Job-Order and Process Costing
CMA Part 1 Certified Management Accountant
Track your progress as you read
Finished sections get a check mark.
1 Introduction
About the CMA Part 1 Exam Exam Structure and Content Breakdown Pass Rates and Scoring How to Use This Study Guide
2 1. External Financial Reporting Decisions
1.A Financial Statement Preparation 1.B Revenue Recognition 1.C Lease Accounting 1.D Inventory and Fixed Assets 1.E Financial Statement Analysis
3 Planning, Budgeting, and Forecasting
Strategic Planning Process Budgeting Methodologies Sales and Production Budgets Financial Budgets Forecasting Techniques
4 Performance Management
Variance Analysis Fundamentals Manufacturing Variances Responsibility Accounting Transfer Pricing Performance Measurement Systems
5 Cost Management
Cost Concepts and Classifications Job-Order and Process Costing Activity-Based Costing Cost-Volume-Profit Analysis Relevant Costing and Decision Making
6 Internal Controls
Internal Control Frameworks Enterprise Risk Management Internal Audit Function Governance and Compliance Fraud Prevention and Detection
7 Technology and Analytics
Data Governance and Management Business Intelligence and Dashboards Predictive Analytics and Modeling Data Visualization Best Practices Emerging Technologies in Finance
Job-Order and Process Costing
Key Takeaways Explain This Topic AI
Job-order costing traces costs to specific jobs or batches; used for custom/unique products.
Process costing averages costs across homogeneous units; used for mass production.
Equivalent units measure the work done on partially completed units.
FIFO method separates beginning inventory costs from current period costs.
Weighted average method combines beginning inventory and current period costs.
Last updated: January 2026
Quick Answer: Job-order costing assigns costs to specific jobs/batches for custom products. Process costing averages costs across equivalent units for mass production. FIFO separates beginning inventory from current costs; weighted average combines them. Equivalent units convert partial work into full-unit equivalents.
The choice between job-order and process costing depends on the nature of production. Custom products use job costing; homogeneous mass production uses process costing.
Job-Order Costing System
Job-order costing is used when products are distinct and identifiable —each job can be separately tracked.
When to Use Job-Order Costing
- Industry Examples
- Construction Building projects, custom homes
- Manufacturing Custom machinery, special orders
- Professional Services Accounting engagements, legal cases
- Printing Custom print jobs, specialized publications
- Healthcare Individual patient treatments
- Job Cost Sheet
Each job has a job cost sheet that accumulates:
- Cost Component How Tracked
- Direct Materials Materials requisition forms
- Direct Labor Time tickets/labor cards
- Manufacturing Overhead Predetermined overhead rate
- Predetermined Overhead Rate (POHR)
Since actual overhead isn't known until period-end, manufacturers use a predetermined overhead rate calculated at the beginning of the year:
Formula: POHR = Estimated Total MOH ÷ Estimated Total Allocation Base
Common Allocation Bases:
- Direct labor hours
- Direct labor cost
- Machine hours
- Direct materials cost
- Example: Estimated MOH = \$500,000
- Estimated DL Hours = 25,000 hours
- POHR = \$500,000 ÷ 25,000 = \$20 per DL hour
- Applied vs. Actual Overhead
- Term Definition
- Applied Overhead POHR × Actual allocation base
- Actual Overhead Real overhead costs incurred
- Overapplied Applied > Actual (credit balance)
- Underapplied Applied < Actual (debit balance)
Disposing of Over/Underapplied Overhead:
- Close to COGS (most common, if immaterial)
- Prorate to WIP, FG, and COGS (if material)
- Job Costing Example
- Job #101 Amount
- Direct Materials $5,000
- Direct Labor (100 hrs × $25) $2,500
- Applied Overhead (100 hrs × $20) $2,000
- Total Job Cost $9,500
- Process Costing System
Process costing is used for homogeneous, mass-produced products where individual units are indistinguishable.
When to Use Process Costing
- Industry Examples
- Chemical Paints, fertilizers, plastics
- Food/Beverage Soft drinks, canned goods
- Petroleum Gasoline, oil products
- Paper Newsprint, cardboard
- Textiles Fabric, thread
- Key Concepts in Process Costing
Equivalent Units (EU): Convert partially completed units to the equivalent number of completed units. Equivalent Units = Physical Units × Percentage Complete
- Example: 1,000 units that are 40% complete = 400 equivalent units
- Process Costing Methods
- Method Beginning WIP Treatment When to Use
- Weighted Average Combined with current costs Simpler, common practice
- FIFO Kept separate from current costs More accurate, changing costs
- Weighted Average Method
The weighted average method combines beginning WIP costs with current period costs .
Steps for Weighted Average:
- Step 1: Physical Flow of Units Units to Account For = Beginning WIP + Units Started
- Units Accounted For = Units Completed + Ending WIP
- Step 2: Calculate Equivalent Units EU = Units Completed + (Ending WIP × % Complete)
- Step 3: Calculate Cost per Equivalent Unit Cost per EU = (Beginning WIP Cost + Current Period Cost) ÷ Total EU
- Step 4: Assign Costs Cost of Completed Units = Units Completed × Cost per EU
- Cost of Ending WIP = EU in Ending WIP × Cost per EU
- Weighted Average Example
- Data Materials Conversion
- Beginning WIP (2,000 units, 100% materials, 60% conversion)
- Beginning WIP costs $10,000 $6,000
- Units started 8,000
- Current period costs $40,000 $54,000
- Units completed 7,000
- Ending WIP (3,000 units, 100% materials, 40% conversion)
Equivalent Units (Weighted Average):
- Materials Conversion
- Completed 7,000 7,000
- Ending WIP 3,000 × 100% = 3,000 3,000 × 40% = 1,200
- Total EU 10,000 8,200
- Cost per Equivalent Unit: Materials: (\$10,000 + \$40,000) ÷ 10,000 = \$5.00 per EU
- Conversion: (\$6,000 + \$54,000) ÷ 8,200 = \$7.317 per EU
- FIFO Method
FIFO separates beginning WIP costs from current period costs , providing more accurate current-period cost information.
Steps for FIFO:
Step 1: Physical Flow (same as weighted average)
Step 2: Calculate Equivalent Units EU = Work to complete Beginning WIP + Units Started and Completed + Ending WIP
- Step 3: Calculate Cost per EU (current period only) Cost per EU = Current Period Costs ÷ FIFO Equivalent Units
- Step 4: Assign Costs
- Beginning WIP costs flow out first
- Current costs applied to remaining work
- FIFO Example (Same Data)
Equivalent Units (FIFO):
- Materials Conversion
- Complete Beginning WIP 2,000 × 0% = 0 2,000 × 40% = 800
- Started and Completed 5,000 5,000
- Ending WIP 3,000 × 100% = 3,000 3,000 × 40% = 1,200
- Total EU 8,000 7,000
- Cost per Equivalent Unit (Current Period Only): Materials: \$40,000 ÷ 8,000 = \$5.00 per EU
- Conversion: \$54,000 ÷ 7,000 = \$7.714 per EU
- Cost Reconciliation
A cost reconciliation verifies that total costs to account for equal total costs accounted for: Costs to Account For = Beginning WIP + Current Period Costs
Costs Accounted For = Completed Units + Ending WIP
These amounts must balance—this is a critical check in process costing.
Comparing Job-Order and Process Costing
- Characteristic Job-Order Process
- Product Type Custom, unique Homogeneous, mass
- Cost Accumulation By job By department/process
- Cost Object Individual job Equivalent units
- Documents Job cost sheets Production reports
- Industries Construction, custom manufacturing Chemicals, food, petroleum