Study guide

15.2 Disinfecting Storage Reservoirs (C652) & Wells (C654)

California Water/Wastewater Operator Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: California Water Regulatory Framework & Certification Ladders

1.1 State Water Board & Regional Boards Structure 1.2 Drinking Water Certification: T1-T5 & D1-D5 Requirements 1.3 Wastewater Certification: Grades I-V & OIT Requirements 1.4 Safe Drinking Water Standards, MCLs & Emerging Contaminants 1.5 California Waterworks Standards (Title 22, Chapter 16) 1.6 Public Water System Types, Permits & the Sanitary Survey

2 Chapter 2: California Water Rights, Title 22 & Environmental Policy

2.1 California Title 22 Recycled Water Standards 2.2 California Environmental Quality Act (CEQA) & Proposition 218 2.3 Water Rights & California Water Resources

3 Chapter 3: Drinking Water Source Quality & Coagulation/Flocculation

3.1 Source Water Quality & Watershed Management 3.2 Coagulation Chemistry & Flash Mixing 3.3 Flocculation & Jar Testing 3.4 Wells, Aquifers & Groundwater Hydraulics 3.5 Raw Water Storage, Clearwells & Reservoir Management

4 Chapter 4: Clarification & Granular Media Filtration

4.1 Sedimentation & Advanced Clarification 4.2 Granular Media Filtration Mechanics & Media Types 4.3 Filter Operation, Backwash Cycles & SWTR Compliance

5 Chapter 5: Disinfection, Oxidation & Advanced Water Treatment

5.1 Chlorination Chemistry & Breakpoint Curves 5.2 Disinfection Kinetics & CT Calculations 5.3 Alternative Disinfection: Ozone, UV & Chlorine Dioxide 5.4 Advanced Treatment: Membranes, AOP & PFAS Adsorption 5.5 Chloramination & Nitrification Control 5.6 Iron & Manganese Removal 5.7 Fluoridation Practice & Compliance 5.8 Corrosion Control Treatment & Water Stability 5.9 Taste & Odor Control and Algal Toxin Management

6 Chapter 6: Wastewater Preliminary & Primary Treatment

6.1 Preliminary Treatment: Screening & Grit Removal 6.2 Primary Clarification Operations 6.3 Primary Sludge Characteristics & Pumping 6.4 Stabilization Ponds, Lagoons & Small-Plant Processes

7 Chapter 7: Secondary Biological Treatment & Activated Sludge

7.1 Activated Sludge Process Fundamentals 7.2 Process Control Parameters: F/M, MCRT & SVI 7.3 Activated Sludge Microbiology & Troubleshooting 7.4 Fixed-Film & Hybrid Biological Processes

8 Chapter 8: Biological Nutrient Removal, Water Reuse & Solids Handling

8.1 Biological Nitrogen Removal: Nitrification & Denitrification 8.2 Biological Phosphorus Removal (EBPR) & Chemical Precipitation 8.3 Anaerobic & Aerobic Digestion 8.4 Sludge Thickening, Dewatering & Biosolids Disposal 8.5 Wastewater Disinfection: Chlorination, Dechlorination & UV

9 Chapter 9: Distribution Systems, Collection Networks & Hydraulics

9.1 Hydraulics, Pressure & Flow Dynamics 9.2 Centrifugal Pumps, Motors & VFDs 9.3 Distribution Network Infrastructure & Cross-Connection Control 9.4 Wastewater Collection Systems, SSMP & FOG Management

10 Chapter 10: Laboratory Analytics, Safety & Water Math

10.1 Water & Wastewater Laboratory Methods 10.2 Laboratory Quality Assurance & Regulatory Reporting 10.3 Chemical Safety, Hazardous Gases & Confined Space 10.4 Essential Water & Wastewater Math for Operators

11 Chapter 11: Federal & California Drinking Water Rules

11.1 The Revised Total Coliform Rule & Assessments 11.2 The Lead and Copper Rule and Service Line Replacement 11.3 Surface Water Treatment Rules & Log Removal Credit 11.4 Stage 1 & Stage 2 Disinfection Byproduct Rules 11.5 Secondary MCLs, Notification Levels & Response Levels 11.6 Public Notification, Consumer Confidence Reports & Recordkeeping

12 Chapter 12: Distribution System Design, Demand & Hydraulics

12.1 System Layout, Pressure Zones & Distribution Maps 12.2 Water Demand, Peaking Factors & Fire Flow 12.3 Distribution Storage: Types, Sizing & Turnover 12.4 Head Loss, C-Factor & Distribution Hydraulic Calculations 12.5 Water Hammer, Surge Control & Air Management

13 Chapter 13: Distribution Equipment Operation, Maintenance & Inspection

13.1 Valves: Types, Operation & Exercising Programs 13.2 Fire Hydrants: Types, Testing & Maintenance 13.3 Water Meters: Types, Accuracy & Meter Management 13.4 Instrumentation, In-Line Sensors, Telemetry & SCADA 13.5 Electrical Systems, Motors & Standby Generators 13.6 External Corrosion, Cathodic Protection & Asset Inspection

14 Chapter 14: Water Mains, Piping & Field Construction

14.1 Pipe Materials & Pipe Selection 14.2 Joints, Fittings, Thrust Restraint & Bedding 14.3 Main Installation, Tapping & Service Line Installation 14.4 Leak Detection, Water Loss Auditing & Main Repair 14.5 Main Cleaning & Maintenance: Flushing, Pigging & Lining 14.6 Excavation, Trench Safety & Utility Locating

15 Chapter 15: Disinfecting Distribution Facilities & Maintaining Water Quality

15.1 Water Main Disinfection (AWWA C651) 15.2 Disinfecting Storage Reservoirs (C652) & Wells (C654) 15.3 Maintaining Distribution Water Quality: Residual, Biofilm & Discolored Water 15.4 Cross-Connection Control Program Administration & Device Testing

16 Chapter 16: Plant Equipment, Chemical Feed & Maintenance

16.1 Chemical Feed Systems: Metering Pumps, Dry Feeders & Calibration 16.2 Gas Chlorination Equipment & Hypochlorite Systems 16.3 Blowers, Compressors & Aeration Equipment 16.4 Flow Measurement Devices: Meters, Weirs & Flumes 16.5 Preventive Maintenance, CMMS & Asset Management

17 Chapter 17: Utility Management, Administration & Emergency Response

17.1 Planning, Organizing, Directing & Controlling a Utility Work Group 17.2 Budgets, Water Rates & Financial Management 17.3 Operator Training, Staffing & Safety Program Development 17.4 Energy Management & Optimization 17.5 Emergency Response Planning, Risk & Resilience & Security 17.6 Water Conservation Planning & Drought Response

18 Chapter 18: Applied Operator Mathematics Workshop

18.1 The Exam Conversion Sheet, Units & Dimensional Analysis 18.2 Distribution & Hydraulic Math Workshop 18.3 Treatment & Wastewater Process Math Workshop

15.2 Disinfecting Storage Reservoirs (C652) & Wells (C654)

Key Takeaways Explain This Topic AI

Storage Reservoir Disinfection and Well Disinfection are two separately named sub-topics in the SWRCB distribution Disinfection category.

22 CCR 64582 incorporates AWWA C652-02 for reservoirs and 22 CCR 64583 incorporates AWWA C654-03 for wells.

AWWA C652 offers three methods, including spraying or brushing surfaces with 200 mg/L solution and filling the tank with 10 mg/L water held 24 hours.

Section 64583 requires sampling a new or repaired well, or one out of operation for more than three months, before use, with disinfection only if coliform is detected.

For both reservoirs and wells, a coliform detection means resampling and submitting results to the State Board for review and approval before return to service.

Last updated: November 2026

Two Standards, Two Triggers

  • Reservoirs (22 CCR 64582) Wells (22 CCR 64583)
  • Standard incorporated AWWA C652-02 AWWA C654-03

Applies when Newly installed, or taken out of service for repair or inspection New, repaired, or not in operation for more than three months

  • First required step Disinfect and sample Sample for bacteriological quality prior to use
  • Disinfection trigger Always, before return to service Only if coliform is detected

If coliform is found Resample; submit results to the State Board for review and approval before placing in service Disinfect per C654-03, resample; submit results to the State Board for review and approval before operation

Important

The trigger logic is reversed between mains and wells. A main is always disinfected before use. A well is sampled first , and disinfection is required only if coliform is detected. Reservoirs follow the main pattern - disinfect, then sample. The three-month out-of-service threshold applies to wells and is a frequent exam distractor.

  • AWWA C652 Reservoir Disinfection Methods
  • Method 1 - Fill and Hold

The tank is filled to overflowing with potable water chlorinated to a free chlorine residual of at least 10 mg/L , held for at least 24 hours , and must retain a residual of at least 10 mg/L at the end of the period. The water may then be flushed to waste (with neutralization) or, if the residual has been reduced to normal distribution levels and quality is acceptable, may be usable.

  • Simple and thorough - every surface below the water line is contacted
  • Uses a full tank volume of heavily chlorinated water, which must then be neutralized and disposed of
  • Method 2 - Spray or Brush

All interior surfaces that will contact stored water are sprayed or brushed with a solution of at least 200 mg/L available chlorine , with the surfaces kept wet for at least 30 minutes . The tank is then filled with potable water, and the water may be placed in service after bacteriological clearance.

  • Uses far less chlorine and produces far less waste
  • Requires people inside the tank , which makes it a permit-required confined space entry with all that entails
  • Requires thoroughness; any missed surface is undisinfected
  • Method 3 - Partial Fill and Hold

A portion of the tank is filled with water chlorinated to a high concentration , held for a specified retention period so that the chlorinated water contacts the lower interior surfaces, and the facility is then filled to the operating level with potable water and held again so that the final mixed water carries a specified residual . The exact fill fraction, dose, retention times, and final residual are set by the edition of C652 in force - verify them in the standard your specification cites rather than from memory.

  • A middle ground between Methods 1 and 2 in chlorine use and waste volume
  • Bacteriological Clearance

After disinfection and refilling, samples are collected and must be coliform-negative . If coliform is detected, 22 CCR 64582 requires that the reservoir be resampled and that the results be submitted to the State Board for review and approval before the reservoir is placed in service. Sample bottles must contain sodium thiosulfate, and analysis must be at an ELAP-certified laboratory.

Tank Entry Safety

Tank interiors are permit-required confined spaces , and tank work has killed operators:

Atmospheric testing before and continuously during entry - oxygen, flammability, toxics. Chlorine vapor accumulates in the headspace of a tank being disinfected and in a tank recently coated

  • Coating solvent vapors are both toxic and flammable; a recoated tank can hold an explosive atmosphere for days
  • Forced-air ventilation throughout the entry
  • Attendant stationed outside , in continuous communication, staying outside until relieved
  • Retrieval system - full body harness and mechanical retrieval for vertical entries
  • Lockout/tagout of fill valves, drains, mixers, and cathodic protection rectifiers
  • Fall protection on roofs and ladders; slippery interior surfaces
  • Never enter a tank alone, and never enter on the strength of a single "it smells fine" judgment
  • AWWA C654 Well Disinfection
  • When It Applies

Under 22 CCR 64583, a new or repaired well, or a well that has not been in operation for more than three months, shall be sampled for bacteriological quality prior to use. If coliform is detected, the well is disinfected per AWWA C654-03 and resampled, with results submitted to the State Board for review and approval before the well is placed in operation.

Calculating the Chlorine Charge

Well disinfection requires knowing the volume of water standing in the casing plus an allowance for the gravel pack and the formation. Gallons per foot = 0.0408 × D ( in ) 2 \text{Gallons per foot} = 0.0408 \times D^{2}_{(\text{in})} Gallons per foot = 0.0408 × D ( in ) 2 ​

  • Casing diameter Gallons per foot
  • 6 in 1.47
  • 8 in 2.61
  • 10 in 4.08
  • 12 in 5.88
  • 16 in 10.44
  • 18 in 13.22

Worked example. A 12-inch well has 240 feet of water standing in the casing and will be dosed to 100 mg/L using 65 percent calcium hypochlorite .

  • Volume = 5.88 x 240 = 1,411 gallons = 0.001411 MG
  • Chlorine required = 0.001411 x 100 x 8.34 = 1.18 lb Calcium hypochlorite = 1.18 / 0.65 = 1.81 lb

In practice the dose is increased to account for the gravel pack and the formation immediately around the screen , and the standard also addresses higher doses (often 100 to 500 mg/L) depending on the situation and whether biofouling is being addressed.

Procedure

Clean the well - remove oil, grease, drilling mud, and debris; the presence of organic material consumes chlorine and shields organisms

Introduce the chlorine solution so it contacts the entire water column , using a tremie pipe or by circulating, not by simply pouring it down the casing where it stratifies at the bottom

Agitate and circulate - surge the well, or recirculate with the pump, so the solution enters the gravel pack and the near-well formation

Hold for the specified contact period, commonly at least 2 to 24 hours depending on method and dose

Pump to waste until the residual is at or below the distribution system level; neutralize the discharge before it reaches a storm drain or watercourse, and be aware that the discharge may also carry turbidity and sediment

Sample for bacteriological quality , and repeat until the results are acceptable

Submit results to the State Board if coliform had been detected, and obtain approval before returning the well to service

Disinfecting the Pump and Appurtenances

The pump, column, discharge head, sounding tube, and any tools that entered the well must also be disinfected - normally by swabbing or spraying with a 200 mg/L solution or dipping before installation. A newly rebuilt pump lowered into a disinfected well with grease and shop dirt on it recontaminates the well immediately.