Study guide

13.1 Valves: Types, Operation & Exercising Programs

California Water/Wastewater Operator Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: California Water Regulatory Framework & Certification Ladders

1.1 State Water Board & Regional Boards Structure 1.2 Drinking Water Certification: T1-T5 & D1-D5 Requirements 1.3 Wastewater Certification: Grades I-V & OIT Requirements 1.4 Safe Drinking Water Standards, MCLs & Emerging Contaminants 1.5 California Waterworks Standards (Title 22, Chapter 16) 1.6 Public Water System Types, Permits & the Sanitary Survey

2 Chapter 2: California Water Rights, Title 22 & Environmental Policy

2.1 California Title 22 Recycled Water Standards 2.2 California Environmental Quality Act (CEQA) & Proposition 218 2.3 Water Rights & California Water Resources

3 Chapter 3: Drinking Water Source Quality & Coagulation/Flocculation

3.1 Source Water Quality & Watershed Management 3.2 Coagulation Chemistry & Flash Mixing 3.3 Flocculation & Jar Testing 3.4 Wells, Aquifers & Groundwater Hydraulics 3.5 Raw Water Storage, Clearwells & Reservoir Management

4 Chapter 4: Clarification & Granular Media Filtration

4.1 Sedimentation & Advanced Clarification 4.2 Granular Media Filtration Mechanics & Media Types 4.3 Filter Operation, Backwash Cycles & SWTR Compliance

5 Chapter 5: Disinfection, Oxidation & Advanced Water Treatment

5.1 Chlorination Chemistry & Breakpoint Curves 5.2 Disinfection Kinetics & CT Calculations 5.3 Alternative Disinfection: Ozone, UV & Chlorine Dioxide 5.4 Advanced Treatment: Membranes, AOP & PFAS Adsorption 5.5 Chloramination & Nitrification Control 5.6 Iron & Manganese Removal 5.7 Fluoridation Practice & Compliance 5.8 Corrosion Control Treatment & Water Stability 5.9 Taste & Odor Control and Algal Toxin Management

6 Chapter 6: Wastewater Preliminary & Primary Treatment

6.1 Preliminary Treatment: Screening & Grit Removal 6.2 Primary Clarification Operations 6.3 Primary Sludge Characteristics & Pumping 6.4 Stabilization Ponds, Lagoons & Small-Plant Processes

7 Chapter 7: Secondary Biological Treatment & Activated Sludge

7.1 Activated Sludge Process Fundamentals 7.2 Process Control Parameters: F/M, MCRT & SVI 7.3 Activated Sludge Microbiology & Troubleshooting 7.4 Fixed-Film & Hybrid Biological Processes

8 Chapter 8: Biological Nutrient Removal, Water Reuse & Solids Handling

8.1 Biological Nitrogen Removal: Nitrification & Denitrification 8.2 Biological Phosphorus Removal (EBPR) & Chemical Precipitation 8.3 Anaerobic & Aerobic Digestion 8.4 Sludge Thickening, Dewatering & Biosolids Disposal 8.5 Wastewater Disinfection: Chlorination, Dechlorination & UV

9 Chapter 9: Distribution Systems, Collection Networks & Hydraulics

9.1 Hydraulics, Pressure & Flow Dynamics 9.2 Centrifugal Pumps, Motors & VFDs 9.3 Distribution Network Infrastructure & Cross-Connection Control 9.4 Wastewater Collection Systems, SSMP & FOG Management

10 Chapter 10: Laboratory Analytics, Safety & Water Math

10.1 Water & Wastewater Laboratory Methods 10.2 Laboratory Quality Assurance & Regulatory Reporting 10.3 Chemical Safety, Hazardous Gases & Confined Space 10.4 Essential Water & Wastewater Math for Operators

11 Chapter 11: Federal & California Drinking Water Rules

11.1 The Revised Total Coliform Rule & Assessments 11.2 The Lead and Copper Rule and Service Line Replacement 11.3 Surface Water Treatment Rules & Log Removal Credit 11.4 Stage 1 & Stage 2 Disinfection Byproduct Rules 11.5 Secondary MCLs, Notification Levels & Response Levels 11.6 Public Notification, Consumer Confidence Reports & Recordkeeping

12 Chapter 12: Distribution System Design, Demand & Hydraulics

12.1 System Layout, Pressure Zones & Distribution Maps 12.2 Water Demand, Peaking Factors & Fire Flow 12.3 Distribution Storage: Types, Sizing & Turnover 12.4 Head Loss, C-Factor & Distribution Hydraulic Calculations 12.5 Water Hammer, Surge Control & Air Management

13 Chapter 13: Distribution Equipment Operation, Maintenance & Inspection

13.1 Valves: Types, Operation & Exercising Programs 13.2 Fire Hydrants: Types, Testing & Maintenance 13.3 Water Meters: Types, Accuracy & Meter Management 13.4 Instrumentation, In-Line Sensors, Telemetry & SCADA 13.5 Electrical Systems, Motors & Standby Generators 13.6 External Corrosion, Cathodic Protection & Asset Inspection

14 Chapter 14: Water Mains, Piping & Field Construction

14.1 Pipe Materials & Pipe Selection 14.2 Joints, Fittings, Thrust Restraint & Bedding 14.3 Main Installation, Tapping & Service Line Installation 14.4 Leak Detection, Water Loss Auditing & Main Repair 14.5 Main Cleaning & Maintenance: Flushing, Pigging & Lining 14.6 Excavation, Trench Safety & Utility Locating

15 Chapter 15: Disinfecting Distribution Facilities & Maintaining Water Quality

15.1 Water Main Disinfection (AWWA C651) 15.2 Disinfecting Storage Reservoirs (C652) & Wells (C654) 15.3 Maintaining Distribution Water Quality: Residual, Biofilm & Discolored Water 15.4 Cross-Connection Control Program Administration & Device Testing

16 Chapter 16: Plant Equipment, Chemical Feed & Maintenance

16.1 Chemical Feed Systems: Metering Pumps, Dry Feeders & Calibration 16.2 Gas Chlorination Equipment & Hypochlorite Systems 16.3 Blowers, Compressors & Aeration Equipment 16.4 Flow Measurement Devices: Meters, Weirs & Flumes 16.5 Preventive Maintenance, CMMS & Asset Management

17 Chapter 17: Utility Management, Administration & Emergency Response

17.1 Planning, Organizing, Directing & Controlling a Utility Work Group 17.2 Budgets, Water Rates & Financial Management 17.3 Operator Training, Staffing & Safety Program Development 17.4 Energy Management & Optimization 17.5 Emergency Response Planning, Risk & Resilience & Security 17.6 Water Conservation Planning & Drought Response

18 Chapter 18: Applied Operator Mathematics Workshop

18.1 The Exam Conversion Sheet, Units & Dimensional Analysis 18.2 Distribution & Hydraulic Math Workshop 18.3 Treatment & Wastewater Process Math Workshop

13.1 Valves: Types, Operation & Exercising Programs

Key Takeaways Explain This Topic AI

Valves is a named sub-topic in the Equipment Operation, Maintenance and Inspections category, which carries 20 to 25 questions at every distribution grade.

Gate valves are for isolation and are operated fully open or fully closed; butterfly valves can throttle but obstruct pigs and swabs.

22 CCR 64577 requires isolation valves no more than 1,320 feet apart on mains 12 inches or smaller, within 100 feet of each tee or cross, and between the main and each fire hydrant.

Most water valves close clockwise, but left-hand-open valves exist and must be identified in records, and the number of turns to close should be recorded for every valve.

A valve exercising program that operates every valve on a one to three year cycle is the only way to know a valve will actually close during an emergency.

Last updated: September 2026

Valve Types and Applications

Valve type Primary use Throttling? Notes

Gate valve Isolation No - operate fully open or fully closed Most common distribution valve; low head loss open; partial opening erodes the disc and seat

Butterfly valve Isolation and throttling ; large diameters Yes Compact and cheap in large sizes; the disc obstructs pigs, swabs, and cleaning tools

  • Ball valve Isolation, small sizes and services Limited Full-port versions give unobstructed flow
  • Plug valve Isolation, sludge and wastewater service Limited Eccentric plug versions handle solids
  • Globe valve Throttling and control Yes High head loss; the body of most automatic control valves

Check valve (swing, silent/spring, dual-disc) Prevent reverse flow - Swing checks slam; spring-assisted "silent" checks close before flow reverses

Pressure reducing valve (PRV) Hold a set downstream pressure Automatic Diaphragm-actuated globe body with a pilot

  • Pressure sustaining/relief valve Hold a minimum upstream pressure, or relieve surge Automatic
  • Altitude valve Prevent tank overflow Automatic Two-way versions allow the tank to feed back
  • Air release / air-vacuum / combination valve Manage air at high points Automatic Required by 22 CCR 64576
  • Blowoff valve Drain and flush a dead end or low point - Must discharge with an air gap
  • Gate Valve Sub-Types

Resilient wedge (resilient seated) - the modern standard. A rubber-encapsulated wedge seals against a smooth, epoxy-coated body with a full unobstructed waterway ; no bottom groove to collect debris.

Double disc (metal seated) - older design with a bottom groove that accumulates sediment and rock, which is the classic reason a 60-year-old valve will not close the last inch.

California Spacing Requirements (22 CCR 64577)

At a minimum, isolation valves shall be installed on all new water mains:

No farther than 1,320 linear feet apart on mains 12 inches or less in diameter;

At each tee or crossing connection between mains 12 inches or less, within 100 feet of that tee or cross with the primary main; and

Between the water main and each fire hydrant served by the main.

Practical consequence: at a standard cross in a gridded system there should be valves on three or four legs , so a crew can isolate one block without shutting the intersection. Systems that installed valves only on the main run - a common 1950s and 1960s economy - discover during a break that isolating one segment blacks out a quarter of a neighborhood.

The hydrant isolation valve (item 3) is what allows a hydrant to be repaired or replaced without shutting down the main. A hydrant with no auxiliary valve is a documented deficiency.

Correct Operating Technique

Know the valve before you turn it. Size, type, number of turns to fully close, direction to close, and whether it is a boundary valve between pressure zones.

Locate and clean the valve box. Debris in the box is the reason keys slip and stems shear.

Count the turns. Record the actual count against the record count. A valve that closes in fewer turns than expected is obstructed ; one that never seats has a broken stem or wedge .

Operate slowly, especially the last quarter. Closing fast generates water hammer; the surge from a rapidly closed 12-inch valve can break a main elsewhere in the system.

Do not force a stuck valve. Excessive torque shears stems and breaks bonnets, turning a stuck valve into a dig. Use a valve exerciser with a torque limit , work the valve back and forth, and consider a valve-turning machine.

Reopen slowly and fully , then back off a quarter to half turn from the fully open position so a later operator can tell open from jammed and so thermal expansion does not lock the stem.

Flush and sample any segment that was depressurized before returning it to service.

Warning

Never leave a valve partially open as a throttling device. A gate valve throttled for weeks will wire-draw and erode at the disc and seat and may then never seal again. If throttling is needed, install a valve designed for it.

Valve Exercising

A valve exercising program operates every valve through its full travel on a scheduled cycle - commonly annually for critical and boundary valves and every one to three years for the rest . It is the only way to know a valve works.

What exercising accomplishes:

  • Verifies the valve closes - the moment you need that information is the worst possible moment to learn it
  • Breaks up scale and tuberculation on the disc and seat
  • Confirms and corrects the record - number of turns, direction, actual location
  • Finds buried and paved-over valves before the emergency

Reduces the isolated segment size during an actual break, which reduces customers out of service, the volume lost, and the length of main requiring disinfection

Records to keep for each valve: unique ID, location with GPS coordinates and ties to permanent features, size, type, manufacturer, year installed, direction to close, turns to close , last exercised date, condition notes, and any restriction such as boundary valve - do not operate without authorization .

Tip

The performance metric that matters is percentage of valves exercised on schedule and average number of customers affected per isolation . A system with excellent maps but no exercising program will still shut down four blocks to fix one service leak.

Common Failure Modes

  • Symptom Cause Response
  • Valve turns freely, never seats Broken stem or detached wedge Excavate and replace

Valve stops several turns short Debris in the bottom groove (double disc), rock, or tuberculation Work it back and forth; if it will not clear, excavate

Valve closes but the segment still holds pressure Wrong valve, unmapped feed, or a partially open valve elsewhere Systematic valve-by-valve check with pressure gauges on hydrants

Water rises in the valve box when operated Leaking stem packing or bonnet gasket Repack or replace

Valve box crushed or paved over Paving or heavy traffic Reset the box; a valve nobody can reach is a valve that does not exist

  • Valve buried under fill Grading changes Locate with valve records and a metal detector or GPR; extend the box
  • Excessive torque required Corrosion, misalignment, bent stem Do not force; excavate
  • Boundary and Control Valves

Two categories deserve locked-out handling:

Pressure zone boundary valves must be tagged and mapped. An accidental opening dumps a high zone into a low zone, blowing out customer plumbing and draining tanks.

Interties with neighboring agencies are normally closed and often have a backflow assembly and metering. Operating them requires coordination and, usually, a written agreement, because water quality from two different sources mixing at the boundary can cause red water, nitrification, or disinfectant incompatibility - notably chlorine meeting chloramine.

Finally, valve work is where cross-connection risk and contamination risk meet. Any main that has been depressurized must be treated as potentially contaminated: disinfect per AWWA C651-05 and sample for coliform before returning it to service, as 22 CCR 64580 requires.