18.1 Pre-Construction & Pre-Installation Meetings and the Construction Manager's Impact on Services

California Supplemental Examination CSE

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: California Architects Practice Act & Professional Practice

1.1 Licensing, Board Authority, and Unlicensed Practice Exceptions 1.2 Mandatory Written Contracts & Required Provisions 1.3 Architect's Stamp, Signature, and Professional Liability

2 Chapter 2: Professional Conduct, Ethics & Business Entities

2.1 Rules of Professional Conduct & Disciplinary Grounds 2.2 Permissible Business Entities, Firm Names, and Filing Requirements 2.3 Copyright, Instruments of Service & Ownership of Architectural Documents

3 Chapter 3: Contractual Roles, Scope & Consultant Agreements

3.1 Standard Owner-Architect Agreements (AIA B101 / B102) & California Practice Realities 3.2 Consultant Selection, Prime-Consultant Agreements & Liability Flow-Down (AIA C401) 3.3 Project Delivery Methods & Impact of Project Funding Sources

4 Chapter 4: Risk Management, Dispute Resolution & Project Planning

4.1 Professional Standard of Care & Managing Contractual Risk and Liability 4.2 Dispute Resolution in California Practice: Mediation, Arbitration, and Litigation 4.3 Project Scheduling, Budgeting Assumptions, and Milestone Approvals

5 Chapter 5: Site Feasibility, Schematic Design & Discretionary Approvals

5.1 Site Feasibility Studies, Existing-Conditions Due Diligence & Project Impacts 5.2 Programming, Schematic Design Development & Stakeholder Engagement 5.3 Local Land-Use Control: General Plans, Zoning, Specific Plans & Local Ordinances 5.4 The Discretionary Approval Process: Use Permits, Variances, Design Review & Hearings 5.5 Entitlement Exhibits, Conditions of Approval & Leading the Approval Team

6 Chapter 6: Environmental Review & CEQA Compliance

6.1 CEQA Regulatory Framework: Lead, Responsible, and Trustee Agencies 6.2 CEQA Process: Statutory & Categorical Exemptions, Initial Studies, and (Mitigated) Negative Declarations 6.3 Environmental Impact Reports (EIR) & Official Filings (NOP, NOC, NOD, NOE)

7 Chapter 7: California Coastal Act & Specialized Regional Regulations

7.1 California Coastal Commission & Coastal Development Permits (CDP) 7.2 Local Coastal Programs (LCP), Coastal Zone Boundaries, and Appeals 7.3 Clean Air Act (CARB/AQMDs) & Clean Water Regulations (Porter-Cologne, RWQCB & SWPPP)

8 Chapter 8: State Agency Jurisdictions: DSA, HCAI & Essential Services

8.1 Division of the State Architect (DSA): Field Act & Public K-12/Community College Oversight 8.2 Department of Health Care Access and Information (HCAI): Alfred E. Alquist Act & Healthcare Facility Classification 8.3 Essential Services Buildings Seismic Safety Act (ESBSSA) & California Historical Building Code (CHBC)

9 Chapter 9: California Building Code (CBC Title 24 Part 2) Core Architecture Provisions

9.1 Occupancy Classifications, Building Heights, and Allowable Floor Areas (CBC Chapters 3 & 5) 9.2 Fire and Smoke Protection Features, Fire Barriers, and Fire-Resistance Ratings (CBC Chapter 7) 9.3 Means of Egress, Occupant Load Calculations, and Exit Separation (CBC Chapter 10) 9.4 California Health and Safety Code: Building Standards Law, State Housing Law & Health Mandates

10 Chapter 10: Accessibility Requirements: Title 24 Chapter 11B & ADA

10.1 California Accessibility Framework: CBC Chapter 11B vs Federal ADA Standards 10.2 Accessible Routes, Entrances, Parking, and Site Arrival Points 10.3 Accessible Restrooms, Signage, Scoping, and Path of Travel Alteration Thresholds

11 Chapter 11: California Site Conditions & Natural Hazards

11.1 Seismic Hazard Mapping: Alquist-Priolo Earthquake Fault Zoning Act & Liquefaction 11.2 Wildland-Urban Interface (WUI) & Fire Hazard Severity Zones (CBC Chapter 7A & CFC Part 9) 11.3 Flood Hazard Zones (FEMA/DWR) & California Wind Exposure Categories

12 Chapter 12: Energy Efficiency: California Energy Code (Title 24 Part 6)

12.1 Energy Code Compliance Approaches: Prescriptive vs Performance & Time Dependent Valuation (TDV) 12.2 Mandatory Energy Measures: Envelope, HVAC, Lighting, Solar PV & Energy Storage Systems

13 Chapter 13: Sustainability (CALGreen) & Systems Integration

13.1 CALGreen (Title 24 Part 11) Mandatory Nonresidential & Residential Green Building Measures 13.2 Life-Cycle Cost Analysis (LCCA) & Value Engineering in California Practice 13.3 Building Systems Integration: MEP Coordination, Materials Evaluation & Acoustic Control

14 Chapter 14: Construction Document Requirements & Regulatory Coordination

14.1 CD Content, Detailing & Inter-Disciplinary Coordination for Agency Approval and Bidding 14.2 Authority Having Jurisdiction (AHJ) Hierarchy, Local Amendments & Local Finding Requirements 14.3 Reconciling Conflicting Codes, Standards, and Regulatory Mandates

15 Chapter 15: Plan Check & Permitting Processes

15.1 Permitting Procedures, Plan Check Review, Agency Comment Inquiries & Approval Pathways 15.2 Phased Permitting, Deferred Approvals, Encroachment Permits & Public Right-of-Way Coordination

16 Chapter 16: California Public Contract Code & Bidding Procedures

16.1 Public Works Bidding, Competitive Bidding Thresholds & Responsive vs Responsible Bidders 16.2 Subletting and Subcontracting Fair Practices Act & Subcontractor Listing Rules (PCC §§ 4100–4114) 16.3 California Prevailing Wage Requirements, DIR Registration & Certified Payroll Records

17 Chapter 17: California Mechanics Lien Law & Payment Remedies

17.1 20-Day Preliminary Notice Requirements & Timing (Civil Code § 8200) 17.2 Mechanics Liens, Recording Deadlines & Impact of Notice of Completion (Civil Code §§ 8400–8494) 17.3 Stop Payment Notices, Payment Bonds & Design Professional Liens (Civil Code §§ 8300–8319, 9350–9566)

18 Chapter 18: Construction Administration: Pre-Construction, Submittals, Changes & Field Observation

18.1 Pre-Construction & Pre-Installation Meetings and the Construction Manager's Impact on Services 18.2 Shop Drawings, Submittals & Architect's Deferred Submittal Review and Stamp 18.3 Construction Changes: Change Orders (CO), CCDs, ASIs & DSA Category A/B CCDs 18.4 Periodic Site Observations, Field Reports & the Means-and-Methods Boundary

19 Chapter 19: Inspection, Close-Out & Post-Construction Services

19.1 Special Inspections, Testing (CBC Chapter 17) & DSA/HCAI Continuous Field Inspection 19.2 Project Close-Out, Payment Applications (G702/G703), Retainage & California Warranty/Defect Limitations (CCP §§ 337.1 & 337.15) 19.3 Post-Construction Services, Record Documents & the Warranty Period 19.4 Construction Industry Standards, Detailing & Referenced Standards

18.1 Pre-Construction & Pre-Installation Meetings and the Construction Manager's Impact on Services

Key Takeaways Explain This Topic AI

The pre-construction conference establishes the project's communication protocol, submittal and request-for-information procedures, schedule of values, payment cycle, change procedure, special inspection program, and closeout requirements before the first work is installed.

Pre-installation conferences are required by individual specification sections for risk-heavy assemblies such as roofing, waterproofing, curtain wall, fireproofing, and flooring, and manufacturers frequently condition extended warranties on holding them.

A construction manager as adviser does not hold the trade contracts — it manages schedule, cost, and coordination and typically joins the architect in certifying payment, but it cannot make the architect's design-conformance judgments — while a construction manager at risk holds the trade contracts, delivers a guaranteed maximum price, must be licensed as a contractor under Business and Professions Code Sections 7026 and 7028, and is administered by the architect as the Contractor.

Government Code Section 4526 requires state and local agencies to select architectural, engineering, and construction project management services on the basis of demonstrated competence and professional qualifications rather than price.

No construction management arrangement relieves the architect of record of the statutory observation and verified-report duties owed to the Division of the State Architect or to the Department of Health Care Access and Information.

Last updated: September 2026

Pre-Construction & Pre-Installation Meetings and the Construction Manager's Impact on Services

Two CSE items sit at the front of the construction phase: the task to participate in pre-construction and pre-installation meetings with contractors as required by the contract documents , and the knowledge statement on construction manager impact on construction administration services . Both are about establishing who talks to whom, who decides what, and what the architect's role actually is once a third party is inserted between the architect and the work.

The Pre-Construction Conference

Held after award and before mobilization, usually convened by the owner or the construction manager, with the architect, contractor, key subcontractors, consultants, the inspector of record on a Division of the State Architect or Department of Health Care Access and Information project, and the local building official where useful.

Standing agenda:

  • Topic What Gets Fixed
  • Lines of communication Who issues instructions, who may not, and how field questions travel

Request for information procedure Format, log, response time, and the rule that a request for information is not a change order

  • Submittal procedure and log Sequence, quantities, review durations, and which items are deferred submittals
  • Schedule Baseline critical path schedule submission, updates, and float ownership
  • Schedule of values Basis for the payment application and the retention calculation
  • Payment application cycle Cutoff date, certification timing, lien release forms required with each application

Change procedure Change order, construction change directive, and supplemental instruction thresholds and forms

Special inspection and testing program Statement of special inspections, who retains the special inspectors, distribution of reports

Agency protocols Inspector of record's role, verified reports, agency change-order categories, field trip requirements

Site logistics and safety Access, staging, hours, dust and stormwater controls, the contractor's exclusive responsibility for safety

Sustainability documentation CALGreen documentation, waste management plan, commissioning scope, acceptance testing

Closeout requirements Record documents, operation and maintenance manuals, warranties, training, attic stock

Minutes are distributed and become part of the project record. The architect's contribution is to state the design-conformance boundary plainly at the outset: the architect reviews submittals for general conformance with the design concept, has authority to reject nonconforming work, and does not control means, methods, sequences, or safety.

Pre-Installation Conferences

These are convened for a specific assembly, before that assembly begins, and are required by individual specification sections rather than by the general conditions. Typical triggers are roofing, air and water barriers and waterproofing, curtain wall and storefront, applied fireproofing, exterior insulation and finish systems, tile, resilient and wood flooring over concrete slabs, and elevator installation.

Attendees are the installing subcontractor's foreman, the manufacturer's technical representative, adjacent trades whose work interfaces with the assembly, the contractor's superintendent, the architect, the testing agency, and the inspector of record. The agenda covers substrate condition and acceptance, moisture and temperature limits, sequencing with adjacent trades, mockup and benchmark installation, testing (adhesion, water, moisture-vapor emission), and the manufacturer's warranty conditions.

Why this matters commercially: manufacturers routinely make an extended or system warranty contingent on holding a documented pre-installation conference and on manufacturer field inspections. Skipping the meeting can void the warranty the specification promised the owner — a foreseeable California moisture-intrusion claim.

Construction Manager as Adviser

In the adviser model the construction manager is the owner's agent and holds no trade contracts. AIA's construction-manager-as-adviser family governs: an owner–construction manager agreement, a construction-manager-as-adviser edition of the owner–architect agreement, owner–contractor agreements with each trade, and a construction-manager-as-adviser edition of the general conditions.

What changes for the architect:

Communication routing. Correspondence, requests for information, and submittals commonly flow through the construction manager, which reviews them first and forwards them to the architect.

Cost and schedule. The construction manager prepares and updates the estimate and the master schedule; the architect no longer carries those.

Payment certification. The construction manager reviews and typically signs the certificate for payment along with the architect.

Multiple prime contracts. With separate trade contracts there is no single general contractor to coordinate the trades, so coordination responsibility shifts to the construction manager — and gaps between trade scopes become the most common source of claims.

What does not change. Interpretation of the contract documents, review of submittals for conformance with the design concept, rejection of nonconforming work, and the architect's independent professional judgment remain the architect's. A construction manager cannot approve a submittal for design conformance or waive a code requirement.

Construction Manager at Risk

In the at-risk model the construction manager holds the trade contracts and carries the price risk, usually converting a preconstruction estimate into a guaranteed maximum price . It provides preconstruction services — estimating, constructability review, phasing, early trade packages, long-lead procurement — and then becomes the Contractor for construction administration purposes.

California specifics:

Because the at-risk construction manager contracts for and performs construction , it must hold a Contractors State License Board license under Business and Professions Code Sections 7026 and 7028. An adviser providing only management services for a fee does not.

Government Code Section 4526 requires state and local agencies to select private architectural, engineering, and construction project management firms on the basis of demonstrated competence and professional qualifications, not low bid.

Public entities have specific statutory authority for alternative delivery — design-build authority for local agencies and school districts, and lease-leaseback for school districts — each with its own procurement rules. The architect should confirm which statute authorizes the delivery model before assuming the roles in the contract documents are enforceable.

Early trade packages and a guaranteed maximum price developed before drawings are complete create phased permitting and deferred-approval coordination, particularly on Division of the State Architect and Department of Health Care Access and Information projects where incremental approvals must be obtained before the corresponding work proceeds.

  • CM as Adviser CM at Risk
  • Holds trade contracts No — owner does Yes
  • Contractor's license required Generally no Yes
  • Price commitment None; owner carries risk Guaranteed maximum price

Architect's counterpart in the field Multiple prime contractors plus the CM The construction manager, acting as Contractor

  • Payment certification CM and architect Architect
  • Design conformance judgment Architect Architect
  • CSE Exam Traps & Practical Takeaways

Trap 1: Letting the construction manager decide design conformance. Routing submittals through a construction manager is a logistics change, not a transfer of professional judgment.

Trap 2: Assuming an at-risk construction manager needs no license. It holds trade contracts and performs construction, so it must be licensed.

Trap 3: Skipping a specified pre-installation conference. It is a contract requirement and often a manufacturer's warranty precondition.

Trap 4: Believing a construction manager absorbs agency duties. The architect of record still owes general observation and verified reports to the Division of the State Architect or the Department of Health Care Access and Information; those duties run to the state and cannot be contracted away.

Trap 5: Ignoring coordination gaps in multiple-prime work. Where no general contractor exists, scope gaps between trade contracts are the predictable claim, and the pre-construction conference is where they are surfaced.