.

Power Lines and Ground Conditions

Under 29 CFR 1926.1408 , the employer first checks whether any part of the crane, load line or load could get within 20 feet of the line. Here it can, so the employer must choose one option: have the utility de-energize and visibly ground the line; keep 20 feet away with encroachment precautions; or keep the Table A distance for the voltage, which is 10 feet for lines up to 50 kV , with the same precautions — a planning meeting, non-conductive tag lines, an elevated warning line or barricade, and a measure such as a proximity alarm or a dedicated spotter. The crane may have ample chart capacity yet still be unsafe if the surface cannot carry outrigger loads. Recently backfilled trenches, voids, soft soil, and slopes undermine support. The plan must verify matting/cribbing, outrigger extension, level setup, and access path; a pad crossing a trench needs engineering or competent evaluation before continuing.

  • Lift factor Field question Risk if ignored
  • Load weight Is actual weight known, including rigging? Overload or failed pick
  • Radius Is radius controlled through the full path? Capacity loss during swing
  • Ground Can the surface support outrigger loads? Tipover or settlement
  • Power line Is the line de-energized, or 20 ft (or Table A 10 ft) kept with precautions? Electrocution
  • Rigging Are slings rated, tagged, edge-protected? Dropped load
  • Rigging and Equipment Controls

Rigging selection is not guesswork. Slings, shackles, hooks, and spreader bars must be rated, inspected, and compatible with hitch type and geometry. 1926.251 requires a legible identification tag stating rated capacity; a missing or unreadable tag removes the sling from service until a qualified person evaluates it. Synthetic slings need protection from sharp edges and heat, and a basket hitch with the legs not vertical reduces capacity by the sling-angle factor (a 60° leg angle yields about 86% of vertical capacity; 30° yields only 50%). Equipment traffic matters too: concrete trucks, telehandlers, and pedestrians should not share an uncontrolled route with crane setup or landing. Backing alarms, spotters, barricades, and high-visibility clothing help but do not replace physical separation.

Emergency Response, Communication, and Documentation

The lift plan should address rising wind, lost communication, line approach, a shifting load, structure contact, or a person entering the zone. Everyone needs authority to give an emergency stop. After a dropped load or struck-by event, preserve the scene when life safety allows, secure the equipment, call EMS as needed, and block restart until investigated. Resist solving a near miss by telling workers to be careful — conflicting signals are a planning failure, an over-people load path is a coordination failure, and an untagged sling is an inspection and procurement failure. The pre-lift meeting covers weight, pick/set points, configuration, roles, signal method, exclusion-zone boundaries, weather stop criteria, tag-line use, and emergency stop, and affected subcontractors get the same briefing.

Qualified Roles and Critical Lifts

Subpart CC defines the roles the exam tests. A crane operator must be certified by type and capacity through an accredited program. A qualified rigger is required whenever workers are within the fall zone hooking, unhooking, guiding, or doing initial connections. A signal person must be qualified, know the standard hand and voice signals, and understand the crane's operations and limitations. The lift director plans and supervises the lift. A critical lift — generally one exceeding a percentage of chart capacity (often 75–90%), multi-crane picks, or lifts over occupied structures — requires a written plan reviewed by a qualified person before work begins.

Exam Judgment

In struck-by and crane items, eliminate any option that keeps people in the fall zone, follows two signal sources, uses untagged rigging, or sets up on unverified ground. The correct answer keeps people out of the line of fire, confirms qualified roles, verifies capacity and clearance, and holds the load until conditions are controlled. After a delay, restart planning must reconsider changed conditions: wind, lighting, fatigue, traffic, ground disturbance, or a revised load path.