2.4 Required Tests: Water, Air, and Backflow Assembly Testing
Colorado Journeyworker Plumber Journeyman Plumber
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Passing the Colorado Journeyworker Plumber Exam
1.1 Exam Blueprint, Format, and the 2024 Code Changeover 1.2 Colorado Licenses, Experience Hours, and Apprentice Supervision 1.3 Permits, Inspections, Blue Tags, and Board Enforcement
2 Chapter 2: General Regulations (IPC Chapter 3)
2.1 Approved Materials, Certification, and General Installation Rules 2.2 Protection of Pipes: Contact, Notching, Shield Plates, and Freezing 2.3 Piping Support, Trenching, Bedding, and Backfill 2.4 Required Tests: Water, Air, and Backflow Assembly Testing
3 Chapter 3: Fixtures and Equipment (IPC Chapter 4)
3.1 Minimum Fixture Counts, Separate Facilities, and Toilet Room Location 3.2 Fixture Clearances, Compartments, and Setting Requirements 3.3 Water Closets, Urinals, Lavatories, Sinks, and Flush Devices 3.4 Showers, Bathtubs, Fixture Fittings, and Scald Protection
4 Chapter 4: Water Heaters (IPC Chapter 5)
4.1 Water Heater Installation, Location, Access, and Clearances 4.2 Relief Valves and Discharge Piping 4.3 Water Heater Pans, Pan Drains, and Storage Tank Requirements 4.4 Thermal Expansion Control and Hot Water Temperature Limits
5 Chapter 5: Water Supply Materials and Installation (IPC Chapter 6)
5.1 Water Service and Distribution Materials, and Sewer Separation 5.2 Joints, Connections, and Dissimilar Materials in Water Piping 5.3 Valves, Shutoffs, and Required Valve Locations
6 Chapter 6: Water Supply Sizing and Pressure (IPC Chapter 6 and Appendix E)
6.1 Pressure Limits, Pressure Reducing Valves, and Water Hammer 6.2 Water Supply Fixture Units and Estimating Demand 6.3 Sizing Water Piping with Appendix E and Table E104.1
7 Chapter 7: Cross-Connection Control and Backflow Prevention (IPC Sections 608-610, Chapter 13)
7.1 Cross-Connection Principles, Backsiphonage, and Backpressure 7.2 Air Gaps and the Backflow Preventer Family 7.3 Applying Backflow Protection to Specific Connections 7.4 Nonpotable Water Systems, Identification, and Reclaimed Water
8 Chapter 8: Sanitary Drainage Materials and Fittings (IPC Chapter 7)
8.1 Sanitary Drainage Materials and Where Each May Be Used 8.2 Drainage Joints, Transitions, and Prohibited Connections 8.3 Fittings for Change of Direction and Drainage Flow Patterns
9 Chapter 9: Sanitary Drainage Sizing (IPC Sections 704, 709-711)
9.1 Drainage Fixture Units and Load Estimation 9.2 Slope of Horizontal Drainage and Installation Rules 9.3 Sizing Building Drains, Building Sewers, and Horizontal Branches 9.4 Stacks, Branch Intervals, and Offsets in Tall Buildings
10 Chapter 10: Cleanouts, Sumps and Below-Sewer Drainage (IPC Sections 708, 712-716)
10.1 Cleanouts, Manholes, and Access Requirements 10.2 Backwater Valves and Fixtures Below the Sewer Level 10.3 Sumps, Sewage Ejectors, and Macerating Toilet Systems 10.4 Building Sewers, Private Disposal, and Special Drainage Conditions
11 Chapter 11: Vent Fundamentals and Terminals (IPC Sections 901-905, 908)
11.1 How Vents Work, Trap Seal Loss, and the One-Inch Rule 11.2 Vent Terminals, Roof Penetrations, and Sidewall Terminations 11.3 Vent Connections, Grade, and the Six-Inch Rules
12 Chapter 12: Vent Types and Sizing (IPC Sections 906-911, 917)
12.1 Individual Vents, Common Vents, and Vents for Stack Offsets 12.2 Trap-to-Vent Distance, Trap Arms, and Fixture Drains 12.3 Sizing Stack Vents, Vent Stacks, Branch Vents, and Headers 12.4 Putting a Vent System Together: A Worked Building
13 Chapter 13: Engineered and Special Venting (IPC Sections 912-916, 918-920)
13.1 Horizontal and Vertical Wet Venting 13.2 Waste Stack Vents, Circuit Vents, and Combination Waste and Vent 13.3 Island Fixture Venting and Air Admittance Valves
14 Chapter 14: Traps, Interceptors and Separators (IPC Chapter 10)
14.1 Fixture Traps, Trap Seals, and Prohibited Trap Types 14.2 Trap Seal Protection, Primers, and Barrier Devices 14.3 Grease Interceptors, Oil Separators, and Solids Interceptors
15 Chapter 15: Indirect and Special Waste (IPC Chapter 8)
15.1 Where Indirect Waste Is Required, and Air Gap Versus Air Break 15.2 Waste Receptors, Hub Drains, and Standpipes 15.3 Special Wastes, Chemical Neutralization, and Health Care Drainage
16 Chapter 16: Storm Drainage (IPC Chapter 11 and Appendix B)
16.1 Storm Drainage Scope, Disposal, and Prohibited Connections 16.2 Storm Drainage Materials, Roof Drains, and Conductors 16.3 Secondary Roof Drains, Scuppers, and Controlled Flow Systems 16.4 Rainfall Rates, Roof Area, and the Flow-Rate Conversion 16.5 Sizing Vertical Conductors, Leaders, and Storm Drains 16.6 Gutters, Subsoil Drains, Building Subdrains, and Storm Sumps
17 Chapter 17: Residential Fire Sprinklers (IRC Section P2904)
17.1 Residential Fire Sprinkler Systems (IRC Section P2904)
18 Chapter 18: Isometric Analysis and Plumbing Calculations
18.1 Reading Plumbing Isometrics and Riser Diagrams 18.2 Analyzing a DWV Isometric for Code Compliance 18.3 Offsets, Travel, and the Plumbing Math the Exam Assumes
2.4 Required Tests: Water, Air, and Backflow Assembly Testing
Key Takeaways Explain This Topic AI
IPC 312.2 requires the drainage and vent water test to apply not less than a 10-foot head of water, held for not less than 15 minutes.
IPC 312.3 sets the drainage and vent air test at a uniform gauge pressure of 5 psi, or enough to balance a 10-inch column of mercury, held not less than 15 minutes.
IPC 312.3 states that plastic piping shall not be tested using air, a sentence Colorado deletes by Board Rule 1.2(E)(1)(m).
IPC 312.5 tests the water supply system at not less than the working pressure with water, or by a 50 psi air test for piping systems other than plastic, held 15 minutes.
IPC 312.10.2 requires backflow prevention assemblies to be tested at installation, immediately after repairs or relocation, and at least annually.
Last updated: September 2026
Whose job the test is
IPC 312.1 assigns the work: the permit holder makes the applicable tests, gives reasonable advance notice to the code official when the plumbing is ready, and furnishes the equipment, material, power and labor for the inspection and test. The permit holder — not the inspector — is responsible for determining that the work will withstand the prescribed pressure.
That has a practical consequence Colorado codifies separately. Board Rule 1.6(B)(3) requires the installation to be "complete and under test " before you request the inspection, and Rule 1.6(B)(5)(a) authorizes a reinspection fee when the job is not ready and an extra trip is required. An inspector who arrives to a zeroed gauge does not troubleshoot your system; the inspection fails and the reinspection fee attaches.
- IPC 312.1 also says systems are tested "with either water or, for piping systems other than plastic, by air."
- Test gauges — IPC 312.1.1
The code specifies gauge resolution, and exam items do ask for it:
- Test pressure Required gauge increments
- 10 psi or less 0.10 psi or less
- Greater than 10 psi through 100 psi 1 psi or less
- Greater than 100 psi 2 psi or less
A DWV air test at 5 psi therefore demands a 0.10 psi gauge. A 100-pound shop gauge reading in 5-pound steps is not an acceptable instrument for that test, which is exactly why a slow leak can pass unnoticed on the wrong gauge.
- The DWV tests
- 312.2 Drainage and vent water test
Apply water to the drainage system in its entirety or in sections .
Entire system: close all openings tightly except the highest , and fill to the point of overflow .
In sections: plug each opening except the highest opening of the section under test ; no section may be tested with less than a 10-foot head of water .
Successive sections: not less than the upper 10 feet of the preceding section must be re-tested, so that no joint or pipe in the building — except the uppermost 10 feet — has been subjected to less than a 10-foot head.
Hold for not less than 15 minutes. The system shall then be tight at all points.
A 10-foot head is 4.33 psi at the base (10 ft / 2.31 ft per psi).
312.3 Drainage and vent air test
Plastic piping shall not be tested using air. An air test shall be made by forcing air into the system until there is a uniform gauge pressure of 5 psi , or sufficient to balance a 10-inch column of mercury . This pressure shall be held for a test period of not less than 15 minutes .
Adjustments for ambient temperature change or gasket seating must be made before the 15-minute test period begins — not during it.
Colorado field note (not exam-scored): Board Rule 1.2(E)(1)(m) deletes the sentence "Plastic piping shall not be tested using air." In Colorado you may air test PVC and ABS DWV, which is why the 5 psi air test is the everyday Colorado rough-in test. On the exam, the model-code answer is that plastic shall not be air tested . Keep the two answers in separate mental drawers.
312.4 Drainage and vent final test
The final test of the completed drainage and vent system is visual and in sufficient detail to determine code compliance. Where a smoke test is used, fill all traps with water, introduce thick pungent smoke from one or more smoke machines, and when smoke appears at the stack openings on the roof, close those openings and hold a pressure equivalent to a 1-inch water column for not less than 15 minutes .
Colorado field note: Board Rule 1.2(E)(1)(n) deletes 312.4 in its entirety , and Rule 1.2(E)(1)(l) removes the matching final-test sentence from 312.1.
The supply-side and sewer tests
Test Section Requirement
Water supply system 312.5 Water at not less than the working pressure of the system; or, for piping other than plastic, an air test of not less than 50 psi . Hold 15 minutes . Test water must come from a potable source
Gravity sewer 312.6 Plug the end of the building sewer at the public sewer connection, fill with water, test with not less than a 10-foot head , maintain 15 minutes
Forced sewer 312.7 Plug at the public sewer connection and apply 5 psi greater than the pump rating , maintain 15 minutes
Storm drainage 312.8 Storm drains within a building are tested by water or air per 312.2 or 312.3
Shower liner 312.9 Plug the shower drain watertight, fill the floor or receptor with potable water to not less than 2 inches measured at the threshold , hold not less than 15 minutes with no evidence of leakage
Notice the constant: 15 minutes is the holding period for nearly every test in Section 312. The variable is the pressure.
Colorado field notes: Rule 1.2(E)(1)(o) removes the "other than plastic" limitation from 312.5, so plastic water piping may be air tested in Colorado. Rule 1.2(E)(1)(p) deletes 312.9 shower liner test from the Colorado Plumbing Code.
Backflow assembly inspection and testing
IPC 312.10.1 requires annual inspections of all backflow prevention assemblies and air gaps to determine whether the assemblies are operable and the air gaps exist.
IPC 312.10.2 requires reduced pressure principle, double check, pressure vacuum breaker, reduced pressure detector fire protection, double check detector fire protection and spill-resistant vacuum breaker assemblies, plus hose connection backflow preventers , to be tested:
- at the time of installation ,
- immediately after repairs or relocation , and
at least annually .
Testing follows ASSE 5013, 5015, 5020, 5047, 5048, 5052, 5056, CSA B64.10 or CSA B64.10.1, and test gauges must comply with ASSE 1064 .
Colorado field note: Board Rule 1.2(E)(1)(q) rewrites 312.10.2 to require the test be performed by a certified cross-connection control technician — a person holding a valid Backflow Prevention Assembly Tester certification from ASSE, the American Backflow Prevention Association, or another Board-recognized agency (Rule 1.2(D)(8)(a)) — and adds the USC Foundation for Cross-Connection Control and Hydraulic Research 10th Edition Manual as an approved procedure.
Worked example: staging a three-story rough-in
A three-story building has a DWV stack 34 feet from the building drain to the roof terminal.
Underground (Colorado inspection category 1): the below-grade DWV is capped and filled to produce at least a 10-foot head, or air tested at 5 psi with a 0.10 psi gauge. Hold 15 minutes.
Section 1 of the stack , floors 1-2: plug all openings except the highest of that section; fill so the section sees at least a 10-foot head.
Section 2 , floors 2-3: re-test the upper 10 feet of section 1 along with section 2, so no joint below the top 10 feet of the building ever sees less than a 10-foot head.
Water supply at rough-in: pressurize to working pressure with potable water — or, on metallic piping under the model code, 50 psi of air — and hold 15 minutes.
Request the inspection only once every system is complete and holding , with plans on site for a commercial job, ladders provided and the address visible from the street.