10.3 Job and Batch Costing: Job Cost Cards, Job Accounts and Pricing a Job

CIMA BA2: Fundamentals of Management Accounting Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: The Context of Management Accounting

1.1 The Need for Management Accounting, the GMAP Definition & Comparison with Financial Accounting 1.2 Qualities of Good Management Information: From Data to Decisions 1.3 Information for Operational, Managerial and Strategic Levels 1.4 The Role of the Management Accountant: CIMA's View, IFAC's Domain & Position in the Organisation 1.5 CIMA as a Professional Body: Members, Candidates, the Profession & Society

2 Chapter 2: Cost Identification, Classification and Behaviour

2.1 Cost Classification by Nature, Function, and Element 2.2 Cost Behaviour Patterns and Relevant Range 2.3 The High-Low Method and Cost Prediction 2.4 Scattergraph and Least-Squares Regression for Cost Estimation

3 Chapter 3: Overheads and Absorption Costing

3.1 Production Overheads: Allocation and Apportionment 3.2 Overhead Absorption Rates (OAR) & Under/Over-Absorption

4 Chapter 4: Marginal Costing, Profit Reconciliation and Cost-Based Pricing

4.1 Marginal Costing vs Absorption Costing Principles 4.2 Reconciling Marginal and Absorption Costing Operating Profits 4.3 Pricing with Cost Information: Full-Cost-Plus, Marginal-Cost-Plus, Mark-Ups, Margins and Return Targets

5 Chapter 5: Budget Preparation: Functional, Master and Cash Budgets

5.1 Purposes of Budgeting & The Budgeting Process 5.2 The Principal Budget Factor & Functional Budgets 5.3 The Master Budget: Budgeted Profit or Loss, Financial Position and Cash Flow 5.4 Cash Budgets & Cash Flow Forecasting

6 Chapter 6: Budgetary Control: Flexible Budgets, Behaviour and Budgeting Approaches

6.1 Fixed vs Flexible Budgeting and Budget Flexing 6.2 Budgetary Control Systems, Participation & Behavioural Aspects 6.3 Alternative Budgeting Approaches: Incremental, ZBB & Rolling Budgets

7 Chapter 7: Standard Costing and Cost Variances

7.1 Standard Costing Principles and Types of Standards 7.2 Direct Material Price and Usage Variances 7.3 Direct Labour Rate, Efficiency, and Idle Time Variances 7.4 Variable and Fixed Overhead Variances

8 Chapter 8: Sales Variances, Operating Statements and Interpreting Variances

8.1 Sales Variances and Operating Statements (Marginal and Absorption Formats) 8.2 Interpreting Variances: Causes, Interrelationships and Deciding What to Investigate

9 Chapter 9: Performance Measurement

9.1 The Need for Performance Measures: Responsibility Accounting, Controllability and Service Industries 9.2 Financial and Non-Financial Performance Measures in Manufacturing and Service Organisations

10 Chapter 10: Integrated Accounts, Job and Batch Costing and Management Reports

10.1 Integrating Cost and Financial Accounts: Control Accounts and the Manufacturing Account 10.2 Integrated Ledgers with Under- and Over-Absorption and Standard Cost Variances 10.3 Job and Batch Costing: Job Cost Cards, Job Accounts and Pricing a Job 10.4 Cost Reports for Manufacturing, Service and Not-for-Profit Organisations

11 Chapter 11: Risk, Probability and Statistics for Decision-Making

11.1 Risk, Uncertainty and Probability: Rules and Joint Probabilities for Decisions 11.2 Expected Values, Expected Value Tables and Their Limitations 11.3 Averages and Dispersion: Mean, Median, Mode, Range, Variance, Standard Deviation and Coefficient of Variation 11.4 The Normal Distribution: Z-Scores, Normal Distribution Tables and Business Probabilities

12 Chapter 12: Relevant Costing and Short-Term Decisions

12.1 Relevant Cost Concepts: Future, Incremental, and Opportunity Costs 12.2 Relevant Costs of Materials, Labour, and Overheads 12.3 Short-Term Operational Decisions: Make-or-Buy, Shutdowns, Special Orders

13 Chapter 13: Breakeven Analysis and Limiting Factor Analysis

13.1 Single-Product Break-Even Analysis & Margin of Safety 13.2 Target Profit Calculations, Operating Gearing & CVP Assumptions 13.3 Multi-Product CVP Analysis & Break-Even Charts 13.4 Limiting Factor Analysis (Key Factor Analysis)

14 Chapter 14: Long-Term Decisions: Time Value of Money, Payback, NPV and IRR

14.1 Time Value of Money: Compounding, Discounting, Annuities & Perpetuities 14.2 Payback Period Method: Constant and Uneven Cash Flows 14.3 Net Present Value (NPV): Methodology and Decision Rules 14.4 Internal Rate of Return (IRR) and Interpolation

10.3 Job and Batch Costing: Job Cost Cards, Job Accounts and Pricing a Job

Key Takeaways Explain This Topic AI

Job costing accumulates costs for an individual customer order, using material requisitions, time records and predetermined overhead absorption rates.

Each job is a sub-account of work-in-progress; when a job is completed and delivered, its cost is transferred to cost of sales (or to finished goods if it is held).

Batch costing treats a batch of identical units as a job and calculates cost per unit as total batch cost divided by the number of good units produced.

A job quotation adds non-production overheads to production cost to find total cost, then adds profit as either a mark-up on cost or a margin on price.

Last updated: September 2026

Why this topic is examined

Syllabus area C4(c) asks you to prepare appropriate accounts for job and batch costing . Questions ask you to complete a job cost card, calculate the cost or price of a job, find a batch cost per unit, or identify the correct accounting entry when a job is finished. Process costing and contract costing are not part of the BA2 syllabus.

When job and batch costing are used

Method Cost unit Typical industries

Job costing An individual order made to a customer's specification Printing, engineering workshops, vehicle repairs, building work, accountancy and consultancy assignments

Batch costing A batch of identical items made together Pharmaceuticals, clothing, bakery products, electronic components

Both are forms of specific order costing : each job or batch has its own identity, and costs are collected separately for it.

The job cost card and its source documents

Each job is given a number and a job cost card (or job cost sheet) on which costs are accumulated:

Cost element Source document How it is valued

Direct materials Materials requisition (and materials returned notes) Issue price per the inventory valuation method

  • Direct labour Job time sheets or time records Hours worked on the job × hourly rate
  • Direct expenses Invoices for items bought specifically for the job Actual cost
  • Production overhead Hours recorded on the job Predetermined absorption rate per cost centre (Section 3.2)
  • Non-production overhead Not recorded until the job is complete Often a percentage of production cost

Note

Materials returned to stores from a job reduce that job's material cost. Overtime premium is normally treated as an overhead, unless the overtime was worked specifically at the customer's request for that job, in which case it is a direct cost of the job.

Worked example: Job 247

A workshop has been asked to quote for Job 247.

  • Item Details
  • Direct materials 400 kg issued at $6 per kg; 20 kg later returned to stores
  • Direct labour, Department A 30 hours at $15
  • Direct labour, Department B 20 hours at $18
  • Direct expense Hire of a special tool: $200
  • Overhead, Department A Absorbed at $12 per direct labour hour
  • Overhead, Department B Absorbed at $20 per machine hour; the job uses 25 machine hours
  • Non-production overhead 20% of production cost
  • Pricing policy 25% margin on selling price
  • Job cost card
  • Job 247 $
  • Direct materials (400 kg × $6) 2,400
  • Less materials returned (20 kg × $6) (120)
  • Direct labour: Dept A (30 × $15) 450
  • Direct labour: Dept B (20 × $18) 360
  • Direct expense: tool hire 200
  • Prime cost 3,290
  • Production overhead: Dept A (30 × $12) 360
  • Production overhead: Dept B (25 × $20) 500
  • Total production cost 4,150
  • Non-production overhead (20% × $4,150) 830
  • Total cost 4,980
  • Profit (balancing figure) 1,660
  • Selling price ($4,980 ÷ 0.75) 6,640

Check: profit of $1,660 ÷ price of $6,640 = 25%. A 25% mark-up on cost would have given $6,225, so reading "margin" correctly matters. (Section 4.3 covers mark-ups and margins in detail.)

Job accounts in the ledger

In an integrated system (Section 10.1), each job is effectively a sub-account of the WIP control account :

  • Event Debit Credit
  • Direct materials issued to Job 247 Job 247 (WIP) Raw materials control
  • Materials returned from Job 247 Raw materials control Job 247 (WIP)
  • Direct labour charged to Job 247 Job 247 (WIP) Wages control
  • Direct expense for Job 247 Job 247 (WIP) Payables
  • Overhead absorbed by Job 247 Job 247 (WIP) Production overhead control
  • Job 247 completed and delivered Cost of sales Job 247 (WIP)
  • Invoice raised for Job 247 Receivables Sales

If a completed job is held before delivery, its cost is transferred to finished goods first. The total of all incomplete jobs at the period end equals the closing WIP balance.

Job 247 account

  • Debit $ Credit $
  • Raw materials 2,400 Raw materials (returns) 120
  • Wages (Depts A and B) 810 Cost of sales (on completion) 4,150
  • Payables (tool hire) 200
  • Production overhead absorbed 860
  • Total 4,270 Total 4,270

Non-production overhead is charged to the statement of profit or loss as a period cost; it is included in the quotation to make sure the price covers it, but it is not part of the job's inventory value.

Batch costing

In batch costing, the batch is treated as a job. Costs are collected on a batch cost card , and the cost per unit is found at the end: Cost per unit = Total batch cost Number of good units in the batch \text{Cost per unit} = \frac{\text{Total batch cost}}{\text{Number of good units in the batch}} Cost per unit = Number of good units in the batch Total batch cost ​

Worked example: batch of circuit boards

A batch of 2,000 circuit boards incurs:

  • Batch 88 $
  • Direct materials 3,600
  • Direct labour (70 hours × $20) 1,400
  • Machine set-up cost 300
  • Production overhead (70 hours × $25) 1,750

Total batch cost 7,050 Cost per board = $ 7,050 2,000 = $ 3.525 \text{Cost per board} = \frac{\text{\textdollar}7{,}050}{2{,}000} = \text{\textdollar}3.525 Cost per board = 2 , 000 $ 7 , 050 ​ = $ 3.525

Set-up costs are incurred once per batch however many units are made, so larger batches spread set-up cost over more units and reduce the cost per unit. If 50 boards failed inspection and were scrapped with no value, the cost of the 1,950 good boards would be $7,050 ÷ 1,950 = $3.615 each.

Using job costs for control and pricing

Quotations: estimated job costs underpin prices. Past job cards help estimate new jobs.

Profitability: comparing actual job cost with the price charged shows which jobs and customers are profitable.

Control: comparing actual job cost with the estimate highlights overruns in materials or hours while the job is in progress.

Tip

Build the job cost card in the order prime cost, production cost, total cost, price. Most wrong answers come from applying the non-production percentage to prime cost instead of production cost, or from confusing margin with mark-up.

Loading diagram... Job Costing Flow