Study guide

9.4 CMAA Standards of Practice

Certified Construction Manager Exam

Track your progress as you read

Finished sections get a check mark.

1 Program & Project Management Fundamentals

1.1 Project Management Fundamentals 1.2 Project Initiation & Chartering 1.3 Scope Management & WBS 1.4 Resource Allocation & Management 1.5 Project Relationships & Stakeholders

2 Chapter 2: Project Planning & Pre-Construction

2.1 Pre-Construction Phase Services 2.2 Project Delivery Methods 2.3 Bidding, Procurement & Award 2.4 Project Communications Management 2.5 Site Management & Logistics

3 Cost Management & Value Engineering

3.1 Cost Management Principles 3.2 Cost Estimating Techniques 3.3 Value Engineering Processes 3.4 Earned Value Management (EVM) 3.5 Progress Payments & Cost Control

4 Chapter 4: Time Management & CPM Scheduling

4.1 Time Management & Scheduling Fundamentals 4.2 Scheduling Techniques (CPM, GERT, Line of Balance, PERT) 4.3 CPM Network Calculations and Logic 4.4 Schedule Compression (Crashing, Fast-tracking, Leveling) 4.5 Time Extensions, Delay Analysis & Schedule Control

5 Chapter 5: Contract Administration & Project Documentation

5.1 Contract Management & Administration Principles 5.2 Contract Types & Payment Provisions 5.3 Submittals, Shop Drawings & RFIs 5.4 Change Orders & Change Directives 5.5 Project Closeout Procedures

6 Chapter 6: Quality Management & Commissioning

6.1 Quality Management Principles 6.2 Quality Management Systems 6.3 Quality Assurance (QA) and Quality Control (QC) 6.4 Quality Inspection & Testing 6.5 Building Commissioning

7 Chapter 7: Safety Management & Incident Prevention

7.1 Safety Management Principles 7.2 OSHA Compliance & Construction Standards 7.3 Hazard Identification & Mitigation 7.4 Safety Training & Communication 7.5 Accident Investigation & Safety Performance

8 Chapter 8: Risk Management, Insurance & Bonds

8.1 Risk Management Principles 8.2 Risk Identification & Assessment 8.3 Risk Response & Mitigation Planning 8.4 Construction Insurance & Bonds 8.5 Contingency Planning & Management

9 Chapter 9: Professional Practice & CMAA Standards

9.1 Professional Practice & Construction Law 9.2 Roles & Responsibilities of the CM 9.3 Ethics & Professional Conduct 9.4 CMAA Standards of Practice 9.5 Construction Claims & Disputes

10 Chapter 10: Sustainability & Environmental Compliance

10.1 Sustainability & Green Construction 10.2 Sustainable Practices & LEED 10.3 Environmental Compliance & Risk

11 Chapter 11: Construction Technology & BIM

11.1 Construction Technology & BIM 11.2 Project Management Software 11.3 Site Technology & Tools

9.4 CMAA Standards of Practice

Key Takeaways Explain This Topic AI

The CMAA Construction Management Standards of Practice is the defining document that outlines the core competencies and procedures for CMs.

Cost Management includes estimating, budget development, cost control, and managing payment applications and change orders.

Time Management focuses on developing master schedules, reviewing contractor baseline schedules, and analyzing schedule updates and delays.

Quality Management encompasses design reviews for constructability, QA/QC planning, and monitoring contractor compliance with specifications.

Project Management integrates all other functions, focusing on communication, document control, team leadership, and risk management.

Last updated: July 2026

The CMAA Construction Management Standards of Practice (SOP) is the foundational document of the CM profession. It defines the standard of care, establishes best practices, and outlines the comprehensive services a professional CM should provide across all project phases. The SOP categorizes CM services into distinct functional areas. Mastery of these areas is heavily tested on the CCM exam.

1. Project Management

Project Management is the overarching function that integrates all other CM disciplines. It is the administrative framework that keeps the project moving forward.

Project Management Plan (PMP): Developing a comprehensive plan that defines project goals, roles and responsibilities, communication protocols, and procedures.

Document Control: Establishing systems for managing RFIs, submittals, meeting minutes, daily reports, and drawing logs.

Communication: Acting as the central hub of communication between the owner, designer, and contractors, ensuring that all stakeholders have timely, accurate information.

Risk Management: Identifying project risks early (financial, physical, environmental) and developing mitigation strategies.

2. Cost Management

Effective cost management ensures the project is completed within the owner's approved budget.

Estimating: Providing conceptual estimates during pre-design, detailed estimates during design development, and pre-bid estimates. CM estimates serve as a check against the designer's estimates.

Budgeting: Establishing the baseline budget, incorporating hard costs (construction), soft costs (design/management fees), and contingencies.

Cost Control: Monitoring expenditures, forecasting cost at completion, and rigorously managing the change order process to prevent scope creep.

Payment Application Review: Scrutinizing contractor schedule of values and monthly pay apps to ensure they accurately reflect work put in place and materials suitably stored.

3. Time Management (Schedule Management)

Time management focuses on completing the project on or before the contractual completion date.

Master Schedule: Developing the overall project schedule encompassing planning, design, procurement, construction, and commissioning.

Baseline Schedule Review: Reviewing and approving the contractor's detailed construction schedule (often utilizing the Critical Path Method - CPM) to ensure it is realistic and complies with contract requirements.

Schedule Monitoring: Analyzing weekly or monthly schedule updates to track progress against the baseline.

Delay Analysis: Identifying variances, determining the cause of delays (excusable vs. inexcusable, compensable vs. non-compensable), and evaluating recovery plans.

4. Quality Management

Quality management ensures that the completed project meets the owner's requirements and complies with the contract documents.

Constructability Reviews: Reviewing design documents to ensure the project can be built efficiently and identifying potential errors or omissions before bidding.

QA/QC Plan: Developing the Quality Assurance (QA) plan—the processes the CM uses to verify quality. The contractor is responsible for Quality Control (QC)—the actual testing and inspection of the work.

Inspection and Testing: Coordinating independent testing agencies (e.g., concrete strength, soil compaction) and monitoring contractor compliance.

Defect Management: Identifying non-conforming work, issuing notices to correct, and managing the punch list process.

5. Contract Administration

Contract administration involves managing the legal and commercial aspects of the project contracts.

Procurement Strategy: Advising on delivery methods, drafting RFP/RFQ documents, and managing the bidding process.

Change Management: Evaluating claims and change order requests for merit, negotiating equitable adjustments for time and money, and preparing change order documentation.

Dispute Resolution: Managing conflicts proactively at the project level to avoid escalation into formal arbitration or litigation.

6. Safety Management

While the contractor bears the primary legal responsibility for safety means and methods on the job site, the CM has a vital role in safety oversight.

Safety Plan Review: Reviewing the general contractor's site-specific safety plan prior to mobilization.

Monitoring and Reporting: Observing site conditions for compliance with safety standards (like OSHA). If an imminent danger is spotted, the CM must act immediately to stop work in that area and notify the contractor.

Multi-Employer Coordination: On multiple-prime projects, the CM often coordinates the overarching safety program and ensures communication regarding hazards between different prime contractors.

7. Sustainability

Increasingly, CMs are tasked with managing sustainability goals, such as LEED certification or energy efficiency targets.

Goal Setting: Assisting the owner and designer in establishing achievable sustainability metrics during pre-design.

Material Tracking: Monitoring the procurement and installation of sustainable materials (e.g., recycled content, low-VOC materials).

Waste Management: Overseeing the contractor's construction waste management plan to maximize recycling and minimize landfill use.

By systematically applying these Standards of Practice, the CM delivers a predictable, controlled process that protects the owner and drives the project to a successful conclusion.