Study guide
8.1 Sanitary Drainage Materials and Where Each May Be Used
Colorado Journeyworker Plumber Journeyman Plumber
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Passing the Colorado Journeyworker Plumber Exam
1.1 Exam Blueprint, Format, and the 2024 Code Changeover 1.2 Colorado Licenses, Experience Hours, and Apprentice Supervision 1.3 Permits, Inspections, Blue Tags, and Board Enforcement
2 Chapter 2: General Regulations (IPC Chapter 3)
2.1 Approved Materials, Certification, and General Installation Rules 2.2 Protection of Pipes: Contact, Notching, Shield Plates, and Freezing 2.3 Piping Support, Trenching, Bedding, and Backfill 2.4 Required Tests: Water, Air, and Backflow Assembly Testing
3 Chapter 3: Fixtures and Equipment (IPC Chapter 4)
3.1 Minimum Fixture Counts, Separate Facilities, and Toilet Room Location 3.2 Fixture Clearances, Compartments, and Setting Requirements 3.3 Water Closets, Urinals, Lavatories, Sinks, and Flush Devices 3.4 Showers, Bathtubs, Fixture Fittings, and Scald Protection
4 Chapter 4: Water Heaters (IPC Chapter 5)
4.1 Water Heater Installation, Location, Access, and Clearances 4.2 Relief Valves and Discharge Piping 4.3 Water Heater Pans, Pan Drains, and Storage Tank Requirements 4.4 Thermal Expansion Control and Hot Water Temperature Limits
5 Chapter 5: Water Supply Materials and Installation (IPC Chapter 6)
5.1 Water Service and Distribution Materials, and Sewer Separation 5.2 Joints, Connections, and Dissimilar Materials in Water Piping 5.3 Valves, Shutoffs, and Required Valve Locations
6 Chapter 6: Water Supply Sizing and Pressure (IPC Chapter 6 and Appendix E)
6.1 Pressure Limits, Pressure Reducing Valves, and Water Hammer 6.2 Water Supply Fixture Units and Estimating Demand 6.3 Sizing Water Piping with Appendix E and Table E104.1
7 Chapter 7: Cross-Connection Control and Backflow Prevention (IPC Sections 608-610, Chapter 13)
7.1 Cross-Connection Principles, Backsiphonage, and Backpressure 7.2 Air Gaps and the Backflow Preventer Family 7.3 Applying Backflow Protection to Specific Connections 7.4 Nonpotable Water Systems, Identification, and Reclaimed Water
8 Chapter 8: Sanitary Drainage Materials and Fittings (IPC Chapter 7)
8.1 Sanitary Drainage Materials and Where Each May Be Used 8.2 Drainage Joints, Transitions, and Prohibited Connections 8.3 Fittings for Change of Direction and Drainage Flow Patterns
9 Chapter 9: Sanitary Drainage Sizing (IPC Sections 704, 709-711)
9.1 Drainage Fixture Units and Load Estimation 9.2 Slope of Horizontal Drainage and Installation Rules 9.3 Sizing Building Drains, Building Sewers, and Horizontal Branches 9.4 Stacks, Branch Intervals, and Offsets in Tall Buildings
10 Chapter 10: Cleanouts, Sumps and Below-Sewer Drainage (IPC Sections 708, 712-716)
10.1 Cleanouts, Manholes, and Access Requirements 10.2 Backwater Valves and Fixtures Below the Sewer Level 10.3 Sumps, Sewage Ejectors, and Macerating Toilet Systems 10.4 Building Sewers, Private Disposal, and Special Drainage Conditions
11 Chapter 11: Vent Fundamentals and Terminals (IPC Sections 901-905, 908)
11.1 How Vents Work, Trap Seal Loss, and the One-Inch Rule 11.2 Vent Terminals, Roof Penetrations, and Sidewall Terminations 11.3 Vent Connections, Grade, and the Six-Inch Rules
12 Chapter 12: Vent Types and Sizing (IPC Sections 906-911, 917)
12.1 Individual Vents, Common Vents, and Vents for Stack Offsets 12.2 Trap-to-Vent Distance, Trap Arms, and Fixture Drains 12.3 Sizing Stack Vents, Vent Stacks, Branch Vents, and Headers 12.4 Putting a Vent System Together: A Worked Building
13 Chapter 13: Engineered and Special Venting (IPC Sections 912-916, 918-920)
13.1 Horizontal and Vertical Wet Venting 13.2 Waste Stack Vents, Circuit Vents, and Combination Waste and Vent 13.3 Island Fixture Venting and Air Admittance Valves
14 Chapter 14: Traps, Interceptors and Separators (IPC Chapter 10)
14.1 Fixture Traps, Trap Seals, and Prohibited Trap Types 14.2 Trap Seal Protection, Primers, and Barrier Devices 14.3 Grease Interceptors, Oil Separators, and Solids Interceptors
15 Chapter 15: Indirect and Special Waste (IPC Chapter 8)
15.1 Where Indirect Waste Is Required, and Air Gap Versus Air Break 15.2 Waste Receptors, Hub Drains, and Standpipes 15.3 Special Wastes, Chemical Neutralization, and Health Care Drainage
16 Chapter 16: Storm Drainage (IPC Chapter 11 and Appendix B)
16.1 Storm Drainage Scope, Disposal, and Prohibited Connections 16.2 Storm Drainage Materials, Roof Drains, and Conductors 16.3 Secondary Roof Drains, Scuppers, and Controlled Flow Systems 16.4 Rainfall Rates, Roof Area, and the Flow-Rate Conversion 16.5 Sizing Vertical Conductors, Leaders, and Storm Drains 16.6 Gutters, Subsoil Drains, Building Subdrains, and Storm Sumps
17 Chapter 17: Residential Fire Sprinklers (IRC Section P2904)
17.1 Residential Fire Sprinkler Systems (IRC Section P2904)
18 Chapter 18: Isometric Analysis and Plumbing Calculations
18.1 Reading Plumbing Isometrics and Riser Diagrams 18.2 Analyzing a DWV Isometric for Code Compliance 18.3 Offsets, Travel, and the Plumbing Math the Exam Assumes
8.1 Sanitary Drainage Materials and Where Each May Be Used
Key Takeaways Explain This Topic AI
IPC Table 702.1 governs above-ground sanitary drainage and vent pipe, Table 702.2 governs underground building drainage and vent pipe, and Table 702.3 governs building sewer pipe.
IPC 702.5 requires drainage piping to have a rated working temperature of not less than 140 degrees F, and 180 degrees F where it receives discharge above 140 degrees F.
IPC 702.6 requires chemical waste to discharge to a separate drainage system, independent of the sanitary drainage system.
IPC 702.7 requires lead bends and traps to have a wall thickness of not less than 0.125 inch.
IPC 701.2 requires every plumbing fixture, drain, appurtenance and appliance to be connected to a sanitary sewer, or to an approved private sewage disposal system.
Last updated: September 2026
Why this area carries twenty items
Sanitary Drainage is the single heaviest content area on the exam. Twenty of one hundred scored items come from IPC Chapter 7 and the parallel IRC Chapter 30. This guide splits that weight across three chapters: materials and fittings here, sizing in Chapter 9, and cleanouts, sumps and below-sewer drainage in Chapter 10.
IPC 701.1 sets the scope: Chapter 7 governs materials, design, construction and installation of sanitary drainage systems.
Connection to the sewer — IPC 701.2
Every plumbing fixture, drain, appurtenance and appliance shall be connected to a sanitary sewer or to an approved private sewage disposal system in accordance with this code.
701.3 Separate sewer connection : a building with more than one sewer connection, or a building having plumbing on more than one lot, must have a separate connection for each lot or building as required by the administrative authority.
701.4 Sewage treatment : sewage or other waste from a plumbing system deleterious to surface or subsurface waters shall not be discharged into the ground or into any waterway unless first rendered innocuous by approved treatment.
701.5 Damage to drainage system or public sewer : waste detrimental to the public sewer or to the functioning of the sewage treatment plant shall be treated and disposed of as directed by the code official.
701.6 Tests : drainage and vent systems are tested per IPC 312 .
701.7 Engineered systems : engineered drainage design complies with IPC 316.1 .
Colorado field note (not exam-scored): Board Rule 1.2(E)(1)(ii) adds an exception to 701.2 permitting floor drains or trench drains in utility buildings and residential garages to be daylighted or discharged to an approved alternative disposal system when written approval has been provided by the jurisdiction having authority through CDPHE or the sewer purveyor.
Three material tables, three applications
The single most common material mistake is applying the wrong table. Read the table title before the material list.
- Table Application
- 702.1 Above-ground sanitary drainage and vent pipe
- 702.2 Underground building sanitary drainage and vent pipe
- 702.3 Building sewer pipe
- 702.4 Pipe fittings
- What is listed where
- Material Above ground (702.1) Underground (702.2) Building sewer (702.3)
- ABS plastic DWV yes yes yes
- PVC plastic DWV yes yes yes
- Cast-iron pipe yes yes yes
- Copper or copper-alloy pipe yes yes yes
- Copper or copper-alloy tubing (Type K, L, M or DWV) yes yes yes
- Galvanized steel pipe yes no no
- Brass pipe yes no no
- Glass pipe (borosilicate) yes no no
- Stainless steel drainage systems, Type 316L yes yes yes
- Polyolefin / PVDF / polypropylene (chemical waste) yes yes —
- Concrete pipe no no yes
- Vitrified clay pipe no no yes
- Polyethylene (PE) plastic pipe no no yes
- Ductile iron — — yes
The pattern to hold on to: galvanized steel, brass and glass are above-ground materials only , and concrete, vitrified clay and PE are building-sewer materials only . ABS, PVC, cast iron, copper and stainless run through all three tables.
IPC 703.2 Drainage pipe in filled ground : where a building drain or sewer is installed on filled or unstable ground , it must be of materials listed in Table 702.2 or 702.3 — the more robust underground materials.
IPC 703.4 : existing building sewers and drains may be used in connection with new systems only where found on examination and test to conform to the new system in quality of material . This is the rule that decides whether an old clay sewer may be reused after a remodel.
Temperature rating — IPC 702.5
Where the drainage piping is to receive discharge of liquid waste at a temperature greater than 140 degrees F , the piping shall have a rated working temperature of not less than 180 degrees F .
The default expectation is 140 degrees F . Standard PVC and ABS DWV are rated for continuous service well below the boiling point, which is why a commercial dishwasher, a sterilizer or a boiler blowdown line typically discharges through an indirect waste to a receptor (IPC Chapter 8) rather than directly into plastic drainage.
Chemical waste — IPC 702.6
Where a chemical waste is discharged to the drainage system, the chemical waste shall discharge to a separate drainage system , independent of the sanitary drainage system.
Chemical waste piping materials are listed in Table 702.1 and 702.2 — polyolefin, PVDF, borosilicate glass and similar chemically resistant systems. IPC 803 requires corrosive liquids and harmful chemicals to be neutralized to a pH between 6.0 and 8.0 through an approved dilution or neutralizing device before discharge.
IPC 702.7 Lead bends and traps : lead bends and traps shall have a wall thickness of not less than 0.125 inch .
Building sewer installation
Section Rule
703.1 Where the building sewer is within 5 feet of the water service , comply with the separation requirements of 603.2 — 5 feet of undisturbed earth, or Table 702.2 materials, or the crossing/elevation exceptions
- 703.2 Filled or unstable ground requires Table 702.2 or 702.3 materials
- 703.3 Sanitary and storm sewers shall be separate where the public sewer system is separate
- 703.4 Existing sewers and drains reused only where they conform in quality of material
- 703.5 Cleanouts on building sewers per Section 708
- 703.6 Where the public sewer is a combined system , the storm sewer connects independently to the public sewer
Recall IPC 305.4.1 Sewer depth is a bracketed section in the model code — the depth numbers are filled in by the adopting jurisdiction. In Colorado, sewer bury depth is a local determination, not a statewide number.
Pipe bursting — IPC Section 716
A modern section worth knowing because it appears on newer exam forms:
Limited to gravity drainage piping 6 inches and smaller ; the replacement pipe is the same nominal size as the existing piping.
Pre-installation : the piping to be replaced must be inspected internally by a recorded video camera survey , noting cleanout positions and connection depths.
Pipe : high-density polyethylene (HDPE) with a standard dimension ratio (SDR) of 17 , complying with ASTM F714 .
Fittings : HDPE complying with ASTM D2683 .
Cleanouts : where the existing sewer or drain lacked compliant cleanouts, cleanout fittings must be installed as the code requires.
Post-installation : another recorded video camera survey.
Vacuum drainage — IPC Section 715
Designed to the manufacturer's instructions with plans submitted for approval. Two numbers to remember:
The completed system is subjected to a vacuum test of 19 inches of mercury (715.3).
The water supply fixture unit value for a vacuum-type water closet is 1 (715.2.3) — dramatically lower than the 2.2 to 10 wsfu of a conventional water closet, because a vacuum closet uses roughly a pint of water per flush.
Drainage fixture units for gravity fixtures in a vacuum system are still based on the Chapter 7 values, and gravity fixtures still need traps and cleanouts per Chapters 7 and 10.
Computerized drainage design — IPC Section 713
Where a drainage system is designed by approved computer design methods , the load is computed from simultaneous or sequential discharge conditions or the peak usage design condition, with fixture discharge profiles from the manufacturer's specifications. Two constraints survive the computer:
713.3 : pipe shall be sized to prevent full-bore flow .
713.3.2 : horizontal drainage piping is still installed at the slopes in Table 704.1 .