Study guide

13.1 Prevailing Wage, DIR Registration, and Certified Payroll

California C-39 Roofing Contractor Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Planning, Codes, and Roofing Estimating

1.1 California Building Codes, Title 24 Energy Standards, and Plan Reading 1.2 Roof Geometry, Area Calculations, and Pitch Multipliers 1.3 Material Takeoffs, Squares, and Waste Calculations 1.4 Roof System Selection, Specifications, Permits, and Project Scheduling 1.5 Labor Production Rates, Overhead, Profit, and Roofing Bid Pricing

2 Chapter 2: Job Site Preparation and Substrate Remediation

2.1 Jobsite Protection, Material Staging, and Temporary Weatherproofing 2.2 Tear-Off Procedures, Overlay Limitations, and Hazardous Materials 2.3 Roof Deck Inspection, Substrate Preparation, and Sheathing Repairs

3 Chapter 3: Low-Slope Roof Systems — Built-Up, Modified Bitumen, and Single-Ply

3.1 Built-Up Roofing (BUR) Systems, Felts, and Hot Bitumen Application 3.2 Modified Bitumen Membrane Systems (APP vs. SBS) and Installation 3.3 Single-Ply Roofing Membranes (TPO, PVC, EPDM) and Seaming Methods

4 Chapter 4: Low-Slope Roof Systems — SPF, Coatings, Flashings, and Maintenance

4.1 Spray Polyurethane Foam (SPF) and Liquid-Applied Protective Coatings 4.2 Low-Slope Drainage, Perimeters, Penetration Flashings, and Scuppers 4.3 Low-Slope Diagnostics, Blister Repairs, and Preventative Maintenance

5 Chapter 5: Steep-Slope Roofing — Flashing, Underlayment, and Ventilation

5.1 Steep-Slope Underlayments, Felt Grades, and Self-Adhering Ice/Water Barriers 5.2 Flashing Details: Valleys, Drip Edges, Step Flashing, Aprons, and Crickets 5.3 Attic and Roof Ventilation: NFVA Requirements, Vent Types, and Airflow Balance

6 Chapter 6: Steep-Slope Roofing — Materials, Installation, and Repair

6.1 Asphalt Shingle Installation, Fastening Patterns, and Wind/Slope Requirements 6.2 Concrete and Clay Tile Roofing (TRI Standards, Battens, and Fastening) 6.3 Standing Seam Metal Panels, Wood Shakes, Slate, and Steep-Slope Repairs 6.4 Steep-Slope Leak Diagnosis, Targeted Repairs, and the Repair-or-Replace Decision

7 Chapter 7: California Roofing Safety — Cal/OSHA, Fall Protection, and Hazards

7.1 Cal/OSHA Fall Protection: Residential Roofing (§1731), Roof Hazards (§1730), and PFAS 7.2 Cal/OSHA Ladder Safety, Scaffold Erection, and Power Line Clearance 7.3 Heat Illness Prevention (CCR §3395), Hot Asphalt Safety, and Personnel PPE 7.4 Injury and Illness Prevention Program, Safety Training, Recordkeeping, and Cal/OSHA Reporting 7.5 Hazard Communication, Asbestos, Lead, and Silica: Managing Unknown Materials

8 Chapter 8: CSLB Licensing Law and Business Organization

8.1 CSLB Licensing Classifications, Bond Requirements, and License Law 8.2 Business Entity Choice, Personnel of Record, and Qualifier Responsibilities 8.3 Advertising Rules, Home Improvement Salespersons, and Subcontracting

9 Chapter 9: Business Finances, Financial Reporting, and Taxes

9.1 Cash Management, Job Costing, and Working Capital 9.2 Budgeting, Business Planning, and Break-Even Analysis 9.3 Financial Reporting: Statements, Accounting Methods, and Key Ratios 9.4 Federal and California Taxes for Roofing Contractors

10 Chapter 10: Employment Requirements, Supervision, and Payroll

10.1 Hiring: Worker Classification, Verification, and New-Hire Reporting 10.2 Supervising and Training Employees 10.3 Performance Evaluation, Personnel Records, and Termination 10.4 California Payroll: Wages, Overtime, Meal and Rest Periods, and Deposits

11 Chapter 11: Insurance, Bonds, and Payment Remedies

11.1 Workers' Compensation Insurance for California Roofing Contractors 11.2 Business Insurance and Surety Bonds 11.3 California Mechanics Lien Law, 20-Day Preliminary Notices, and Lien Waivers

12 Chapter 12: Contract Requirements, Bidding, and Project Execution

12.1 California Roofing Contracts, Home Improvement Law (B&P §7159), and Warranties 12.2 Bidding Practices, Bid Documents, and Competitive Bidding Law 12.3 Job Cost Control and Change Order Management 12.4 Project Organization, Scheduling, and Documentation 12.5 Payments: Progress Payments, Retention, and California Prompt Payment Law

13 Chapter 13: Public Works Roofing Projects

13.1 Prevailing Wage, DIR Registration, and Certified Payroll 13.2 Public Works Bonding and Insurance Requirements

13.1 Prevailing Wage, DIR Registration, and Certified Payroll

Key Takeaways Explain This Topic AI

A contractor must be registered with the California Department of Industrial Relations to bid on or perform public works, and registration runs by fiscal year from July 1 to June 30 at a fee of $400 per year.

Certified payroll reporting and DIR registration requirements are tied to project thresholds of more than $25,000 for construction work and more than $15,000 for maintenance work.

The prevailing wage is the general prevailing rate of per diem wages determined by the Director of Industrial Relations for the craft and the county, and it includes the basic hourly rate plus employer payments for fringe benefits.

Prevailing wage overtime follows the applicable wage determination rather than the contractor's ordinary practice, and the determination governs shift differentials, travel and subsistence, and holiday pay.

Certified payroll records must be submitted to the Labor Commissioner through the DIR electronic reporting system, and penalties for underpaying prevailing wages include back wages plus statutory penalties per worker per day plus liquidated damages.

Last updated: September 2026

Prevailing Wage, DIR Registration, and Certified Payroll

Quick Answer: If a roofing job is paid for in whole or part with public funds , it is a public work and three obligations attach at once: the contractor must be registered with the DIR (fiscal year July 1 to June 30, $400 per year , with one-, two-, and three-year options at $400, $800, and $1,200); every worker must be paid the general prevailing rate of per diem wages determined by the Director of Industrial Relations for the craft and the county ; and certified payroll records must be filed electronically with the Labor Commissioner. Registration and certified payroll obligations key off project thresholds of more than $25,000 for construction and more than $15,000 for maintenance .

Public Works is 5 percent of the Law and Business exam. Small weight, high stakes — the penalties dwarf the margin on a roofing job.

1. When Is a Roofing Job a Public Work?

A public work is generally construction, alteration, demolition, installation, repair, or maintenance work done under contract and paid for in whole or in part out of public funds . That includes:

  • School district and community college reroofing
  • City, county, and state facility roofs
  • Special district buildings — water, fire, transit

Housing and other privately-built projects that receive public subsidy or financing, which is a trap: a private-looking job can be a public work because of its funding source

Read the bid documents. If they reference prevailing wage, DIR registration, certified payroll, or Labor Code § 1720, the answer is yes. When in doubt, ask the awarding body in writing.

2. DIR Public Works Contractor Registration

Who: every contractor and subcontractor that bids on, is listed on a bid for, or performs public works.

Term: by fiscal year , July 1 through June 30. Contractors may register or renew for one, two, or three fiscal years at $400, $800, or $1,200 .

Effect of not registering: an unregistered contractor's bid is generally non-responsive, and a prime that uses an unregistered subcontractor is exposed to penalties.

Small project exemption: registration and the related reporting obligations are tied to project thresholds of more than $25,000 for construction work and more than $15,000 for maintenance work.

Note on currency: as of July 1, 2026 the Director may adjust the annual registration and renewal fees by publishing them on the DIR website without formal rulemaking. Confirm the current amount at registration rather than relying on a figure from a prior year.

3. Reading and Applying a Prevailing Wage Determination

The general prevailing rate of per diem wages is determined by the Director of Industrial Relations by craft or classification and by county , and it is not a single number. A determination states:

  • Component What it is
  • Basic hourly rate The straight-time wage that must be paid to the worker
  • Health and welfare Employer payment per hour
  • Pension Employer payment per hour
  • Vacation and holiday Employer payment per hour
  • Training Employer payment per hour, which funds approved apprenticeship programs
  • Other Additional employer payments specified by the determination
  • Total hourly Basic rate plus all employer payments

Fringe benefits may be paid in cash or to a bona fide plan. A non-union roofing contractor commonly pays the entire total as wages; a contractor with a qualifying plan credits the plan contributions against the fringe portion. What is not permitted is paying only the basic hourly rate and ignoring the employer payments.

Overtime follows the determination, not your handbook. The determination specifies the overtime and holiday rules for the craft — which shifts, which days, and at what multiple. It may differ from the general California daily overtime rules in Section 10.4, and the determination governs on the public job.

Other determination-driven items: shift differentials, travel and subsistence, and the specific holidays recognized.

Classification matters. A worker performing roofing work is paid the roofer determination for that county. Paying a laborer rate for roofing work is a classic underpayment finding.

4. Apprenticeship

Public works contracts above the statutory threshold carry apprenticeship obligations: submit the contract award information to the applicable apprenticeship committees, employ apprentices at the required ratio of apprentice hours to journeyman hours for the craft, and pay the training fund contribution stated in the determination (or to the California Apprenticeship Council where no approved program applies). Failure to request dispatch, or failure to employ the required ratio, is its own penalty category.

5. Certified Payroll Records

What: for each worker on the public job, each pay period — name and address, an identifier, classification, straight-time and overtime hours, the rate paid, fringe payments and to whom, deductions, and net pay — certified as true under penalty of perjury.

How: submitted to the Labor Commissioner through the DIR electronic certified payroll reporting system , and furnished to the awarding body on request.

When: on the schedule the project and the DIR system require, typically weekly or monthly; records must also be available for inspection.

Retention: keep the underlying payroll records at least three years, consistent with Labor Code § 1174.

Non-reporting has its own penalties , independent of whether the workers were actually paid correctly. A contractor that paid every dollar of prevailing wage and failed to file is still exposed.

6. Penalties for Getting It Wrong

Violation Consequence

Underpayment of prevailing wages Back wages to each worker, plus statutory penalties per worker per day of underpayment, plus liquidated damages where wages remain unpaid after the statutory period

  • Failure to pay overtime at the determination rate Separate per-worker, per-day penalties
  • Failure to submit certified payroll Per-day penalties, independent of wage compliance
  • Apprenticeship violations Per-day penalties
  • Working unregistered Per-day penalties for the contractor and for the prime that used it

Repeat or willful violations Debarment — ineligibility to bid on or be awarded public works for a period of years

Withholding from progress payments. The awarding body may withhold from payments to cover assessed wages and penalties, which means the money is gone before the dispute is resolved.

Debarment is the real risk. A roofing contractor whose business depends on school district work and loses the ability to bid for three years does not have a penalty problem; it has an existence problem. Price the compliance cost into the bid — accurate classification, correct fringe handling, apprentice dispatch, and someone who owns the certified payroll filing every week.