12.5 Payments: Progress Payments, Retention, and California Prompt Payment Law
California C-39 Roofing Contractor Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Planning, Codes, and Roofing Estimating
1.1 California Building Codes, Title 24 Energy Standards, and Plan Reading 1.2 Roof Geometry, Area Calculations, and Pitch Multipliers 1.3 Material Takeoffs, Squares, and Waste Calculations 1.4 Roof System Selection, Specifications, Permits, and Project Scheduling 1.5 Labor Production Rates, Overhead, Profit, and Roofing Bid Pricing
2 Chapter 2: Job Site Preparation and Substrate Remediation
2.1 Jobsite Protection, Material Staging, and Temporary Weatherproofing 2.2 Tear-Off Procedures, Overlay Limitations, and Hazardous Materials 2.3 Roof Deck Inspection, Substrate Preparation, and Sheathing Repairs
3 Chapter 3: Low-Slope Roof Systems — Built-Up, Modified Bitumen, and Single-Ply
3.1 Built-Up Roofing (BUR) Systems, Felts, and Hot Bitumen Application 3.2 Modified Bitumen Membrane Systems (APP vs. SBS) and Installation 3.3 Single-Ply Roofing Membranes (TPO, PVC, EPDM) and Seaming Methods
4 Chapter 4: Low-Slope Roof Systems — SPF, Coatings, Flashings, and Maintenance
4.1 Spray Polyurethane Foam (SPF) and Liquid-Applied Protective Coatings 4.2 Low-Slope Drainage, Perimeters, Penetration Flashings, and Scuppers 4.3 Low-Slope Diagnostics, Blister Repairs, and Preventative Maintenance
5 Chapter 5: Steep-Slope Roofing — Flashing, Underlayment, and Ventilation
5.1 Steep-Slope Underlayments, Felt Grades, and Self-Adhering Ice/Water Barriers 5.2 Flashing Details: Valleys, Drip Edges, Step Flashing, Aprons, and Crickets 5.3 Attic and Roof Ventilation: NFVA Requirements, Vent Types, and Airflow Balance
6 Chapter 6: Steep-Slope Roofing — Materials, Installation, and Repair
6.1 Asphalt Shingle Installation, Fastening Patterns, and Wind/Slope Requirements 6.2 Concrete and Clay Tile Roofing (TRI Standards, Battens, and Fastening) 6.3 Standing Seam Metal Panels, Wood Shakes, Slate, and Steep-Slope Repairs 6.4 Steep-Slope Leak Diagnosis, Targeted Repairs, and the Repair-or-Replace Decision
7 Chapter 7: California Roofing Safety — Cal/OSHA, Fall Protection, and Hazards
7.1 Cal/OSHA Fall Protection: Residential Roofing (§1731), Roof Hazards (§1730), and PFAS 7.2 Cal/OSHA Ladder Safety, Scaffold Erection, and Power Line Clearance 7.3 Heat Illness Prevention (CCR §3395), Hot Asphalt Safety, and Personnel PPE 7.4 Injury and Illness Prevention Program, Safety Training, Recordkeeping, and Cal/OSHA Reporting 7.5 Hazard Communication, Asbestos, Lead, and Silica: Managing Unknown Materials
8 Chapter 8: CSLB Licensing Law and Business Organization
8.1 CSLB Licensing Classifications, Bond Requirements, and License Law 8.2 Business Entity Choice, Personnel of Record, and Qualifier Responsibilities 8.3 Advertising Rules, Home Improvement Salespersons, and Subcontracting
9 Chapter 9: Business Finances, Financial Reporting, and Taxes
9.1 Cash Management, Job Costing, and Working Capital 9.2 Budgeting, Business Planning, and Break-Even Analysis 9.3 Financial Reporting: Statements, Accounting Methods, and Key Ratios 9.4 Federal and California Taxes for Roofing Contractors
10 Chapter 10: Employment Requirements, Supervision, and Payroll
10.1 Hiring: Worker Classification, Verification, and New-Hire Reporting 10.2 Supervising and Training Employees 10.3 Performance Evaluation, Personnel Records, and Termination 10.4 California Payroll: Wages, Overtime, Meal and Rest Periods, and Deposits
11 Chapter 11: Insurance, Bonds, and Payment Remedies
11.1 Workers' Compensation Insurance for California Roofing Contractors 11.2 Business Insurance and Surety Bonds 11.3 California Mechanics Lien Law, 20-Day Preliminary Notices, and Lien Waivers
12 Chapter 12: Contract Requirements, Bidding, and Project Execution
12.1 California Roofing Contracts, Home Improvement Law (B&P §7159), and Warranties 12.2 Bidding Practices, Bid Documents, and Competitive Bidding Law 12.3 Job Cost Control and Change Order Management 12.4 Project Organization, Scheduling, and Documentation 12.5 Payments: Progress Payments, Retention, and California Prompt Payment Law
13 Chapter 13: Public Works Roofing Projects
13.1 Prevailing Wage, DIR Registration, and Certified Payroll 13.2 Public Works Bonding and Insurance Requirements
12.5 Payments: Progress Payments, Retention, and California Prompt Payment Law
Key Takeaways Explain This Topic AI
Under B&P § 7108.5 a prime contractor or subcontractor must pay each subcontractor within seven days after receiving a progress payment, and a violation carries a penalty of 2 percent of the amount due per month plus attorney's fees to the prevailing party.
Effective January 1, 2026, Civil Code § 8811 added by SB 61 caps retention on private California construction contracts at 5 percent of the payment and 5 percent of the contract price, applying uniformly at every tier.
On public works, Public Contract Code § 7201 caps retention at 5 percent and § 7107 requires the public entity to release retention within 60 days after the date of completion.
Where there is a good faith dispute, a prime contractor or subcontractor may withhold no more than 150 percent of the disputed amount from a progress payment.
On residential home improvement work the down payment cannot exceed 10 percent of the contract price or $1,000, whichever is less, and progress payments cannot exceed the value of work performed or materials delivered to the site.
Last updated: September 2026
Payments: Progress Payments, Retention, and California Prompt Payment Law
Quick Answer: California regulates construction payment at every tier. On residential work the deposit is capped at 10 percent of the contract price or $1,000, whichever is less , and progress payments may not exceed the value of work performed or material delivered. Once money moves, B&P § 7108.5 gives a prime 7 days from receipt of a progress payment to pay its subcontractors, with a 2 percent per month penalty and attorney's fees for violating it. Retention is now capped at 5 percent on both sides of the market: Public Contract Code § 7201 for public works, and — new for contracts entered into on or after January 1, 2026 — Civil Code § 8811 , added by SB 61 , for private works. Public retention is released within 60 days of completion under PCC § 7107 . In a good faith dispute , no more than 150 percent of the disputed amount may be withheld.
1. Structuring the Payment Schedule
A payment schedule should track the value in place , so cash arrives roughly as cost goes out.
A typical residential reroof schedule:
- Milestone Share
- Deposit at signing Lesser of 10% or $1,000 (statutory cap)
- Tear-off complete and dry-in passed 40%
- Field covering complete 35%
- Final inspection signed and punch list complete Balance
Two hard residential rules:
Down payment. Never demand or accept more than 10 percent of the contract price or $1,000, whichever is less . Exceeding it is a misdemeanor.
Progress payments. They may not exceed the value of the work performed or the materials delivered to the job site , and the contract must state each payment in specific dollars and cents tied to a defined stage of work. Front-loading a payment schedule is a violation even if the homeowner agrees.
On commercial work, the payment application is normally a schedule-of-values billing supported by a percentage-complete certification, lien releases for the prior period, and a certified payroll where the job is public.
2. Retention
Retention is a percentage withheld from each payment and released after completion, held as security that the contractor will finish and correct defects.
Project type Cap Release
Public works 5 percent of the contract price (Public Contract Code § 7201) Within 60 days after the date of completion (PCC § 7107); withholding beyond that carries 2 percent per month plus attorney's fees
Private works, contracts entered into on or after January 1, 2026 5 percent of each payment and of the contract price ( Civil Code § 8811 , added by SB 61 ) Per the contract and the Civil Code prompt payment provisions
SB 61 in brief. Signed July 14, 2025 and operative for contracts entered into on or after January 1, 2026, Civil Code § 8811 brings private construction into line with the public works cap that has applied since 2012, ending the long-standing 10 percent private norm. The cap applies uniformly at every tier , so an owner or general contractor cannot push a larger withholding downstream. The prevailing party in an action to enforce it recovers reasonable attorney's fees. Two carve-outs matter to roofers: the statute does not apply to non-mixed-use residential projects that do not exceed four stories, and where a subcontractor was told in writing before or at bid time that performance and payment bonds would be required and then failed to furnish them, the retaining party may withhold up to 10 percent .
Because the cap turns on the date the contract was entered into , a roofing contractor will be working under both regimes for some time. Check the contract date before assuming the 5 percent cap applies.
Retention is a working-capital commitment. Five percent of a $900,000 annual commercial volume is $45,000 permanently out in the field. Budget it as such (Section 9.1).
3. Prompt Payment Deadlines
Payment flow Deadline Penalty
Prime or sub → subcontractor , progress payment (public or private) 7 days after receipt (B&P § 7108.5) 2 percent per month of the amount due, plus attorney's fees and costs to the prevailing party
Owner → direct contractor , private progress payment Per Civil Code prompt payment provisions, commonly within 30 days of demand 2 percent per month plus attorney's fees
Owner → direct contractor , private retention Within 45 days after completion of the work of improvement 2 percent per month plus attorney's fees
Direct contractor → subcontractor , retention Within 10 days after receipt of retention from the owner 2 percent per month plus attorney's fees
Public entity → contractor , retention Within 60 days after the date of completion (PCC § 7107) 2 percent per month plus attorney's fees
The 2 percent per month is a penalty, not interest — it runs in addition to the amount owed, and the fee-shifting provision is what makes these claims worth bringing.
4. Good Faith Disputes and Lawful Withholding
Prompt payment law does not require paying disputed money. B&P § 7108.5 provides that where there is a good faith dispute over all or part of a progress payment, the paying party may withhold no more than 150 percent of the disputed amount .
Two failure modes:
Withholding too much. Holding the entire $60,000 payment over a $5,000 punch item exceeds 150 percent of $5,000 and exposes the withholder to the penalty and attorney's fees.
Calling a preference a dispute. A good faith dispute needs a documented basis — a defect, a non-conforming product, a failure to furnish releases. "Cash is tight this month" is not a dispute.
On public works, a public entity may withhold 150 percent of the value of disputed work from the final payment under PCC § 7107(c).
5. Payment and the Lien Clock
Payment administration and lien preservation are the same job. Serve the 20-day preliminary notice on schedule (Section 11.3). Calendar the lien recording deadline the day the work starts — 60 days for a direct contractor and 30 days for a subcontractor after a recorded Notice of Completion, or 90 days from completion if none is recorded. Calendar the 90-day foreclosure deadline the day the lien is recorded. On public works, the remedies are the payment bond and the public stop payment notice , because a lien cannot attach to public property.
Use the statutory releases correctly. Sign a conditional release when submitting a billing, and an unconditional release only after the payment has actually cleared the bank. An unconditional release signed against a check that later bounces has released the lien rights anyway.
6. Pay-If-Paid and Pay-When-Paid
A pay-when-paid clause addresses timing — the sub is paid within a reasonable time after the prime is paid — and is generally enforceable as a timing mechanism. A pay-if-paid clause tries to make the owner's payment a condition precedent , shifting the risk of owner insolvency onto the subcontractor. California courts have held that a pay-if-paid clause cannot be used to defeat a subcontractor's mechanics lien rights , which are constitutionally grounded and cannot be waived in advance. Read the clause before signing, and never rely on it as a reason to skip the preliminary notice.