28.1 Earned Value Management (EVM) for Capital Project Oversight

Certified Government Financial Manager CGFM

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Organization, Authority and Structure of Government — Part I

1.1 Levels, Branches, and Separation of Powers 1.2 Components of Government & Public Authorities 1.3 Subnational Governments: General-Purpose vs. Special-Purpose

2 Chapter 2: Organization, Authority and Structure of Government — Part II

2.1 Legal Authority, Charters, and Sovereign Powers 2.2 Tribal Sovereignty & Intergovernmental Relations 2.3 Categorical Grants vs. Block Grants

3 Chapter 3: The Government Financial Management Cycle & Legal Framework — Part I

3.1 The Seven Phases of the Financial Management Cycle 3.2 The Closed-Loop Feedback Architecture 3.3 The Constitutional Basis: The Power of the Purse

4 Chapter 4: The Government Financial Management Cycle & Legal Framework — Part II

4.1 Types of Legislative Appropriations 4.2 The Hierarchy of Budgetary Spending Controls 4.3 Legal Mechanisms Dedicating Public Revenues

5 Chapter 5: Government Revenues, Grants & Debt Financing — Part I

5.1 Public Tax Policy and Tax Structures 5.2 Wealth and Property Taxes 5.3 Intergovernmental Grants & the Uniform Guidance Lifecycle 5.4 The OMB Uniform Guidance Grant Lifecycle (2 CFR 200)

6 Chapter 6: Government Revenues, Grants & Debt Financing — Part II

6.1 User Charges, Cost Recovery, Leases & Public-Private Partnerships 6.2 Public Debt Issuance, Bond Types & Credit Ratings 6.3 Certificates of Participation (COPs) and Lease-Revenue Bonds

7 Chapter 7: Public Accountability, Transparency & Open Government — Part I

7.1 Legislative Frameworks for Accountability: IG Act & CFO Act 7.2 Government Management Reform Act (GMRA) of 1994 7.3 Assessing Fiscal Sustainability, Solvency & SEA Reporting

8 Chapter 8: Public Accountability, Transparency & Open Government — Part II

8.1 Net Pension Liability (NPL) Recognition 8.2 Open Government, DATA Act of 2014 & Citizen-Centric Reporting 8.3 Digital Open Checkbooks

9 Chapter 9: Public Sector Ethics & Digital Government — Part I

9.1 Public Service Ethics Principles & the AGA Code of Ethics 9.2 The Ethical Spectrum: The Ethical Floor vs. The Ethical Ceiling 9.3 Managing Conflicts of Interest, Due Care, Whistleblowing & Nepotism

10 Chapter 10: Public Sector Ethics & Digital Government — Part II

10.1 Post-Employment "Revolving Door" Prohibitions (18 U.S.C. § 207) 10.2 E-Government Services, Public Portals & NIST Cybersecurity Standards 10.3 Personally Identifiable Information (PII)

11 Chapter 11: Governmental Accounting Principles & Cost Allocation — Part I

11.1 Environmental Differences, Standard Setters & GAAP Hierarchies 11.2 Standard-Setting Bodies and Jurisdictional Framework 11.3 State and Local GAAP Hierarchy: GASB Statement No. 76 11.4 Measurement Focus, Basis of Accounting & Nonexchange Transactions

12 Chapter 12: Governmental Accounting Principles & Cost Allocation — Part II

12.1 The Four GASB Statement No. 33 Nonexchange Categories 12.2 Managerial Cost Accounting, SFFAS 4 & Intergovernmental Fee Establishment 12.3 Cost Allocation under OMB Uniform Guidance (2 CFR 200 Subpart E)

13 Chapter 13: Public Budgeting Concepts & Controls — Part I

13.1 Public Budget Formulation, Structures & Budgeting Approaches 13.2 Fund 13.3 Performance-Based Budgeting (PBB) 13.4 Capital Project Financing, Capital Budgets & Revenue/Expenditure Forecasting

14 Chapter 14: Public Budgeting Concepts & Controls — Part II

14.1 Public-Private Partnerships (P3s) 14.2 Budgetary Control Techniques & General Ledger Accounting Operations 14.3 Stock Statements vs. Flow Statements

15 Chapter 15: State & Local Fund Accounting & Budgetary Accounting — Part I

15.1 The Eleven State & Local Fund Types & Accounting Bases 15.2 Capital Projects Funds (CPF) 15.3 Custodial Funds 15.4 Modified Accrual Accounting: Revenues, Expenditures & Financing Sources

16 Chapter 16: State & Local Fund Accounting & Budgetary Accounting — Part II

16.1 Other Financing Sources (OFS) and Other Financing Uses (OFU) 16.2 Budgetary Integration, Encumbrance Entries & GASB 54 Fund Balance Classifications 16.3 Nonspendable Fund Balance

17 Chapter 17: State & Local Financial Reporting & Statements — Part I

17.1 Defining the State & Local Reporting Entity & Component Units 17.2 Pathway 3: Misleading to Exclude & Affiliated Organizations (GASB 39 & 90) 17.3 Joint Ventures 17.4 The Annual Comprehensive Financial Report (ACFR) Structure & RSI

18 Chapter 18: State & Local Financial Reporting & Statements — Part II

18.1 Required Supplementary Information (RSI Other than MD&A) 18.2 Government-Wide Financial Statements, Interfund Eliminations & Reconciliation 18.3 Internal Balances (Due To / Due From)

19 Chapter 19: Federal Budgetary Accounting & the USSGL — Part I

19.1 Federal Accounting Governance: FASAB, OMB, Treasury & GAO 19.2 Comparative Analysis: The Quadripartite Leadership 19.3 Federal Budgetary Terminology, the Budgetary Equation & Fund Types

20 Chapter 20: Federal Budgetary Accounting & the USSGL — Part II

20.1 General Fund of the United States Government 20.2 The U.S. Standard General Ledger (USSGL) & Dual-Track Budgetary Accounting 20.3 Milestone 2: OMB Apportionment (Form SF 132)

21 Chapter 21: Federal Proprietary Accounting & Financial Reporting — Part I

21.1 Federal Proprietary Accounting & Fund Balance with Treasury (FBWT) 21.2 Non-FBWT Budgetary Authority (Offsets) 21.3 Stewardship PP&E: Heritage Assets and Stewardship Land (SFFAS 29) 21.4 Federal Credit Reform Act (FCRA): Direct Loans, Loan Guarantees & Subsidy Accounting

22 Chapter 22: Federal Proprietary Accounting & Financial Reporting — Part II

22.1 The Liquidating Account (Budgetary - Pre-1992) 22.2 Federal Financial Reporting: AFR, PAR, Basic Financial Statements & the U.S. Consolidated Report 22.3 The Statement of Changes in Net Position (SCNP)

23 Chapter 23: Cash, Investment & Debt Operations — Part I

23.1 Government Cash Management, Collections, Lockboxes & Banking Controls 23.2 Fees vs. Compensating Balances: Strategic Analysis 23.3 Public Investment Policies, Safety-Liquidity-Yield, Prudent Person Rule & Risk Disclosures 23.4 Authorized Public Investment Instruments: Comparative Analysis

24 Chapter 24: Cash, Investment & Debt Operations — Part II

24.1 GASB Statement No. 40: Deposit and Investment Risk Disclosures 24.2 Electronic Payments, EFT, P-Cards & Disbursement Controls 24.3 Public Benefit Disbursements: EBT and Reloadable Debit Cards

25 Chapter 25: Procurement, Asset Stewardship & Operational Systems — Part I

25.1 Public Procurement Standards, Fair Competition & Contract Administration 25.2 Contract Types and Cost Risk Allocation 25.3 Capital Asset Stewardship, Property Disposal, Inventory & OM&S Controls 25.4 Environmental Compliance and Electronic Data Sanitization

26 Chapter 26: Procurement, Asset Stewardship & Operational Systems — Part II

26.1 Financial Management Information Systems (FMIS), ERP, Cloud Hosting & Automation 26.2 Development Methodologies: Waterfall vs. Agile 26.3 Shared Services Delivery & Public Sector Project Management 26.4 The PMBOK Five Process Groups

27 Chapter 27: Financial, Managerial & Forensic Analysis — Part I

27.1 Mathematical and Financial Foundations of Time Value of Money (TVM) 27.2 Internal Rate of Return (IRR) 27.3 Financial Statement Trend and Comparative Analysis

28 Chapter 28: Financial, Managerial & Forensic Analysis — Part II

28.1 Earned Value Management (EVM) for Capital Project Oversight 28.2 Public Sector Data Sources and Reliability Verification 28.3 Common Red Flags and Public Sector Fraud Schemes

29 Chapter 29: Internal Control Frameworks & Enterprise Risk Management — Part I

29.1 COSO Internal Control Integrated Framework & the GAO Green Book 29.2 Component 2: Risk Assessment 29.3 Internal Control Deficiencies, Corrective Action Plans & Management Reporting

30 Chapter 30: Internal Control Frameworks & Enterprise Risk Management — Part II

30.1 FMFIA Reporting Sections 30.2 Enterprise Risk Management (ERM) & OMB Circular A-123 Implementation 30.3 Core Elements of a Federal Risk Profile

31 Chapter 31: Performance Measurement, Government Auditing & the Single Audit — Part I

31.1 Performance Measurement, SEA Reporting, GPRA & Public Accountability 31.2 Baselines, Targets, Benchmarking, and Stakeholder Engagement 31.3 Government Auditing Standards: The Yellow Book & Auditor Independence 31.4 Quality Management and External Peer Review

32 Chapter 32: Performance Measurement, Government Auditing & the Single Audit — Part II

32.1 Performance Audit Fieldwork, Reporting & Auditee Responsibilities 32.2 Cause ("Why It Happened") 32.3 The Single Audit Act & Uniform Guidance (2 CFR 200 Subpart F) 32.4 Internal Control over Compliance Testing

28.1 Earned Value Management (EVM) for Capital Project Oversight

Key Takeaways Explain This Topic AI

Cost Performance Index (CPI) and Schedule Performance Index (SPI) provide early-warning project efficiency indicators utilized to project final costs through Estimate at Completion (EAC).

Earned Value Management (EVM) measures project progress by comparing Planned Value (PV), Earned Value (EV), and Actual Cost (AC) to compute Cost Variance (CV) and Schedule Variance (SV).

ANSI-standard process flowcharts visually articulate accounting workflows, identify single points of failure, and enforce critical segregation of duties across transaction authorization, custody, recording, and reconciliation.

Last updated: September 2026

Earned Value Management (EVM) for Capital Project Oversight

Public sector capital infrastructure projects—such as highway construction, airport expansions, automated defense systems, and enterprise software implementations—frequently experience schedule delays and cost overruns. Earned Value Management (EVM) is an ANSI-standard (ANSI/EIA-748) management methodology that integrates project scope , schedule , and cost metrics to deliver objective progress measurement and forecasting.

Foundational EVM Parameters

EVM relies on three core data parameters established through the project's Work Breakdown Structure (WBS):

Planned Value (PV) / Budgeted Cost of Work Scheduled (BCWS) :

The authorized budget allocated to the scheduled work planned to be completed up to a specific evaluation date. PV = % Planned Work Completed × Budget at Completion (BAC) \text{PV} = \% \text{ Planned Work Completed} \times \text{Budget at Completion (BAC)} PV = % Planned Work Completed × Budget at Completion (BAC)

Earned Value (EV) / Budgeted Cost of Work Performed (BCWP) :

The budgeted value of physical work actually completed up to the evaluation date. EV = % Actual Work Completed × Budget at Completion (BAC) \text{EV} = \% \text{ Actual Work Completed} \times \text{Budget at Completion (BAC)} EV = % Actual Work Completed × Budget at Completion (BAC)

Actual Cost (AC) / Actual Cost of Work Performed (ACWP) :

The total direct and indirect costs incurred in accomplishing the work performed up to the evaluation date.

Variance Metrics

Variances indicate whether a project is tracking ahead of or behind its baseline. In EVM, variances are always computed as Earned Value minus the comparison baseline, meaning positive values represent favorable conditions and negative values indicate unfavorable conditions :

  • Cost Variance (CV) : CV = EV − AC \text{CV} = \text{EV} - \text{AC} CV = EV − AC
  • CV > 0 \text{CV} > 0 CV > 0 : Favorable (under budget)
  • CV < 0 \text{CV} < 0 CV < 0 : Unfavorable (cost overrun)
  • Schedule Variance (SV) : SV = EV − PV \text{SV} = \text{EV} - \text{PV} SV = EV − PV
  • SV > 0 \text{SV} > 0 SV > 0 : Favorable (ahead of schedule)
  • SV < 0 \text{SV} < 0 SV < 0 : Unfavorable (behind schedule)
  • Efficiency Performance Indices

Performance indices express cost and schedule efficiency as ratios. A value of 1.00 represents on-target performance , values above 1.00 denote superior efficiency , and values below 1.00 signal severe inefficiency :

Cost Performance Index (CPI) : CPI = EV AC \text{CPI} = \frac{\text{EV}}{\text{AC}} CPI = AC EV ​ Measures cost efficiency. A CPI of 0.80 indicates that for every dollar expended, the project has earned only 80 cents of budgeted work.

Schedule Performance Index (SPI) : SPI = EV PV \text{SPI} = \frac{\text{EV}}{\text{PV}} SPI = PV EV ​ Measures schedule efficiency. An SPI of 0.90 indicates work is progressing at 90% of the planned schedule rate.

Project Outcome Forecasting

EVM metrics empower project managers to forecast total expenditures at completion:

Budget at Completion (BAC) : Total approved initial baseline budget.

Estimate at Completion (EAC) : The projected total final cost of the project upon completion.

Standard Assumption (future work proceeds at current cost efficiency) : EAC = BAC CPI \text{EAC} = \frac{\text{BAC}}{\text{CPI}} EAC = CPI BAC ​

Atypical Variances (past variances will not recur; remaining work completed at planned budget) : EAC = AC + ( BAC − EV ) \text{EAC} = \text{AC} + (\text{BAC} - \text{EV}) EAC = AC + ( BAC − EV )

Compound Impact (both current cost and schedule performance impact remaining work) : EAC = AC + [ BAC − EV CPI × SPI ] \text{EAC} = \text{AC} + \left[ \frac{\text{BAC} - \text{EV}}{\text{CPI} \times \text{SPI}} \right] EAC = AC + [ CPI × SPI BAC − EV ​ ]

Estimate to Complete (ETC) : Expected additional funds needed to finish the project: ETC = EAC − AC \text{ETC} = \text{EAC} - \text{AC} ETC = EAC − AC

Variance at Completion (VAC) : Expected budget surplus or deficit at project conclusion: VAC = BAC − EAC \text{VAC} = \text{BAC} - \text{EAC} VAC = BAC − EAC

EVM Metric Abbreviation Formula Favorable Indicator Unfavorable Indicator

Cost Variance CV EV − AC \text{EV} - \text{AC} EV − AC CV > 0 \text{CV} > 0 CV > 0 (Under Budget) CV < 0 \text{CV} < 0 CV < 0 (Over Budget)

Schedule Variance SV EV − PV \text{EV} - \text{PV} EV − PV SV > 0 \text{SV} > 0 SV > 0 (Ahead of Schedule) SV < 0 \text{SV} < 0 SV < 0 (Behind Schedule)

Cost Performance Index CPI EV / AC \text{EV} / \text{AC} EV / AC CPI > 1.00 \text{CPI} > 1.00 CPI > 1.00 (High Efficiency) CPI < 1.00 \text{CPI} < 1.00 CPI < 1.00 (Cost Inefficient)

Schedule Performance Index SPI EV / PV \text{EV} / \text{PV} EV / PV SPI > 1.00 \text{SPI} > 1.00 SPI > 1.00 (Accelerated Pace) SPI < 1.00 \text{SPI} < 1.00 SPI < 1.00 (Project Delayed)

Estimate at Completion EAC BAC / CPI \text{BAC} / \text{CPI} BAC / CPI EAC ≤ BAC \text{EAC} \le \text{BAC} EAC ≤ BAC (Under/At Budget) EAC > BAC \text{EAC} > \text{BAC} EAC > BAC (Projected Overrun)

Walkthrough Scenario: State Highway Interchange Reconstruction

A state department of transportation contracts out a major interstate bridge and interchange reconstruction project:

Total Baseline Budget (BAC) : $12,000,000 across a 24-month timeline.

Performance Status at Month 12 :

  • Planned Value (PV) = $6,000,000 (50% of work planned)
  • Earned Value (EV) = $4,800,000 (40% of work physically certified as complete)
  • Actual Cost (AC) = $5,600,000

EVM Diagnostic Calculations :

CV = EV − AC = $ 4 , 800 , 000 − $ 5 , 600 , 000 = − $ 800 , 000 \text{CV} = \text{EV} - \text{AC} = \text{\textdollar}4,800,000 - \text{\textdollar}5,600,000 = -\text{\textdollar}800,000 CV = EV − AC = $ 4 , 800 , 000 − $ 5 , 600 , 000 = − $ 800 , 000 (Unfavorable: $800,000 cost overrun to date)

SV = EV − PV = $ 4 , 800 , 000 − $ 6 , 000 , 000 = − $ 1 , 200 , 000 \text{SV} = \text{EV} - \text{PV} = \text{\textdollar}4,800,000 - \text{\textdollar}6,000,000 = -\text{\textdollar}1,200,000 SV = EV − PV = $ 4 , 800 , 000 − $ 6 , 000 , 000 = − $ 1 , 200 , 000 (Unfavorable: $1,200,000 worth of work behind schedule)

CPI = EV AC = $ 4 , 800 , 000 $ 5 , 600 , 000 = 0.857 \text{CPI} = \frac{\text{EV}}{\text{AC}} = \frac{\text{\textdollar}4,800,000}{\text{\textdollar}5,600,000} = 0.857 CPI = AC EV ​ = $ 5 , 600 , 000 $ 4 , 800 , 000 ​ = 0.857 (The state is receiving only ~86 cents of value per dollar spent)

SPI = EV PV = $ 4 , 800 , 000 $ 6 , 000 , 000 = 0.800 \text{SPI} = \frac{\text{EV}}{\text{PV}} = \frac{\text{\textdollar}4,800,000}{\text{\textdollar}6,000,000} = 0.800 SPI = PV EV ​ = $ 6 , 000 , 000 $ 4 , 800 , 000 ​ = 0.800 (Project is progressing at only 80% of scheduled speed)

EAC = BAC CPI = $ 12 , 000 , 000 0.857143 = $ 14 , 000 , 000 \text{EAC} = \frac{\text{BAC}}{\text{CPI}} = \frac{\text{\textdollar}12,000,000}{0.857143} = \text{\textdollar}14,000,000 EAC = CPI BAC ​ = 0.857143 $ 12 , 000 , 000 ​ = $ 14 , 000 , 000

VAC = BAC − EAC = $ 12 , 000 , 000 − $ 14 , 000 , 000 = − $ 2 , 000 , 000 \text{VAC} = \text{BAC} - \text{EAC} = \text{\textdollar}12,000,000 - \text{\textdollar}14,000,000 = -\text{\textdollar}2,000,000 VAC = BAC − EAC = $ 12 , 000 , 000 − $ 14 , 000 , 000 = − $ 2 , 000 , 000 projected final deficit.

Flowcharting, Process Mapping & Internal Control Walkthroughs

Auditors and governmental managers utilize process mapping to document accounting cycles, execute internal control walkthroughs, and diagnose operational bottlenecks. Under the GAO Green Book ( Standards for Internal Control in the Federal Government ) and the COSO Internal Control Integrated Framework , documentation must demonstrate how transactions originate, receive authorization, pass through custody, enter financial records, and undergo independent reconciliation.

Standard ANSI Flowchart Symbols

Standardized American National Standards Institute (ANSI) flowchart symbols provide uniform visual language across audit files and management manuals:

Terminator / Terminal (Oval / Stadium) : Indicates the starting or stopping boundary of a process flow (e.g., "Vendor Submits Invoice" or "End of Disbursement Process").

Process (Rectangle) : Represents an action, clerical step, calculation, or system processing activity (e.g., "Accounts Payable Clerk matches invoice to purchase order").

Decision (Diamond) : Marks a logical decision branching point with alternative exit paths based on a condition (e.g., "Does invoice amount exceed $10,000? [Yes / No]").

Document (Rectangle with Wavy Base) : Represents physical or digital paperwork entering or exiting the process (e.g., Purchase Requisition, Bill of Lading, Receiving Report, Warrant Check).

Input / Output (Parallelogram) : Represents generic input or output of information into an automated application.

On-Page Connector (Small Circle) : Connects disparate flowchart lines on the same page, avoiding crossing lines.

Off-Page Connector (Pentagon pointing downward) : Directs process flow to a separate page in complex multi-page operational walkthroughs.

Database / Magnetic Storage (Cylinder) : Depicts data storage in electronic general ledgers or enterprise databases.

Documenting Walkthroughs and Segregation-of-Duties Bottlenecks

An internal control walkthrough traces a single transaction from initial inception through processing, authorization, recording, and reporting. In financial audits, flowcharting is uniquely effective at identifying violations of Segregation of Duties (SOD) .

Adequate segregation of duties mandates that distinct individuals perform four key transaction responsibilities ( CARR ):

  • Custody of assets (handling cash, blank checks, physical inventory)
  • Authorization of transactions (approving purchase orders, contract awards)
  • Recording transactions (posting journal entries to general ledger)
  • Reconciliation of accounts (performing independent bank or subledger reconciliations)

Common Bottlenecks & Control Vulnerabilities Detected via Process Mapping :

Custody Combined with Recording : An accounts receivable clerk who accepts cash payments over the counter and also possesses system permissions to post credit adjustments to customer accounts (creating severe lapping fraud risk).

Authorization Combined with Custody : A department supervisor who can approve purchase orders and also receives physical goods at the loading dock without independent receiving verification.

Single-Point Approvals : Diamond decision nodes lacking dollar escalation thresholds, permitting large procurement commitments without executive countersignature.

Loading diagram... Earned Value Management (EVM) Project Tracking and Forecasting Flow