14.3 Grease Interceptors, Oil Separators, and Solids Interceptors

Colorado Journeyworker Plumber Journeyman Plumber

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Passing the Colorado Journeyworker Plumber Exam

1.1 Exam Blueprint, Format, and the 2024 Code Changeover 1.2 Colorado Licenses, Experience Hours, and Apprentice Supervision 1.3 Permits, Inspections, Blue Tags, and Board Enforcement

2 Chapter 2: General Regulations (IPC Chapter 3)

2.1 Approved Materials, Certification, and General Installation Rules 2.2 Protection of Pipes: Contact, Notching, Shield Plates, and Freezing 2.3 Piping Support, Trenching, Bedding, and Backfill 2.4 Required Tests: Water, Air, and Backflow Assembly Testing

3 Chapter 3: Fixtures and Equipment (IPC Chapter 4)

3.1 Minimum Fixture Counts, Separate Facilities, and Toilet Room Location 3.2 Fixture Clearances, Compartments, and Setting Requirements 3.3 Water Closets, Urinals, Lavatories, Sinks, and Flush Devices 3.4 Showers, Bathtubs, Fixture Fittings, and Scald Protection

4 Chapter 4: Water Heaters (IPC Chapter 5)

4.1 Water Heater Installation, Location, Access, and Clearances 4.2 Relief Valves and Discharge Piping 4.3 Water Heater Pans, Pan Drains, and Storage Tank Requirements 4.4 Thermal Expansion Control and Hot Water Temperature Limits

5 Chapter 5: Water Supply Materials and Installation (IPC Chapter 6)

5.1 Water Service and Distribution Materials, and Sewer Separation 5.2 Joints, Connections, and Dissimilar Materials in Water Piping 5.3 Valves, Shutoffs, and Required Valve Locations

6 Chapter 6: Water Supply Sizing and Pressure (IPC Chapter 6 and Appendix E)

6.1 Pressure Limits, Pressure Reducing Valves, and Water Hammer 6.2 Water Supply Fixture Units and Estimating Demand 6.3 Sizing Water Piping with Appendix E and Table E104.1

7 Chapter 7: Cross-Connection Control and Backflow Prevention (IPC Sections 608-610, Chapter 13)

7.1 Cross-Connection Principles, Backsiphonage, and Backpressure 7.2 Air Gaps and the Backflow Preventer Family 7.3 Applying Backflow Protection to Specific Connections 7.4 Nonpotable Water Systems, Identification, and Reclaimed Water

8 Chapter 8: Sanitary Drainage Materials and Fittings (IPC Chapter 7)

8.1 Sanitary Drainage Materials and Where Each May Be Used 8.2 Drainage Joints, Transitions, and Prohibited Connections 8.3 Fittings for Change of Direction and Drainage Flow Patterns

9 Chapter 9: Sanitary Drainage Sizing (IPC Sections 704, 709-711)

9.1 Drainage Fixture Units and Load Estimation 9.2 Slope of Horizontal Drainage and Installation Rules 9.3 Sizing Building Drains, Building Sewers, and Horizontal Branches 9.4 Stacks, Branch Intervals, and Offsets in Tall Buildings

10 Chapter 10: Cleanouts, Sumps and Below-Sewer Drainage (IPC Sections 708, 712-716)

10.1 Cleanouts, Manholes, and Access Requirements 10.2 Backwater Valves and Fixtures Below the Sewer Level 10.3 Sumps, Sewage Ejectors, and Macerating Toilet Systems 10.4 Building Sewers, Private Disposal, and Special Drainage Conditions

11 Chapter 11: Vent Fundamentals and Terminals (IPC Sections 901-905, 908)

11.1 How Vents Work, Trap Seal Loss, and the One-Inch Rule 11.2 Vent Terminals, Roof Penetrations, and Sidewall Terminations 11.3 Vent Connections, Grade, and the Six-Inch Rules

12 Chapter 12: Vent Types and Sizing (IPC Sections 906-911, 917)

12.1 Individual Vents, Common Vents, and Vents for Stack Offsets 12.2 Trap-to-Vent Distance, Trap Arms, and Fixture Drains 12.3 Sizing Stack Vents, Vent Stacks, Branch Vents, and Headers 12.4 Putting a Vent System Together: A Worked Building

13 Chapter 13: Engineered and Special Venting (IPC Sections 912-916, 918-920)

13.1 Horizontal and Vertical Wet Venting 13.2 Waste Stack Vents, Circuit Vents, and Combination Waste and Vent 13.3 Island Fixture Venting and Air Admittance Valves

14 Chapter 14: Traps, Interceptors and Separators (IPC Chapter 10)

14.1 Fixture Traps, Trap Seals, and Prohibited Trap Types 14.2 Trap Seal Protection, Primers, and Barrier Devices 14.3 Grease Interceptors, Oil Separators, and Solids Interceptors

15 Chapter 15: Indirect and Special Waste (IPC Chapter 8)

15.1 Where Indirect Waste Is Required, and Air Gap Versus Air Break 15.2 Waste Receptors, Hub Drains, and Standpipes 15.3 Special Wastes, Chemical Neutralization, and Health Care Drainage

16 Chapter 16: Storm Drainage (IPC Chapter 11 and Appendix B)

16.1 Storm Drainage Scope, Disposal, and Prohibited Connections 16.2 Storm Drainage Materials, Roof Drains, and Conductors 16.3 Secondary Roof Drains, Scuppers, and Controlled Flow Systems 16.4 Rainfall Rates, Roof Area, and the Flow-Rate Conversion 16.5 Sizing Vertical Conductors, Leaders, and Storm Drains 16.6 Gutters, Subsoil Drains, Building Subdrains, and Storm Sumps

17 Chapter 17: Residential Fire Sprinklers (IRC Section P2904)

17.1 Residential Fire Sprinkler Systems (IRC Section P2904)

18 Chapter 18: Isometric Analysis and Plumbing Calculations

18.1 Reading Plumbing Isometrics and Riser Diagrams 18.2 Analyzing a DWV Isometric for Code Compliance 18.3 Offsets, Travel, and the Plumbing Math the Exam Assumes

14.3 Grease Interceptors, Oil Separators, and Solids Interceptors

Key Takeaways Explain This Topic AI

IPC 1003.3.2 prohibits a food waste disposer from discharging to a grease interceptor.

IPC 1003.3.7 determines gravity grease interceptor capacity by multiplying peak drain flow in gallons per minute by a retention time of 30 minutes.

IPC 1003.3.5.2 requires grease interceptors to be equipped with flow control devices, vented and terminating not less than 6 inches above the flood rim level.

IPC 1003.4 requires oil separators at repair garages with floor or trench drains, car washing facilities, factories producing oily and flammable liquid wastes, and hydraulic elevator pits.

IPC 1003.4.2.2 requires an oil separator at a garage or service station to have a capacity of not less than 6 cubic feet for the first 100 square feet drained, plus 1 cubic foot for each additional 100 square feet.

Last updated: September 2026

The general requirement — IPC 1003.1

Interceptors and separators shall be provided to prevent the discharge of oil, grease, sand and other substances harmful or hazardous to the public sewer, the private sewage system or the sewage treatment plant or processes .

IPC 1003.2 Approval : size, type and location are designed and installed per the manufacturer's instructions and this section, based on the anticipated conditions of use . Wastes that do not require treatment or separation shall not be discharged into any interceptor or separator — sending clean waste through a grease interceptor dilutes its retention and shortens its service interval.

Colorado field note (not exam-scored): Board Rule 1.2(E)(1)(vv) adds an exception to 1003.1 where special regulations exist by the local wastewater or sanitation district into which the grease trap or interceptor effluent is transported or treated: those regulations may supersede the IPC requirement. In Colorado, always check with the district before sizing.

  • Grease interceptors — IPC 1003.3
  • 1003.3.1 Where required

A grease interceptor or automatic grease removal device is required to receive drainage from fixtures and equipment with grease-laden waste located in food preparation areas , such as restaurants, hotel kitchens, hospitals, school kitchens, bars, factory cafeterias and clubs. The fixtures and equipment include:

  • pot sinks ;
  • prerinse sinks ;
  • soup kettles or similar devices ;
  • wok stations ;
  • floor drains or sinks into which kettles are drained ;
  • automatic hood wash units ; and

dishwashers without prerinse sinks .

Interceptors shall receive waste only from fixtures and equipment that allow fats, oils or grease to be discharged . Where space or other constraints prevent installation or replacement, one or more interceptors may be installed on or above the floor and upstream of an existing grease interceptor .

1003.3.4 Where not required

A grease interceptor or an automatic grease removal device shall not be required for individual dwelling units or any private living quarters .

1003.3.2 Food waste disposers

A food waste disposer shall not discharge to a grease interceptor.

Ground food solids overwhelm a grease interceptor's retention volume and are carried through with the effluent.

Colorado field note (not exam-scored): Board Rule 1.2(E)(1)(ww) adds an exception to the food waste disposer restriction "when using a gravity interceptor equal to or greater than 500 gallon capacity ."

1003.3.3 Additives

Dispensing systems that dispense interceptor performance additives are prohibited except where they dispense microbes for aerobic bioremediation of grease and other organic material, or for inhibiting growth of pathogenic organisms by anaerobic methods. Such microbial systems are permitted only where the interceptor manufacturer's instructions allow them and the systems conform to ASME A112.14.6 . Systems that discharge emulsifiers, chemicals or enzymes to grease interceptors shall be prohibited — an emulsifier simply carries the grease past the interceptor and into the sewer.

Two sizing methods

Type Sizing rule Section

Hydromechanical grease interceptors, FOG disposal systems and automatic grease removal devices Sized per ASME A112.14.3, ASME A112.14.4, ASME A112.14.6, CSA B481.3 or PDI G101 ; grease retention capacity per Table 1003.3.5.1 1003.3.5

Gravity grease interceptors Peak drain flow into the interceptor in gpm x a retention time of 30 minutes ; designed and tested per IAPMO/ANSI Z1001 1003.3.7

Table 1003.3.5.1 Capacity of grease interceptors pairs a flow-through rating with a grease retention capacity, and the relationship is simple: retention capacity in pounds is twice the flow-through rating in gpm .

  • Total flow-through rating (gpm) Grease retention capacity (pounds)
  • 4 8
  • 10 20
  • 15 30
  • 20 40
  • 25 50
  • 35 70
  • 50 100
  • 75 150
  • 100 200

Footnote a : for flow-through ratings greater than 100 gpm, double the flow-through rating to determine the grease retention capacity.

Worked gravity interceptor sizing

A restaurant's kitchen fixtures produce a peak drain flow of 45 gpm into a gravity grease interceptor.

Capacity = peak flow x 30 minutes = 45 x 30 = 1,350 gallons.

Compare the hydromechanical route at the same flow: a 50 gpm flow-through unit provides 100 pounds of grease retention capacity under Table 1003.3.5.1 — a far smaller device that must be serviced far more often.

1003.3.5.2 Flow control

Grease interceptors shall be equipped with devices to control the rate of water flow so that the water flow does not exceed the rated flow . The flow-control device shall be vented and terminate not less than 6 inches above the flood rim level , or be installed in accordance with the manufacturer's instructions.

A hydromechanical interceptor separates by residence time. Flow faster than its rating pushes grease straight through. The flow control restricts the rate, and the vent on the flow control prevents the restriction from siphoning the interceptor.

1003.3.6 and 1003.3.8

Automatic grease removal devices are located downstream of each fixture or multiple fixtures per the manufacturer, sized to pretreat the measured or calculated flows for all connected fixtures, with ready access for inspection and maintenance.

1003.3.8 Direct connection : the discharge piping from a grease interceptor shall be directly connected to the sanitary drainage system. Not indirect — directly connected.

Remember the slope rule from IPC 704.1: piping upstream of a grease interceptor slopes not less than 1/4 inch per foot , regardless of size.

Oil separators — IPC 1003.4

At repair garages where floor or trench drains are provided , car washing facilities , factories where oily and flammable liquid wastes are produced and hydraulic elevator pits , oil separators shall be installed into which oil-bearing, grease-bearing or flammable wastes shall be discharged before emptying into the building drainage system or other point of disposal.

Exception: an oil separator is not required in hydraulic elevator pits where an approved alarm system is installed . Such alarm systems shall not terminate the operation of pumps used to maintain emergency operation of the elevator by fire fighters.

Design requirements

Rule Requirement

1003.4.1 A mixture of treated or untreated light and heavy liquids with various specific gravities shall be separated in an approved receptacle

1003.4.2 Oil separators shall be listed and labeled , or designed per 1003.4.2.1 and 1003.4.2.2

1003.4.2.1 Depth not less than 2 feet below the invert of the discharge drain ; the outlet opening shall have not less than an 18-inch water seal

1003.4.2.2 Garages and service stations: capacity not less than 6 cubic feet for the first 100 square feet of area drained, plus 1 cubic foot for each additional 100 square feet

1003.4.2.2 also carves out two cases: parking garages in which servicing, repairing or washing is not conducted and gasoline is not dispensed do not require a separator, and areas of commercial garages used only for storage of automobiles need not drain through a separator.

Worked oil separator sizing

A repair garage drains 1,400 square feet of floor area through trench drains.

First 100 square feet: 6 cubic feet .

Remaining 1,300 square feet: 1,300 / 100 = 13 , at 1 cubic foot each = 13 cubic feet .

Total required capacity: 19 cubic feet.

Recall the companion rule from IPC 301.6: floor drains, sumps and sump pumps at the base of an elevator shaft must be indirectly connected and comply with Section 1003.4 — the oil separator section — because elevator pits collect hydraulic oil.

Other interceptors and separators

Application Requirement Section

Sand and heavy solids in commercial establishments Designed and located with ready access for cleaning ; water seal not less than 6 inches 1003.5

Clothes washer discharge Discharge through an interceptor with a wire basket or similar removable device preventing passage of solids 1/2 inch or larger , string, rags, buttons or similar material. Exceptions : clothes washers in individual dwelling units, and a single dwelling-unit-type washer installed outside a dwelling unit 1003.6

Bottling establishments Process wastes discharge into an interceptor separating broken glass or other solids 1003.7

Slaughterhouses Slaughtering and dressing room drains equipped with approved separators preventing discharge of feathers, entrails and other clogging materials 1003.8

Venting, access and materials

1003.9 Venting : interceptors and separators shall be designed so as not to become air bound and shall be vented in accordance with one of the methods in Chapter 9 . Recall the exception in IPC 905.4 : the 6-inch vertical rise requirement does not apply to vents for interceptors located outdoors .

1003.10 Access and maintenance : access shall be provided to each interceptor and separator , which shall be maintained by periodic removal of accumulated grease, scum, oil, other floating substances and deposited solids.

1004.1 Materials : materials and methods comply with Chapter 10 and the applicable provisions of Chapters 4 and 7 ; fittings shall not have ledges, shoulders or reductions capable of retarding or obstructing flow.

Colorado field note (not exam-scored): Board Rule 1.2(E)(1)(uu) adds an exception to IPC 1002.1 permitting trench and floor drains connected to a sand oil interceptor to go untrapped , provided the drain piping from the trench or floor drains is turned down after entering the interceptor so the discharge point is a minimum of 4 inches below the standing water level of the interceptor.

Loading diagram... Interceptor and separator selection