11.1 Vertical Curve Geometry and Grades
California Civil Engineering Surveying CES
Track your progress as you read
Finished sections get a check mark.
1 Introduction & Exam Overview
1.1 Current Exam Facts 1.2 California Civil PE Path and Scheduling 1.3 Test Day, References, and Calculators
2 Chapter 2: Civil Engineer Surveying Authority
2.1 Professional Engineers Act: Engineering Surveying 2.2 Civil Engineer vs Professional Land Surveyor Limits 2.3 Board Rules, Accuracy Statements, and Map Act Context
3 Chapter 3: Survey Types and Control
3.1 Control Surveys: Purpose and Procedures 3.2 Alignment and Route Surveys 3.3 Topographic Surveys: Aerial, Surface, and Utilities
4 Chapter 4: Data Collection Methods, Accuracy, and GIS
4.1 Data Collection Methods: Leveling and LiDAR 4.2 Accuracy, Precision, and Error Types 4.3 GIS Applications for Civil Engineering Surveys
5 Chapter 5: Horizontal and Vertical Datums
5.1 Horizontal Datums and Assumed Systems 5.2 Vertical Datums and Benchmarks 5.3 Control Networks and Datum Selection
6 Chapter 6: Field Distances, Angles, and Conflicts
6.1 Measuring Horizontal Distances 6.2 Measuring Angles and Establishing Points 6.3 Construction Conflicts: Utilities, Structures, and Substructures
7 Chapter 7: Field Leveling and Equipment
7.1 Differential Leveling and Level Notes 7.2 Trigonometric Leveling 7.3 Surveying Equipment: Distance, Angle, Elevation
8 Chapter 8: Traverse and Rectangular Coordinates
8.1 Latitudes, Departures, and Coordinates 8.2 Error of Closure 8.3 Traverse Adjustment and Side Shots
9 Chapter 9: Angles, Distances, and Equipment Errors
9.1 Azimuths, Bearings, Backbearings, and Deflections 9.2 Horizontal, Slope, and Vertical Distances 9.3 Equipment Errors and Corrections
10 Chapter 10: Horizontal Curves
10.1 Circular Curve Elements 10.2 Horizontal Curve Stationing and Layout 10.3 Compound and Reverse Curves
11 Chapter 11: Vertical Curves and Line and Grade
11.1 Vertical Curve Geometry and Grades 11.2 High and Low Points and Intermediate Elevations 11.3 Line and Grade from Plans and Profiles
12 Chapter 12: Contours, Offsets, Areas, and Earthwork
12.1 Contours and Cross-Sections 12.2 Offsets and Vertical Interference 12.3 Areas, DMD, and Earthwork Volumes
13 Chapter 13: Mapping
13.1 Interpreting Maps and Plans 13.2 Interpolating Elevations and Plotting Features 13.3 Map Scales and Accuracy Standards
14 Chapter 14: Construction Staking and Cross-Sections
14.1 Stationing and Stake Marking 14.2 Hinge Points, Catch Points, and Grade Breaks 14.3 Slope Staking from Typical Sections
15 Chapter 15: Construction Alignment Layout
15.1 Staking Horizontal Alignment and Curves 15.2 Staking Vertical Alignment and Grades 15.3 Mixed Layout Problems and Exam Strategy
11.1 Vertical Curve Geometry and Grades
Key Takeaways Explain This Topic AI
Equal-tangent parabolic vertical curve: PVI is halfway from PVC to PVT. A = g2 − g1 in one unit system. Elevation on the curve is elev_PVC + g1 x + (A/(2L)) x², with x measured along the curve from the PVC.
Worked crest: g1 = +2.0%, g2 = −1.5%, L = 400 ft, PVC elevation 520.00 ft. PVI elevation 524.00 ft, PVT elevation 521.00 ft, midpoint offset 1.75 ft below the PVI.
Crest curves have A < 0 and lie below the tangents. Sag curves have A > 0 and lie above the tangents. The sign of A is the exam’s fastest crest/sag test.
Keep g1, g2, and A in the same units as the distance convention you chose. +2.0% is +0.020 ft/ft. Mixing percent with feet without converting by 100 wrecks every elevation.
K = L/A (L in stations, A in percent) is a highway-design convenience for choosing curve length. The 2022 CES list is high/low point, intermediate point, and rate of grade — not a Caltrans HDM K table you must memorize.
Last updated: September 2026
11.1 Vertical Curve Geometry and Grades
Quick Answer: An equal-tangent parabolic vertical curve joins incoming grade g1 to outgoing grade g2 . A = g2 − g1 . Curve length L is the horizontal length from PVC to PVT . From the PVC, offset y = (A/(2L)) x² and elev = elev_PVC + g1 x + (A/(2L)) x² . On the worked crest ( g1 = +2.0% , g2 = −1.5% , L = 400 ft , PVC 520.00 ft ): PVI = 524.00 ft , PVT = 521.00 ft , midpoint offset 1.75 ft below the PVI.
This section is CES Domain III item F at the geometry layer: rate of grade and the parabola you will use for high/low points and intermediate elevations in §11.2. Domain III as a whole is the heaviest official weight (30%). The professional activity “determine line and grade from plans and profiles” is §11.3. Construction staking of the same curve is Chapter 15 — preview only here.
California notes may say BVC/EVC (begin/end of vertical curve) for PVC/PVT. Same three points: PVC (point of vertical curvature), PVI (point of vertical intersection of the two tangents), PVT (point of vertical tangency).
Equal-Tangent Parabola
On an equal-tangent curve the two tangent lengths are equal:
PVC to PVI = PVI to PVT = L/2 (horizontal).
The curve is a parabola in elevation versus station. That is the civil-engineering default on roadway, channel, and pipe profiles. CES items that give one length L and two grades, and that never say the tangent lengths differ, are equal-tangent.
The parabola is not a circular vertical curve. Do not bring Chapter 10’s radius, tangent T = R tan(Δ/2) , or chord definitions into a profile. Horizontal-curve L is an arc; vertical-curve L is a horizontal length along the stationing.
Grades g1 and g2, and Algebraic Difference A
g1 is the incoming (back) tangent grade. g2 is the outgoing (forward) tangent grade. Both are slopes: rise over run.
Write them two ways and pick one system for the whole solution :
- Form Meaning Example
- Percent feet of rise per 100 ft of station g1 = +2.0% , g2 = −1.5%
- Decimal (ft/ft) feet of rise per foot of station g1 = +0.020 , g2 = −0.015
A = g2 − g1 is the algebraic difference in grade . Use the same unit system as the grades:
- Percent: A = −1.5 − (+2.0) = −3.5%
- Decimal: A = −0.015 − (+0.020) = −0.035 ft/ft
A is not |g1| + |g2| with the sign guessed afterward, and it is not g1 − g2. Subtract incoming from outgoing : g2 minus g1 . A sign error here flips crest versus sag and sends every offset to the wrong side of the tangent.
A plus grade climbs as station increases. A minus grade falls. Rate of grade on a tangent is constant: Δelev = g × Δx with matching units (decimal g with x in feet, or percent g with x in stations: +2.0% × 2.00 stations = +4.00 ft ).
Length L — Stations or Feet, Not Both at Once
L is the horizontal PVC-to-PVT length. 1 station = 100 ft .
The worked curve uses L = 400 ft = 4.00 stations . If PVC is at 20+00 :
- PVI station = 20+00 + 2+00 = 22+00
- PVT station = 20+00 + 4+00 = 24+00
Stay consistent inside each formula. If x and L are in feet and A is decimal , y comes out in feet. If x and L are in stations and A is in percent , y = A x² / (2L) also comes out in feet. The exam trap is A in percent with x in feet stuffed into A/(2L) as if A were decimal — offsets 100 times too large.
Percent-and-feet form of the same offset (A in percent, x and L in feet):
y = (A% × x²) / (200 L)
Because A_decimal / (2L) = (A%/100) / (2L) = A% / (200L).
Offset and Elevation from the PVC
Measure x along the curve from the PVC (horizontal station difference). The offset from the incoming tangent is
y = (A / (2L)) x²
The elevation on the curve is the incoming-tangent elevation plus that offset:
elev = elev_PVC + g1 x + (A / (2L)) x²
At x = 0 (PVC), y = 0 and elev = elev_PVC. At x = L (PVT) the parabola meets the outgoing tangent.
On an equal-tangent curve the midpoint offset (x = L/2), which is also the offset from the PVI down (crest) or up (sag) to the curve, is
E = A L / 8
Same units warning as above. E is not the high or low point unless g1 = −g2 (§11.2).
The PVI elevation is not on the curve. It is the intersection of the two tangents :
- elev_PVI = elev_PVC + g1 × (L/2)
- elev_PVT = elev_PVI + g2 × (L/2)
Those two tangent equations are how you check the parabola at x = L.
Crest versus Sag
- Type Sign of A = g2 − g1 Curve relative to tangents Typical grades
- Crest (summit) A < 0 Curve below the tangents + to −, or flattening of a climb
- Sag (valley) A > 0 Curve above the tangents − to +, or steepening of a climb
A crest that goes from upgrade to downgrade is the usual picture. A curve can still be a crest if both grades are positive but g2 is smaller than g1 (the climb flattens): A is still negative and the parabola still sits below the tangents. Sag is the opposite. Read A , not the cartoon of a hill.
Unequal-Tangent Curves (Know They Exist)
An unequal-tangent vertical curve has PVC-to-PVI ≠ PVI-to-PVT . The PVI is not at station PVC + L/2, and the single-parabola E = AL/8 does not apply at that PVI. CES numbers that give one L and two grades are equal-tangent unless the stem states unequal tangents or gives two different tangent lengths. If a stem does split the tangents, compute each tangent elevation with its own horizontal length; do not force L/2.
Worked Equal-Tangent Crest
Given: g1 = +2.0% = +0.020 ft/ft , g2 = −1.5% = −0.015 ft/ft , L = 400 ft , PVC elevation 520.00 ft . Hold PVC at station 20+00 for stationing.
A = −0.015 − 0.020 = −0.035 ft/ft (or −3.5% ). A < 0 → crest , offsets below the tangents.
PVI at x = 200 ft, station 22+00 :
elev_PVI = 520.00 + 0.020 × 200 = 520.00 + 4.00 = 524.00 ft
PVT at x = 400 ft, station 24+00 :
elev_PVT = 524.00 + (−0.015) × 200 = 524.00 − 3.00 = 521.00 ft
Parabola check at x = L:
- elev = 520.00 + 0.020 × 400 + (−0.035 / (2 × 400)) × 400²
- = 520.00 + 8.00 + (−0.035 × 400) / 2
= 528.00 − 7.00 = 521.00 ft . Matches.
Midpoint offset at x = 200 ft:
E = A L / 8 = (−0.035)(400) / 8 = −14.00 / 8 = −1.75 ft
Percent-and-feet check: y = (−3.5)(200)² / (200 × 400) = −140,000 / 80,000 = −1.75 ft .
Elevation on the curve at the PVI station: 524.00 + (−1.75) = 522.25 ft . That 522.25 is the curve at 22+00, not the high point (the incoming 2% is steeper than the outgoing 1.5% fall, so the summit sits past the PVI — §11.2).
K = L/A as Optional Highway-Design Context
Highway designers often store K = L / |A| with L in stations and A in percent . For this curve L = 4.00 stations and |A| = 3.5, so K ≈ 1.14 . In AASHTO and Caltrans Highway Design Manual practice, K is a convenience for picking L from a design speed and a sight-distance or headlight chart.
The 2022 CES test plan names high/low point , intermediate point , and rate of grade . It does not name HDM K values. If you brought a bound HDM in the Prometric box, a K chart is optional professional context — not a CES-required table to memorize. Compute L , A , offsets, and elevations from the parabola. Do not hunt a K table to answer a high-point item.
Exam Traps
A = g1 − g2 — reverses crest/sag and the sign of every y .
PVI elevation treated as a curve elevation — 524.00 is on the tangents; the curve at that station is 522.25 .
Percent A in a decimal formula — A = −3.5 stuffed into A/(2L) with L in feet yields offsets 100 times too big.
Circular-curve formulas on a profile — no radius on this parabola.
Unequal-tangent instinct on an equal-L stem — PVI is at L/2 unless the problem gives two tangent lengths.