5.1 Site Feasibility Studies, Existing-Conditions Due Diligence & Project Impacts

California Supplemental Examination CSE

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: California Architects Practice Act & Professional Practice

1.1 Licensing, Board Authority, and Unlicensed Practice Exceptions 1.2 Mandatory Written Contracts & Required Provisions 1.3 Architect's Stamp, Signature, and Professional Liability

2 Chapter 2: Professional Conduct, Ethics & Business Entities

2.1 Rules of Professional Conduct & Disciplinary Grounds 2.2 Permissible Business Entities, Firm Names, and Filing Requirements 2.3 Copyright, Instruments of Service & Ownership of Architectural Documents

3 Chapter 3: Contractual Roles, Scope & Consultant Agreements

3.1 Standard Owner-Architect Agreements (AIA B101 / B102) & California Practice Realities 3.2 Consultant Selection, Prime-Consultant Agreements & Liability Flow-Down (AIA C401) 3.3 Project Delivery Methods & Impact of Project Funding Sources

4 Chapter 4: Risk Management, Dispute Resolution & Project Planning

4.1 Professional Standard of Care & Managing Contractual Risk and Liability 4.2 Dispute Resolution in California Practice: Mediation, Arbitration, and Litigation 4.3 Project Scheduling, Budgeting Assumptions, and Milestone Approvals

5 Chapter 5: Site Feasibility, Schematic Design & Discretionary Approvals

5.1 Site Feasibility Studies, Existing-Conditions Due Diligence & Project Impacts 5.2 Programming, Schematic Design Development & Stakeholder Engagement 5.3 Local Land-Use Control: General Plans, Zoning, Specific Plans & Local Ordinances 5.4 The Discretionary Approval Process: Use Permits, Variances, Design Review & Hearings 5.5 Entitlement Exhibits, Conditions of Approval & Leading the Approval Team

6 Chapter 6: Environmental Review & CEQA Compliance

6.1 CEQA Regulatory Framework: Lead, Responsible, and Trustee Agencies 6.2 CEQA Process: Statutory & Categorical Exemptions, Initial Studies, and (Mitigated) Negative Declarations 6.3 Environmental Impact Reports (EIR) & Official Filings (NOP, NOC, NOD, NOE)

7 Chapter 7: California Coastal Act & Specialized Regional Regulations

7.1 California Coastal Commission & Coastal Development Permits (CDP) 7.2 Local Coastal Programs (LCP), Coastal Zone Boundaries, and Appeals 7.3 Clean Air Act (CARB/AQMDs) & Clean Water Regulations (Porter-Cologne, RWQCB & SWPPP)

8 Chapter 8: State Agency Jurisdictions: DSA, HCAI & Essential Services

8.1 Division of the State Architect (DSA): Field Act & Public K-12/Community College Oversight 8.2 Department of Health Care Access and Information (HCAI): Alfred E. Alquist Act & Healthcare Facility Classification 8.3 Essential Services Buildings Seismic Safety Act (ESBSSA) & California Historical Building Code (CHBC)

9 Chapter 9: California Building Code (CBC Title 24 Part 2) Core Architecture Provisions

9.1 Occupancy Classifications, Building Heights, and Allowable Floor Areas (CBC Chapters 3 & 5) 9.2 Fire and Smoke Protection Features, Fire Barriers, and Fire-Resistance Ratings (CBC Chapter 7) 9.3 Means of Egress, Occupant Load Calculations, and Exit Separation (CBC Chapter 10) 9.4 California Health and Safety Code: Building Standards Law, State Housing Law & Health Mandates

10 Chapter 10: Accessibility Requirements: Title 24 Chapter 11B & ADA

10.1 California Accessibility Framework: CBC Chapter 11B vs Federal ADA Standards 10.2 Accessible Routes, Entrances, Parking, and Site Arrival Points 10.3 Accessible Restrooms, Signage, Scoping, and Path of Travel Alteration Thresholds

11 Chapter 11: California Site Conditions & Natural Hazards

11.1 Seismic Hazard Mapping: Alquist-Priolo Earthquake Fault Zoning Act & Liquefaction 11.2 Wildland-Urban Interface (WUI) & Fire Hazard Severity Zones (CBC Chapter 7A & CFC Part 9) 11.3 Flood Hazard Zones (FEMA/DWR) & California Wind Exposure Categories

12 Chapter 12: Energy Efficiency: California Energy Code (Title 24 Part 6)

12.1 Energy Code Compliance Approaches: Prescriptive vs Performance & Time Dependent Valuation (TDV) 12.2 Mandatory Energy Measures: Envelope, HVAC, Lighting, Solar PV & Energy Storage Systems

13 Chapter 13: Sustainability (CALGreen) & Systems Integration

13.1 CALGreen (Title 24 Part 11) Mandatory Nonresidential & Residential Green Building Measures 13.2 Life-Cycle Cost Analysis (LCCA) & Value Engineering in California Practice 13.3 Building Systems Integration: MEP Coordination, Materials Evaluation & Acoustic Control

14 Chapter 14: Construction Document Requirements & Regulatory Coordination

14.1 CD Content, Detailing & Inter-Disciplinary Coordination for Agency Approval and Bidding 14.2 Authority Having Jurisdiction (AHJ) Hierarchy, Local Amendments & Local Finding Requirements 14.3 Reconciling Conflicting Codes, Standards, and Regulatory Mandates

15 Chapter 15: Plan Check & Permitting Processes

15.1 Permitting Procedures, Plan Check Review, Agency Comment Inquiries & Approval Pathways 15.2 Phased Permitting, Deferred Approvals, Encroachment Permits & Public Right-of-Way Coordination

16 Chapter 16: California Public Contract Code & Bidding Procedures

16.1 Public Works Bidding, Competitive Bidding Thresholds & Responsive vs Responsible Bidders 16.2 Subletting and Subcontracting Fair Practices Act & Subcontractor Listing Rules (PCC §§ 4100–4114) 16.3 California Prevailing Wage Requirements, DIR Registration & Certified Payroll Records

17 Chapter 17: California Mechanics Lien Law & Payment Remedies

17.1 20-Day Preliminary Notice Requirements & Timing (Civil Code § 8200) 17.2 Mechanics Liens, Recording Deadlines & Impact of Notice of Completion (Civil Code §§ 8400–8494) 17.3 Stop Payment Notices, Payment Bonds & Design Professional Liens (Civil Code §§ 8300–8319, 9350–9566)

18 Chapter 18: Construction Administration: Pre-Construction, Submittals, Changes & Field Observation

18.1 Pre-Construction & Pre-Installation Meetings and the Construction Manager's Impact on Services 18.2 Shop Drawings, Submittals & Architect's Deferred Submittal Review and Stamp 18.3 Construction Changes: Change Orders (CO), CCDs, ASIs & DSA Category A/B CCDs 18.4 Periodic Site Observations, Field Reports & the Means-and-Methods Boundary

19 Chapter 19: Inspection, Close-Out & Post-Construction Services

19.1 Special Inspections, Testing (CBC Chapter 17) & DSA/HCAI Continuous Field Inspection 19.2 Project Close-Out, Payment Applications (G702/G703), Retainage & California Warranty/Defect Limitations (CCP §§ 337.1 & 337.15) 19.3 Post-Construction Services, Record Documents & the Warranty Period 19.4 Construction Industry Standards, Detailing & Referenced Standards

5.1 Site Feasibility Studies, Existing-Conditions Due Diligence & Project Impacts

Key Takeaways Explain This Topic AI

The buildable envelope is set by the zoning ordinance (permitted use, height, setbacks, floor area ratio, lot coverage, open space, parking) and then further reduced by recorded easements, CC&Rs, protected trees, creek and bluff setbacks, and Alquist-Priolo fault-zone setbacks.

Existing-conditions due diligence relies on instruments the architect does not produce: a preliminary title report, an ALTA/NSPS Land Title Survey, a topographic and boundary survey, a geotechnical report under CBC Chapter 18, utility will-serve letters, and hazardous-materials surveys.

A Phase I Environmental Site Assessment (ASTM E1527) evaluates recognized environmental conditions in soil and groundwater; it is not a building hazardous-materials survey and does not satisfy the asbestos and lead survey obligations that precede demolition or renovation.

Statewide hazard maps must be checked parcel-by-parcel before design begins: Alquist-Priolo Earthquake Fault Zones, Seismic Hazard Zones for liquefaction and landslide, Fire Hazard Severity Zones, FEMA Flood Insurance Rate Maps, and the Cortese List of contaminated sites under Government Code Section 65962.5.

Buildings roughly 45 to 50 years old or older must be screened for historical-resource status before demolition or exterior alteration is assumed, because a qualifying historical resource converts a routine project into a CEQA significant-impact analysis.

Last updated: September 2026

Site Feasibility Studies, Existing-Conditions Due Diligence & Project Impacts

The CSE test plan opens its largest content area with a single task: conduct site feasibility studies to clarify and address project requirements . In California this is not a casual exercise. A parcel can be legally buildable and physically impossible, or physically ideal and legally frozen by a coastal boundary, a fault zone, a recorded easement, or an unmapped historical resource. Every schematic design decision that follows rests on the quality of the feasibility work, and every entitlement risk the client will later blame the architect for was visible at this stage.

Feasibility work also generates the existing-conditions data the exam tests separately: what the architect must obtain, who produces it, and what each instrument does and does not prove.

The Four-Part Feasibility Test

Work the questions in order. Each one can kill the project, so answering them out of sequence wastes the client's money.

1. Entitlement Feasibility: Is the Use Allowed?

Start with the general plan land use designation , then the zoning district . Zoning must be consistent with the general plan in general-law cities and counties, so a use permitted by zoning but inconsistent with the general plan designation signals that a general plan amendment — a legislative act, not an administrative one — is required. Confirm whether the use is permitted by right, permitted with a conditional use permit , or prohibited.

2. Physical Feasibility: Does the Program Fit?

Build the buildable envelope from the development standards and subtract every physical and legal encumbrance:

Envelope Control Typical Source What It Removes

Height limit, story limit Zoning ordinance Vertical capacity; may be measured from average natural grade, not finish grade

  • Front, side, rear setbacks Zoning ordinance Perimeter footprint
  • Floor area ratio (FAR), lot coverage Zoning ordinance Total and per-floor area
  • Required parking, loading, bicycle parking Zoning ordinance Ground-level area or a podium/subterranean level
  • Usable open space, landscape ratio Zoning ordinance Site area

Recorded easements, rights-of-way Preliminary title report Buildable area, sometimes across the middle of the parcel

Private CC&Rs, HOA design rules Title report exceptions Massing, materials, colors — enforceable privately even where zoning permits

Protected/heritage trees, creek and riparian setbacks Local ordinance, survey Footprint and grading limits

Alquist-Priolo fault setback (presumptively 50 feet) State fault-zone map A hard no-build band for structures for human occupancy

Coastal bluff, wetland, or shoreline setbacks Local Coastal Program Seaward development area

3. Regulatory Feasibility: What Approvals and Review Apply?

Identify the discretionary approvals required, the decision body for each, and the resulting CEQA pathway. Determine early whether a state agency preempts the local building department — a public school triggers DSA review, a general acute care hospital triggers HCAI review, and a project in the coastal zone triggers a coastal development permit . Run a preliminary California Building Code analysis at the same time: occupancy group, construction type, allowable height and area with any frontage and sprinkler increases, separation of occupancies, and whether the resulting building can actually be built in the envelope from step two. A program that only fits as Type I construction may be financially infeasible even though it is legally permitted.

4. Schedule and Cost Feasibility

Convert the approval pathway into a calendar. An initial study with a mitigated negative declaration and a planning commission hearing behaves very differently from a full environmental impact report with a city council appeal. Document the assumptions; they become the basis of the design schedule and of the additional-services triggers in the owner-architect agreement.

Existing-Conditions Due Diligence: Who Produces What

The architect coordinates this evidence but does not generate most of it. Knowing the correct instrument — and its limits — is exam-tested and malpractice-relevant.

Instrument What It Establishes Who Produces It California Note

Preliminary title report Ownership, legal description, recorded easements, CC&Rs, liens Title company Order the underlying recorded documents; the report only lists exceptions

ALTA/NSPS Land Title Survey Boundaries reconciled with title exceptions, plotted easements, encroachments Licensed land surveyor The only reliable boundary source; assessor parcel maps are not survey-grade

Topographic survey Contours, spot elevations, trees, utilities, improvements Licensed land surveyor Drives grading, accessible route slopes, and drainage design

Geotechnical/soils report Soil profile, bearing capacity, groundwater, seismic site class, liquefaction and expansive-soil findings Geotechnical engineer Required by CBC Chapter 18; a Seismic Hazard Zone triggers a site-specific investigation

Utility will-serve letters and capacity studies Whether water, sewer, power, and gas capacity actually exists at the property line Serving utilities and districts Capacity — not just proximity — governs; sewer capacity commonly limits infill projects

Record drawings and as-builts Existing building configuration Owner, building department microfiche Verify in the field; record drawings are evidence, not fact

Phase I Environmental Site Assessment (ASTM E1527) Recognized environmental conditions in soil and groundwater Environmental professional Does not cover building materials; a Phase II involves sampling

Hazardous building materials survey Asbestos-containing materials, lead-based paint, PCBs, mercury Certified asbestos consultant, lead inspector Required before demolition or disturbance under Cal/OSHA and air district rules

Historical resource evaluation (DPR 523 forms) Eligibility for the California Register or a local register Architectural historian A qualifying historical resource makes demolition or major alteration a CEQA impact

Statewide Hazard and Contamination Screening

Every California feasibility study includes a parcel-level map check. These are free, public, and dispositive:

Alquist-Priolo Earthquake Fault Zones — presumptive 50-foot setback from an active trace for structures for human occupancy unless a site-specific fault investigation demonstrates otherwise.

Seismic Hazard Zones — liquefaction and earthquake-induced landslide zones under the Seismic Hazards Mapping Act; trigger a site investigation and mitigation report before a permit issues.

Fire Hazard Severity Zones — moderate, high, and very high zones in State and Local Responsibility Areas; a very high zone imposes CBC Chapter 7A ignition-resistant construction and defensible-space obligations.

FEMA Flood Insurance Rate Maps and state awareness floodplain maps — establish the base flood elevation and the freeboard the local floodplain ordinance requires.

Cortese List (Government Code Section 65962.5) — the state list of hazardous-materials release sites; a listed parcel affects both CEQA analysis and lender due diligence.

Coastal Zone boundary and Local Coastal Program maps — determine whether a coastal development permit is required and whether appeal jurisdiction lies with the Coastal Commission.

Determining Project Impacts

Feasibility work produces the environmental baseline the CEQA document will use: the physical conditions on the site at the time the notice of preparation is published or environmental review begins. Common early impact screens include vehicle miles traveled under Public Resources Code Section 21099, construction and operational noise against the local noise element, shade and shadow on adjacent uses, biological resources, tribal cultural resources under Assembly Bill 52 consultation, and archaeological sensitivity. Identifying these early lets the design team avoid an impact rather than mitigate it, which is always cheaper.

CSE Exam Traps & Practical Takeaways

Trap 1: Treating a Phase I ESA as a hazardous materials survey. A Phase I addresses soil and groundwater contamination. It does not look for asbestos, lead paint, or PCBs in the building, and a demolition contractor cannot rely on it.

Trap 2: Designing to the assessor parcel map. Assessor maps are for taxation. Only a boundary or ALTA/NSPS survey establishes the property line the setbacks are measured from.

Trap 3: Confusing proximity with capacity. A sewer main in the street is not the same as sewer capacity. Get the will-serve letter before you fix the unit count.

Trap 4: Skipping the age screen on existing buildings. A structure approaching 50 years old must be evaluated for historical significance before the team assumes demolition. Discovering a historical resource after the entitlement application is filed restarts environmental review.

Trap 5: Reporting feasibility as a yes or no. The correct deliverable is a written feasibility report identifying the approval path, the assumptions, the unresolved items, and the risks — the document that later proves the architect disclosed the constraint.