11.5 Commissioning: Pre-Start Checks, Run-In & Documentation
Red Seal Industrial Mechanic Millwright
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Safety & Occupational Skills
1.1 WHMIS, SDS & Hazardous Materials 1.2 Lockout/Tagout (LOTO) & Energy Isolation 1.3 Confined Space Entry & Fall Protection 1.4 Blueprint Reading, Trade Math & Precision Measurement Tools 1.5 Hand Tools, Portable Power Tools & Shop Machines 1.6 Access Equipment: Ladders, Scaffolds & Elevating Work Platforms 1.7 Planning Work, Permits, Communication & Mentoring
2 Chapter 2: Fasteners & Bolted Joints
2.1 Threaded Fasteners, Bolts & Thread Standards 2.2 Torque Values, Tightening Patterns & Thread Pitch/Gaging 2.3 Non-Threaded Fasteners, Pins, Keys & Anchors
3 Chapter 3: Rigging, Hoisting & Crane Signals
3.1 Sling Angles, Sling Types & Leg Tension Calculations 3.2 Working Load Limit (WLL) & Hardware Inspection 3.3 Centre of Gravity & Load Weight Estimation 3.4 Hoists, Overhead Cranes & Standard Hand Signals 3.5 Jacking, Skidding, Rollers & Moving Equipment 3.6 Lift Planning, Area Control & Rigging Equipment Maintenance
4 Chapter 4: Prime Movers & Electric Motors
4.1 Electric Motors, Enclosures, Frame Sizes & Synchronous Speed 4.2 Motor Installation, Nameplates & Overload Protection 4.3 Engine Prime Movers & Mechanical Drives Introduction
5 Chapter 5: Belt & Chain Mechanical Drives
5.1 V-Belts, Timing Belts & Sheave Alignment 5.2 Belt Tensioning, Pitch Diameter & Speed Ratios 5.3 Roller Chains, Sprocket Alignment & Lubrication 5.4 Clutches, Brakes & Torque Limiters
6 Chapter 6: Gear Drives, Couplings & Reducers
6.1 Gear Types, Geometry & Gear Ratios 6.2 Couplings (Rigid, Flexible, Fluid) & Installation 6.3 Shaft Keys, Keyways, Taper Sleeves & Hub Fits 6.4 Gear Reducers, Backlash & Mechanical Drive Troubleshooting
7 Chapter 7: Industrial Pumps & Systems
7.1 Centrifugal Pumps, Impellers & Performance Curves 7.2 Positive Displacement Pumps (Gear, Vane, Piston, Diaphragm) 7.3 Cavitation, NPSHa vs NPSHr & Pump Priming 7.4 Pump Maintenance, Packing & Mechanical Seals
8 Chapter 8: Compressors, Fans & Pneumatics
8.1 Reciprocating & Rotary Screw Air Compressors 8.2 Compressed Air Treatment, FRL Units & Air Receivers 8.3 Centrifugal & Axial Fans, Affinity Laws & Airflow 8.4 Pneumatic Circuits, Valves, Actuators & Troubleshooting 8.5 Vacuum Systems, Pumps & Venturi Generators
9 Chapter 9: Bearings, Lubrication & Seals
9.1 Plain Bearings, Bushings & Fits 9.2 Rolling Element Bearings & Installation 9.3 Bearing Heating Limits, Fits & Removal Tools 9.4 Industrial Lubricants, Viscosity, Grease NLGI Grades & Seals
10 Chapter 10: Precision Alignment & Foundations
10.1 Precision Shaft Alignment (Rim-and-Face & Reverse-Dial Methods) 10.2 Laser Alignment, Soft Foot Correction & Thermal Growth 10.3 Machinery Foundations, Leveling, Grouting & Dowelling
11 Chapter 11: Vibration Analysis & Predictive Maintenance
11.1 Vibration Analysis, Dynamic Balancing & Thermography 11.2 Preventive/Predictive Maintenance & Decommissioning 11.3 Non-Destructive Testing (NDT) Methods 11.4 Lubricant & Fluid Analysis 11.5 Commissioning: Pre-Start Checks, Run-In & Documentation
12 Chapter 12: Hydraulic Systems
12.1 Hydraulic Fundamentals: Pascal’s Law, Pressure, Flow & Power 12.2 Hydraulic Fluids, Reservoirs, Filtration & Contamination Control 12.3 Hydraulic Pumps: Gear, Vane & Piston Designs 12.4 Hydraulic Valves: Pressure, Directional & Flow Control 12.5 Hydraulic Actuators: Cylinders, Motors & Accumulators 12.6 Hydraulic Conductors, ISO 1219 Symbols & System Troubleshooting
13 Chapter 13: Conveying Systems, Material Handling & Automation
13.1 Belt Conveyors: Components, Tracking & Training 13.2 Screw, Bucket, Roller, Chain & Pneumatic Conveyors 13.3 Robotics & Automated Equipment
14 Chapter 14: Process Piping, Tanks & Vessels
14.1 Process Piping: Materials, Sizing, Fittings & Joining 14.2 Flanges, Gaskets & Piping Bolted-Joint Assembly 14.3 Tanks, Vessels & Containers: Installation, Inspection & Repair
15 Chapter 15: Materials, Fabrication, Cutting & Welding
15.1 Material Identification: Ferrous & Non-Ferrous Metals, Plastics 15.2 Heat Treatment of Metals 15.3 Oxy-Fuel & Plasma Arc Cutting 15.4 Welding Processes: SMAW, GMAW, GTAW, OFW & Equipment Care 15.5 Layout Procedures & Maintaining Precision Measuring Tools
11.5 Commissioning: Pre-Start Checks, Run-In & Documentation
Key Takeaways Explain This Topic AI
Commissioning verifies mechanical completion, then proves the equipment performs to specification under progressively increasing load before it is handed to operations.
Motor rotation must be confirmed uncoupled before a pump, fan or compressor is coupled, because reverse rotation can destroy an impeller, a seal or a screw element in seconds.
Baseline readings — vibration, bearing temperature, current draw, alignment values and flow or pressure — are recorded at commissioning and become the reference for all future condition monitoring.
Hot alignment checks after the machine reaches operating temperature confirm that the cold offsets compensated thermal growth correctly.
A commissioning package is not complete until as-built drawings, test records, baseline data, lubrication charge details and operator training are all documented and handed over.
Last updated: August 2026
Task F-24 (Commissions and decommissions equipment) carries 5 exam questions. Section 11.2 covers decommissioning; this section covers F-24.01 (Commissions systems and components) — the disciplined sequence that turns an installed machine into a machine that will run reliably for twenty years.
- The Commissioning Sequence MECHANICAL -> PRE-START -> UNCOUPLED -> COUPLED -> LOADED -> HANDOVER
- COMPLETION CHECKS SOLO RUN NO-LOAD RUN RUN-IN PACKAGE
- installed, static motor rotate the progressive as-builts,
- aligned, verification rotation, train, check load steps, baselines,
- torqued, of every current, vibration full duty, training,
- lubricated system vibration and temps performance sign-off
Each gate must pass before the next begins. Skipping a gate is how new equipment fails in its first week.
Stage 1 — Mechanical Completion Verification
Check What to confirm
Foundation and grout Grout cured and sound, anchor bolts torqued to specification, no voids under the baseplate (hammer test)
- Soft foot Corrected and documented, within about 0.05 mm (0.002 in) at every foot
- Alignment Final cold alignment recorded, including the thermal-growth offsets used (section 10.2)
- Piping Pipe strain checked with a dial indicator at the flanges; supports and hangers set (section 14.1)
- Fasteners All bolts torqued to specification and marked; couplings, guards and access covers secure
- Guards Every rotating component guarded, guards secure and correctly fitted
Lubrication Correct lubricant grade and quantity in every sump, bearing and gearbox; sight glasses at the correct level; grease points charged; auto-lubricators set and dated
Cleanliness Systems flushed; hydraulic and lube circuits flushed to the target ISO cleanliness code before the machine runs on them
- Instrumentation Gauges, thermowells, vibration sensors and switches installed, calibrated and readable
- Rotation by hand Turn the train by hand to confirm it is free, with no rubbing or binding
- Stage 2 — Pre-Start Checks and Permits
Confirm all construction lock-outs are removed and the correct operational isolation state exists.
Verify electrical checks are complete — megger and continuity tests, overload settings matched to nameplate FLA and service factor (section 4.2), and control wiring proven.
Confirm safety devices are functional and not bypassed : vibration switches, temperature switches, low-flow and low-level trips, belt-slip and misalignment switches, emergency stops, and interlocks. Never commission with a protective device jumpered out.
Confirm cooling water, seal flush, purge gas and instrument air are lined up.
Clear and barricade the area , brief everyone involved, and assign roles including who has authority to stop.
Stage 3 — Uncoupled Solo Run of the Driver
Always confirm motor rotation with the coupling disconnected. Reverse rotation will:
Unscrew a threaded pump impeller and wreck the pump in seconds.
Run a rotary screw compressor backward and destroy the element.
Reverse a fan's flow at drastically reduced volume, hiding the fault until the process fails.
Drive a positive-displacement pump against a closed suction and burst a line.
With the coupling out:
Bump the motor and confirm rotation against the arrow on the casing.
Run the motor solo, and record no-load current, vibration and bearing temperatures .
Confirm the direction again if the electrical connection is changed at any point afterwards.
Stage 4 — Coupled No-Load Run
Reconnect the coupling to the recorded alignment, fit the guard, and run the train unloaded (recirculation valve open, damper closed, or clutch disengaged as applicable):
Watch for the first minutes continuously, listening for rubs, and be ready to stop.
Record vibration at every bearing in three directions , bearing temperatures, and current.
Check for leaks at every joint, seal and fitting under real running pressure.
Confirm oil flow at every sight glass and return line, and that the seal flush is proven.
Let the machine reach thermal equilibrium — usually one to four hours — while monitoring temperature trends toward a stable plateau.
Stage 5 — Progressive Load Run-In
Load the machine in steps, commonly 25%, 50%, 75% and 100%, holding at each step long enough for temperatures to stabilize. At each step record:
Vibration (overall level and spectrum), bearing and winding temperature, current and power.
Process values — flow, suction and discharge pressure, differential pressure, speed.
Any noise or behaviour change.
Compare against the manufacturer's acceptance criteria and the design duty point. A pump that will not make its head at rated flow, or a fan drawing more power than the curve predicts, has an installation or a system problem that must be resolved before handover, not after.
Break-in requirements matter on specific equipment: new gearboxes often require a break-in oil change after a short initial run (commonly 100–500 hours) to remove the metal debris generated as gear teeth bed in, and new V-belt drives need re-tensioning after the initial run-in period because they seat and lose tension quickly.
Stage 6 — Hot Alignment Verification
Once the machine has reached stable operating temperature, shut it down, lock out, and re-check the alignment immediately while hot . This confirms that the thermal-growth offsets applied cold actually brought the machine into alignment at temperature. A machine that was aligned within tolerance cold and is now out of tolerance hot needs its offsets corrected — the calculation was wrong, or the growth is not what the manufacturer predicted.
Stage 7 — Baseline Data and Handover
Baseline data captured at commissioning is the single most valuable maintenance asset a machine will ever have , because all future condition monitoring is a comparison against it.
- Baseline record Why it matters
- Vibration spectra at every bearing The signature of a healthy machine; future spectra are compared to it
- Bearing and winding temperatures at each load step Establishes the normal thermal profile
- Motor current and power at each load step Detects future increases in mechanical drag
- Final alignment values, cold and hot Reference for future alignment checks
- Process performance data Proves the duty point and provides a degradation reference
- Thermographic images Baseline heat pattern of couplings, bearings, and electrical connections
- Lubricant type, quantity and a new-oil sample Reference for all future oil analysis
The handover package must include:
As-built drawings and P&IDs with all field changes redlined and incorporated.
Completed inspection and test records with sign-offs.
Manufacturer manuals, spare parts lists and recommended spares holding.
Lubrication schedule and chart entered into the CMMS.
Preventive-maintenance job plans and intervals loaded into the CMMS.
Warranty terms and start date.
Operator and maintainer training , delivered and documented.
A formal sign-off transferring custody from the project or maintenance group to operations.
A machine is not commissioned when it runs. It is commissioned when it has been proven to specification and the documentation, baselines and training exist to keep it that way.