12.1 Early Lease Buyout Valuation & Surrender Premium Formulas

Certified Commercial Investment Member CCIM

Track your progress as you read

Finished sections get a check mark.

1 Getting Started: The CCIM Designation & Comprehensive Exam

About the CCIM Comprehensive Exam

2 Chapter 1: Time Value of Money & Cash Flow Modeling

1.1 Core Time Value of Money Principles & Compounding Dynamics 1.2 Annuity Mechanics, Sinking Funds & Loan Amortization Mathematics 1.3 The CCIM Cash Flow Model: From Gross Potential Income to BTCF

3 Chapter 2: Debt Financing, Cash-on-Cash Return & Direct Capitalization

2.1 Debt Financing Metrics: DCR, LTV & Maximum Loan Sizing 2.2 Cash-on-Cash Return & First-Year Equity Dividend Rates 2.3 Direct Capitalization & Capitalization Rate Derivation

4 Chapter 3: Advanced Capitalization & Mortgage-Equity Valuation

3.1 Band of Investment Technique (Debt & Equity Components) 3.2 Mortgage-Equity Analysis & The Ellwood Formulation 3.3 Discounted Cash Flow (DCF) Modeling & Net Present Value (NPV)

5 Chapter 4: Yield Metrics & After-Tax Investment Analysis

4.1 Internal Rate of Return (IRR) Mechanics, Limitations & MIRR 4.2 Commercial Real Estate Tax Fundamentals & MACRS Cost Recovery 4.3 After-Tax Cash Flow (ATCF) & After-Tax Equity Reversion (ATER) 4.4 Capital Accumulation & the Annual Growth Rate of Capital (AGRC)

6 Chapter 5: Market Fundamentals & Economic Base Analysis

5.1 The CCIM Strategic Analysis Model & Market Delineation 5.2 Economic Base Theory: Basic vs. Non-Basic Employment Dynamics 5.3 Location Quotient (LQ) & Economic Base Multipliers

7 Chapter 6: Supply, Demand & Trade Area Dynamics

6.1 Supply Analysis: Inventory, Pipeline & Competitor Benchmarking 6.2 Demand Modeling, Absorption Metrics & Market Slack 6.3 Trade Area Delineation: Primary, Secondary & Tertiary Zones

8 Chapter 7: Demographics, Site Evaluation, Regulatory Due Diligence & Geospatial Analysis

7.1 Psychographic & Demographic Profiling with Esri Tapestry Segmentation 7.2 Physical Site Evaluation, Ingress/Egress & Accessibility 7.3 Zoning, Land-Use Entitlements & Environmental Screening 7.4 Geospatial Analysis: Intellisite, Drive-Time Trade Areas & Retail Gap Modeling

9 Chapter 8: Commercial Sector Market Analysis: Office, Industrial, Retail & Multifamily

8.1 Office Sector Dynamics: Space Utilization, Classes & Submarket Drivers 8.2 Industrial & Logistics Facilities: E-Commerce, Clear Heights & Intermodal Hubs 8.3 Retail Trade Analysis: Reilly's Law, Huff Gravity Model & Sales Thresholds 8.4 Multifamily Analytics: Demographics, Household Formation & Concession Impact

10 Chapter 9: User Foundations, Space Measurement & Commercial Lease Types

9.1 The User Perspective vs. The Investor Perspective 9.2 Space Measurement Standards: BOMA Usable vs. Rentable Area & Load Factors 9.3 Commercial Lease Types: Gross, Modified Gross, Single, Double & Triple Net

11 Chapter 10: Expense Allocations, Percentage Rent & Comparative Lease Analysis

10.1 Expense Stops, Base Year Adjustments & Operating Expense Escalations 10.2 Retail Percentage Rent, Natural & Unnatural Breakpoints 10.3 Comparative Lease Analysis: Effective Rent & Net Present Cost Modeling

12 Chapter 11: Lease vs. Purchase Analysis & Sale-Leaseback Transactions

11.1 Cost of Capital & Appropriate Discount Rates for User Decisions 11.2 Structuring the Lease vs. Purchase Decision Framework 11.3 Sale-Leaseback Mechanics, Underwriting & Capital Optimization

13 Chapter 12: Lease Buyouts, Accounting Standards (ASC 842) & Interest-Based Negotiations

12.1 Early Lease Buyout Valuation & Surrender Premium Formulas 12.2 Corporate Lease Accounting (ASC 842 / IFRS 16) & Balance Sheet Impact 12.3 Interest-Based Negotiations in Commercial Leasing

14 Chapter 13: The Investment Lifecycle, Annual Review & Capital Decisions

13.1 The Real Estate Investment Lifecycle & Holding Period Optimization 13.2 Annual Property Performance Auditing & Variance Analysis 13.3 Refinancing Decisions & Capital Extraction Analysis

15 Chapter 14: Renovations, Disposition Timing & Leverage Dynamics

14.1 Value-Add Renovation Underwriting & Incremental Yield 14.2 Optimal Disposition Timing & Marginal Rate of Return (MRR) Analysis 14.3 Leverage Dynamics: Positive, Neutral & Negative Leverage

16 Chapter 15: Risk Quantification, Sensitivity Analysis & 1031 Exchange Fundamentals

15.1 Risk Analysis Frameworks: Sensitivity, Scenario & Monte Carlo Modeling 15.2 IRC Section 1031 Tax-Deferred Exchange Rules, Deadlines & Boot 15.3 Advanced 1031 Structures: Reverse, Construction & Delaware Statutory Trusts

17 Chapter 16: Syndication Waterfalls, Portfolio Strategy & Investment Committee Due Diligence

16.1 Real Estate Syndication, Promote Structures & Waterfall Distributions 16.2 Modern Portfolio Theory (MPT) & Diversification in Commercial Real Estate 16.3 Investment Committee Due Diligence, Underwriting Packages & Synthesis

12.1 Early Lease Buyout Valuation & Surrender Premium Formulas

Key Takeaways Explain This Topic AI

A landlord's buyout fee floor reflects net economic damages: the present value of remaining contract rent minus the present value of replacement tenant mitigation rent, plus direct re-tenanting capital outlays and unamortized initial lease concessions.

The negotiation settlement zone (ZOPA) spans between the landlord's damage floor and the tenant's ceiling, which is the net present value of paying rent while dark minus net sublease recovery.

Subleasing and lease assignments do not release the original corporate tenant from primary contractual liability because privity of contract endures unless the landlord executes an explicit written novation.

A Right of First Refusal (ROFR) forces landlords to negotiate binding third-party terms subject to tenant preemption, chilling market interest; a Right of First Offer (ROFO) preserves marketing agility by requiring landlord notification prior to public marketing.

Unamortized tenant improvements and leasing commissions must be recovered using straight-line or annuity amortization based on the remaining unexpired lease term.

Last updated: September 2026

Early Lease Buyout Valuation & Surrender Premium Formulas

Note

Strategic User Restructuring : In commercial real estate user analysis, corporate space requirements fluctuate across business cycles. Mergers, acquisitions, technological shifts, and structural workforce changes frequently force occupiers to realign physical footprints years before contractual lease expiration. CCIM designees must master the financial modeling, legal mechanics, and restructuring strategies governing early buyouts, space contractions, and facility expansions.

Early Lease Termination Economics: Motivations & Market Drivers

An early lease buyout is a legally binding bilateral contract in which the landlord agrees to release the tenant from ongoing lease obligations in exchange for a negotiated cash settlement (a buyout fee or surrender premium). The motivations driving lease buyouts differ fundamentally across parties:

Tenant Motivations :

Operational Downsizing : Eliminating surplus overhead costs following corporate restructuring or head-count contractions.

Footprint Consolidation : Eliminating redundant facilities following corporate mergers and acquisitions.

Upgrading Facilities : Relocating to higher-quality Class-A premises to enhance employee productivity and talent recruitment.

Insolvency Mitigation : Avoiding catastrophic default and formal bankruptcy litigation by negotiating a controlled lease surrender.

Landlord Motivations :

Rising Market Recapture : Recapturing space in an escalating rental market where market rent substantially exceeds in-place contract rent, enabling the landlord to re-lease at a premium.

Credit Risk Elimination : Replacing a financially distressed tenant with a creditworthy, investment-grade corporate tenant.

Asset Redevelopment : Clearing entire floor plates or buildings to execute major capital renovations, conversions, or property disposition.

The CCIM Buyout Valuation Methodology: Net Economic Damages

Under contract law and CCIM financial standards, the analytical baseline for determining a lease buyout fee rests on quantifying the landlord's net economic damages . Under common law and statutory leasing doctrine, a landlord has an affirmative duty to mitigate damages by making commercially reasonable efforts to re-let vacated premises. Consequently, a landlord cannot simply demand the gross undiscounted sum of all remaining lease payments.

The landlord's minimum acceptable settlement—referred to as the Landlord Damage Floor —is calculated as follows: Landlord Buyout Fee (Floor) = PV ( Remaining Contract Rent ) − PV ( Replacement Mitigation Rent ) + PV ( Re-tenanting Capital Costs ) + Unamortized Concessions \text{Landlord Buyout Fee (Floor)} = \text{PV}(\text{Remaining Contract Rent}) - \text{PV}(\text{Replacement Mitigation Rent}) + \text{PV}(\text{Re-tenanting Capital Costs}) + \text{Unamortized Concessions} Landlord Buyout Fee (Floor) = PV ( Remaining Contract Rent ) − PV ( Replacement Mitigation Rent ) + PV ( Re-tenanting Capital Costs ) + Unamortized Concessions

Detailed Decomposition of Core Variables

PV of Remaining Contract Rent & Recoveries : The discounted present value of all contractual base rents and mandatory operating expense reimbursements (NNN pass-throughs or expense stop escalations) that the existing tenant is obligated to pay through the scheduled expiration date, discounted at the landlord's safe reinvestment rate or cost of debt.

PV of Replacement Mitigation Rent : The discounted present value of anticipated rental income collected from a replacement tenant following an estimated vacancy downtime period. This reflects the landlord's duty to mitigate damages in accordance with local submarket absorption velocity.

PV of Re-tenanting Capital Costs : The discounted capital outlays required to secure a replacement occupant, including turnkey Tenant Improvements (TIs), leasing commissions (LCs) paid to listing and procuring brokers, space demolition, space planning, and legal expenses.

Recovery of Unamortized Initial Lease Concessions : Landlords invest substantial capital upfront in TIs, free rent concessions, and leasing commissions, amortizing these costs over the initial lease term. Upon early termination, the unamortized balance represents unrecovered capital that must be repaid: Unamortized Concession = Initial Total Concession × ( Remaining Lease Term (Months) Total Initial Lease Term (Months) ) \text{Unamortized Concession} = \text{Initial Total Concession} \times \left( \frac{\text{Remaining Lease Term (Months)}}{\text{Total Initial Lease Term (Months)}} \right) Unamortized Concession = Initial Total Concession × ( Total Initial Lease Term (Months) Remaining Lease Term (Months) ​ )

Surrender Premiums & Landlord-Initiated Buyouts (Reverse Buyouts)

While tenants initiate most lease terminations, situations arise where the landlord initiates the buyout (a "reverse buyout"). In supply-constrained submarkets experiencing rapid rent escalation, an in-place tenant paying $25.00/RSF under a long-term lease may occupy space that commands $45.00/RSF on the open market. Alternatively, a landlord may require vacant possession to sell the asset to an owner-user or raze the structure for high-density redevelopment.

In a landlord-initiated buyout, the landlord must pay the tenant a Surrender Premium . The tenant's minimum reservation price encompasses:

Relocation & Moving Expenses : Physical transportation of equipment, furniture, fixtures, and IT infrastructure.

Turnkey Replacement Build-Out Costs : Upfitting replacement premises above any landlord improvement allowance.

Rental Differential (Present Value) : The present value of the spread between the higher market rent at the replacement facility and the lower in-place rent over the remaining lease term.

Business Interruption & Disruption Premium : Compensation for lost revenue, employee downtime, and client disruption during the relocation.

Tenant Buyout Cost vs. Landlord Damages: The Settlement Zone (ZOPA)

A negotiated lease buyout succeeds when an overlapping settlement range exists between the landlord's damage floor and the tenant's walk-away ceiling. This bargaining range represents the Zone of Possible Agreement (ZOPA) :

Negotiation Boundary Analytical Basis Key Determining Factors

Landlord Floor (Minimum) Landlord Net Economic Damages PV(Contract Rent) - PV(Mitigation Rent) + PV(Re-tenanting Outlays) + Unamortized Concessions

Tenant Ceiling (Maximum) Cost of Going Dark & Subleasing PV(Contract Rent + Carrying Costs) - PV(Net Sublease Recovery)

Settlement Range (ZOPA) Overlapping Bargaining Spread Spread between Landlord Damage Floor and Tenant Walk-Away Ceiling

The Tenant's Walk-Away Alternative: The Cost of "Going Dark"

If the landlord demands an exorbitant buyout fee, the tenant's primary walk-away alternative (BATNA) is to vacate the premises ("go dark") while continuing to pay monthly rent, or to sublease the space to an outside party: Tenant Ceiling = PV ( Remaining Rent + Direct Carrying Costs ) − PV ( Net Sublease Cash Inflows ) \text{Tenant Ceiling} = \text{PV}(\text{Remaining Rent} + \text{Direct Carrying Costs}) - \text{PV}(\text{Net Sublease Cash Inflows}) Tenant Ceiling = PV ( Remaining Rent + Direct Carrying Costs ) − PV ( Net Sublease Cash Inflows )

When evaluating a sublease alternative, corporate occupiers must underwrite significant market frictions:

Sublease Rental Discount : Sublease space universally trades at a 20% to 35% discount to direct landlord space due to secondary credit risk and shorter remaining durations.

Downtime & Marketing Absorption : Subleasing typically requires 6 to 12 months of marketing downtime.

Sublease Transaction Friction : Sublease tenant improvement allowances, legal documentation, and broker commissions (typically 4% to 6% of sublease aggregate rent).

If the landlord's damage floor is $1,192,000 and the tenant's net cost to go dark and sublease is $1,271,000, a positive ZOPA of $79,000 exists ($1,192,000 to $1,271,000), within which the parties can negotiate a mutually beneficial buyout.

Space Contraction Strategies: Subleasing, Assignment & Continuing Liability

When a total buyout is economically infeasible, tenants pursue contraction alternatives to mitigate overhead:

1. Partial Surrender

The tenant surrenders a discrete portion of its premises (e.g., an entire floor or demised wing) while renewing or extending the lease on the retained space. The landlord typically mandates that the tenant pay for physical demising walls, HVAC system re-balancing, separate utility submetering, and the unamortized concessions attributable to the surrendered square footage.

2. Sublease vs. Assignment: Privity of Contract vs. Privity of Estate

Understanding the legal distinction between a sublease and an assignment is essential for CCIM user advisory: LEGAL RELATIONSHIPS IN COMMERCIAL SPACE TRANSFERS

  • ------------------------------------------------------------------------
  • SUBLEASE: Landlord <=== Privity of Contract & Estate ===> Master Tenant
  • ^
  • | Sublease Contract
  • v
  • Subtenant
  • ASSIGNMENT: Landlord <======== Privity of Estate ========> Assignee
  • ^ |
  • +------------- Privity of Contract ------------+ (Assignor retains liability!)
  • ------------------------------------------------------------------------

Sublease :

The master tenant transfers less than its entire leasehold interest (either a portion of space or a shorter time duration).

The master tenant retains both privity of contract and privity of estate with the prime landlord.

The subtenant has privity of contract only with the master tenant. If the subtenant defaults, the master tenant remains 100% liable to the landlord for all rent and operational obligations.

Assignment :

The tenant transfers its entire remaining leasehold estate to an assignee.

The assignment establishes privity of estate between the landlord and the assignee, obligating the assignee to pay rent directly to the landlord.

The Critical CCIM Legal Trap : The original tenant (assignor) remains bound under privity of contract throughout the entire remaining lease term unless the landlord executes an express written release or novation . If the assignee defaults or declares bankruptcy 3 years later, the landlord can legally demand full payment from the original tenant.

3. Landlord Consent Standards

Commercial leases generally restrict transfers through consent clauses:

Sole and Absolute Discretion : Landlord can deny sublease or assignment requests arbitrarily.

Commercially Reasonable Standard : Landlord cannot unreasonably withhold consent. Permissible denial criteria include poor financial creditworthiness, conflicting operational use, or tenant-prospect competition with existing building occupants.

Growth Clauses & Expansion Strategies

Growing enterprises face duration risk: leasing too much space upfront creates expensive "ghost space," while leasing too little chokes business expansion. Corporate real estate advisors incorporate specific growth clauses to manage this risk:

Growth Mechanism Operational Mechanics Landlord Impact Tenant Impact

Right of First Refusal (ROFR) Tenant has right to match any bona fide third-party offer within 5 to 15 business days Highly restrictive; chills third-party market interest Maximum control; preempts third-party prospects

Right of First Offer (ROFO) Landlord must offer space to existing tenant at market terms before public marketing Flexible; preserves open-market marketing agility Priority access; must act before open market testing

Expansion Option Unilateral right to lease specified contiguous space at fixed dates and predetermined rates Constrains leasing; creates unrentable shadow space Guarantees contiguous growth without early rent outlays

Must-Take Space Phased occupancy commitment where tenant takes additional space on pre-agreed dates Guaranteed revenue absorption and stable tenancy Avoids upfront rent while locking guaranteed expansion

Comprehensive Worked Case Study: 3-Year Early Buyout Valuation

A corporate tenant occupies 20,000 RSF under a 10-year Class-A office lease. At the end of Year 7 (Month 84), the tenant requests an early lease buyout with exactly 36 months remaining. The landlord's cost of capital / safe reinvestment discount rate is 6.0% per annum (0.50% per month).

Baseline Underwriting Data

In-Place Contract Rent : $30.00/RSF NNN ($50,000/month base rent) plus $10.00/RSF operating expense pass-throughs ($16,666.67/month), totaling $66,666.67 per month .

Original Concessions : At lease execution, landlord funded $500,000 in Tenant Improvements and $100,000 in leasing commissions ($600,000 total), amortized straight-line over 120 months ($5,000/month).

Remaining Concession Amortization : At Month 84, 36 months remain unamortized: 36 × $ 5 , 000 = $ 180 , 000 36 \times \text{\textdollar}5,000 = \text{\textdollar}180,000 36 × $ 5 , 000 = $ 180 , 000 .

Market Mitigation Profile : Submarket analysis indicates 8 months of vacancy downtime. A replacement tenant will commence in Month 9 at market rent of $32.00/RSF NNN ($53,333.33/month) plus $10.00/RSF operating expense pass-throughs ($16,666.67/month), totaling $70,000.00 per month across the remaining 28 overlapping months (Months 9 to 36).

Re-tenanting Capital Outlays : New TI allowance of $25.00/RSF ($500,000) and leasing commissions of 5.0% on a new 5-year lease ($96,000) total $596,000 , payable at Month 8.

Step 1: PV of Remaining Contract Rent Obligations

Discount 36 monthly payments of $66,666.67 at 0.50% monthly ( i = 0.005 i = 0.005 i = 0.005 ): PVAF = 1 − ( 1 + 0.005 ) − 36 0.005 = 1 − 0.835645 0.005 = 32.871016 \text{PVAF} = \frac{1 - (1 + 0.005)^{-36}}{0.005} = \frac{1 - 0.835645}{0.005} = 32.871016 PVAF = 0.005 1 − ( 1 + 0.005 ) − 36 ​ = 0.005 1 − 0.835645 ​ = 32.871016 PV ( Contract Rent ) = $ 66 , 666.67 × 32.871016 = $ 2 , 191 , 400 \text{PV}(\text{Contract Rent}) = \$66,666.67 \times 32.871016 = \$2,191,400 PV ( Contract Rent ) = $66 , 666.67 × 32.871016 = $2 , 191 , 400

Step 2: PV of Replacement Tenant Mitigation Rent

The replacement tenant pays $70,000.00 per month for 28 months (Months 9 through 36).

First, calculate the present value of this 28-month annuity at Month 8: PVAF 28 = 1 − ( 1 + 0.005 ) − 28 0.005 = 1 − 0.869768 0.005 = 26.046467 \text{PVAF}_{28} = \frac{1 - (1 + 0.005)^{-28}}{0.005} = \frac{1 - 0.869768}{0.005} = 26.046467 PVAF 28 ​ = 0.005 1 − ( 1 + 0.005 ) − 28 ​ = 0.005 1 − 0.869768 ​ = 26.046467 PV Month 8 = $ 70 , 000.00 × 26.046467 = $ 1 , 823 , 253 \text{PV}_{\text{Month 8}} = \$70,000.00 \times 26.046467 = \$1,823,253 PV Month 8 ​ = $70 , 000.00 × 26.046467 = $1 , 823 , 253

Next, discount this lump-sum back 8 months to Month 0 (commencement of buyout): PV 0 ( Mitigation Rent ) = $ 1 , 823 , 253 ( 1.005 ) 8 = $ 1 , 823 , 253 1.040707 = $ 1 , 751 , 937 \text{PV}_0(\text{Mitigation Rent}) = \frac{\$1,823,253}{(1.005)^8} = \frac{\$1,823,253}{1.040707} = \$1,751,937 PV 0 ​ ( Mitigation Rent ) = ( 1.005 ) 8 $1 , 823 , 253 ​ = 1.040707 $1 , 823 , 253 ​ = $1 , 751 , 937

Step 3: PV of Direct Re-tenanting Capital Outlays

The landlord must spend $596,000 in TIs and LCs at Month 8. Discount this capital outlay back 8 months to Month 0: PV 0 ( Re-tenanting Outlays ) = $ 596 , 000 ( 1.005 ) 8 = $ 596 , 000 1.040707 = $ 572 , 688 \text{PV}_0(\text{Re-tenanting Outlays}) = \frac{\$596,000}{(1.005)^8} = \frac{\$596,000}{1.040707} = \$572,688 PV 0 ​ ( Re-tenanting Outlays ) = ( 1.005 ) 8 $596 , 000 ​ = 1.040707 $596 , 000 ​ = $572 , 688

Step 4: Recovery of Unamortized Concessions

Unamortized concession balance at Month 84: Unamortized Concessions = $ 600 , 000 × ( 36 120 ) = $ 180 , 000 \text{Unamortized Concessions} = \$600,000 \times \left( \frac{36}{120} \right) = \$180,000 Unamortized Concessions = $600 , 000 × ( 120 36 ​ ) = $180 , 000

Step 5: Compute Landlord Damage Floor Floor = PV ( Contract Rent ) − PV ( Mitigation Rent ) + PV ( Re-tenanting ) + Unamortized Concessions \text{Floor} = \text{PV}(\text{Contract Rent}) - \text{PV}(\text{Mitigation Rent}) + \text{PV}(\text{Re-tenanting}) + \text{Unamortized Concessions} Floor = PV ( Contract Rent ) − PV ( Mitigation Rent ) + PV ( Re-tenanting ) + Unamortized Concessions Floor = $ 2 , 191 , 400 − $ 1 , 751 , 937 + $ 572 , 688 + $ 180 , 000 = $ 1 , 192 , 151 \text{Floor} = \$2,191,400 - \$1,751,937 + \$572,688 + \$180,000 = \$1,192,151 Floor = $2 , 191 , 400 − $1 , 751 , 937 + $572 , 688 + $180 , 000 = $1 , 192 , 151

Step 6: Evaluate Tenant Ceiling & Final Settlement

If the tenant vacates and goes dark without subleasing, it incurs $2,191,400 in rent PV plus $30,000 in carrying costs ($2,221,400 total).

If the tenant subleases the space, factoring in 12 months of downtime, a 25% rent discount, and 5% sublease commissions, the net present cost is $1,271,000.

Settlement Zone (ZOPA) : Spans between the landlord's floor of $1,192,151 and the tenant's ceiling of $1,271,000 . The parties possess an actionable $78,849 bargaining range, typically settling around $1,225,000 .

CCIM Exam Traps & Common Underwriting Pitfalls

Treating Unamortized Concessions as Sunk Costs : Assuming that upfront tenant improvement allowances and broker commissions are non-recoverable historical sunk costs. Under commercial lease damage formulas, unamortized initial concessions represent direct contractual damages owed to the landlord upon early lease termination.

Double-Counting Vacancy Downtime : Calculating lost rent during the vacancy period while simultaneously failing to discount the replacement tenant's cash flows back from their actual commencement date, distorting net mitigation value.

The Sublease Assignment Novation Fallacy : Believing that assigning a lease or subleasing space completely releases the original corporate tenant from continuing financial liability. In the absence of an express written novation or release from the landlord, privity of contract endures throughout the lease term.

Using Property Capitalization Rates for Buyout Discounting : Discounting buyout cash flows using the property's overall direct capitalization rate ( R o R_o R o ​ ) rather than a safe reinvestment rate or corporate borrowing rate. Capitalization rates reflect perpetuity yields on real property assets, whereas buyout cash flows represent short-duration contractual credit obligations.