Study guide
12.5 Emergency Action Plans, Security Vulnerability, Spill Containment & CDPHE Tier 1/2/3 Public Notice
Colorado Water/Wastewater Operator Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: State Laws, Regulations & CCWP Certification
1.1 CDPHE CCWP Program & Regulatory Framework (Regulation 100 / 5 CCR 1003-2) 1.2 Facility Classification & Operator in Responsible Charge (ORC) Requirements 1.3 Certification Levels, Education, Experience & Exam Eligibility (Class D-A, Grade 1-4, Class S/T) 1.4 License Renewal, Training Units (TUs) & Mandatory Regulatory Training 1.5 Colorado Primary Drinking Water Regulations (Regulation 11) & Compliance 1.6 Colorado Discharge Permit System (Regulations 61/62), DMRs & Biosolids Reporting
2 Chapter 2: Source Water & Drinking Water Treatment Processes
2.1 Raw Water Sources, High-Altitude Characteristics & Reservoir Quality 2.2 Coagulation Chemistry, Rapid Mixing & Chemical Dosing (Alum, Ferric, Polymers) 2.3 Flocculation & Sedimentation Basin Design, Operation & Settling Zones 2.4 Granular Media Filtration, Backwash Procedures & Turbidity Standards 2.5 Advanced Treatment: Membranes, Softening, GAC/PAC Adsorption & Aeration 2.6 Groundwater Sources, Well Hydraulics, Static and Pumping Levels & Specific Capacity 2.7 Source Water Characteristics, Contaminant Categories & Watershed Protection Plans 2.8 Pretreatment: Presedimentation, Aeration, Algae Control & Taste-and-Odor Management 2.9 Direct, In-Line, Pressure, Cartridge & Diatomaceous Earth Filtration 2.10 Lime-Soda Softening, Ion Exchange & Water Stabilization 2.11 Water Treatment Plant Residuals: Lagoons, Drying Beds, Land Application & Recycle
3 Chapter 3: Disinfection & Chemical Addition
3.1 Chlorine Chemistry: Hypochlorous Acid, Free/Combined Residual & Breakpoint Chlorination 3.2 Disinfection Kinetics, Baffle Factors, T10 & CT Compliance Calculations 3.3 Disinfection Byproducts (TTHMs, HAA5s) & Stage 1/2 DBP Rules 3.4 Alternative Disinfection: Chloramination, Ultraviolet (UV) Light & Chlorine Dioxide 3.5 Corrosion Control, Lead & Copper Rule Revisions (LCRR) & Fluoridation Practices
4 Chapter 4: Water Treatment Plant Equipment, Instrumentation & Maintenance
4.1 Raw Water Intakes, Screening Equipment & Raw Water Pumping 4.2 Chemical Feed Equipment: Feeders, Day Tanks, Carrier Water & Feed-Rate Calibration 4.3 Chlorination Equipment: Gas Systems, Vacuum Regulators, Hypochlorite Storage & Onsite Generation 4.4 Filter Underdrains, Support Gravel, Surface Wash, Air Scour & Filter-to-Waste 4.5 Plant Process Control, SCADA and PLC Systems, Alarm Management & Records of Operation 4.6 Preventive, Corrective and Predictive Maintenance, Work Orders & Asset Management
5 Chapter 5: Wastewater Treatment Principles & Biological Processes
5.1 Preliminary Treatment: Bar Screens, Shredders, Grit Chambers & Flow Equalization 5.2 Primary Clarification, Solids Separation & Scum Removal Mechanics 5.3 Activated Sludge Fundamentals: Aerobic Microbiology, DO Control & Biomass Growth 5.4 Return & Waste Activated Sludge Management (RAS/WAS Operations & Sludge Age) 5.5 Activated Sludge Troubleshooting: Bulking, Nocardia Foaming, Rising Sludge & Pin Floc 5.6 Wastewater Characteristics, Organic and Hydraulic Loading, Diurnal Flow & Septicity 5.7 Activated Sludge Arrangements: Conventional, Complete Mix, Step Feed, Contact Stabilization, Extended Aeration, Oxidation Ditch, SBR & MBR 5.8 Aeration Systems: Blowers, Diffusers, Surface Aerators, Oxygen Transfer & Altitude Effects
6 Chapter 6: Advanced Wastewater Treatment & Solids Management
6.1 Biological Nutrient Removal: Nitrification, Denitrification & Anoxic Zones 6.2 Biological & Chemical Phosphorus Removal (EBPR & Coagulant Precipitation) 6.3 Sludge Thickening, Aerobic & Anaerobic Digestion (Mesophilic/Thermophilic) 6.4 Dewatering Equipment (Centrifuges, Belt Filter Presses) & Biosolids Standards (Reg 64) 6.5 Pond & Lagoon Operations, Trickling Filters & Rotating Biological Contactors (RBCs) 6.6 Secondary Clarification: Overflow and Solids Loading Rates, RAS Rate Setting & Clarifier Diagnostics 6.7 Tertiary Filtration, Effluent Polishing & Wastewater Disinfection with Chlorine, Dechlorination and UV 6.8 Effluent Disposal, Rapid Infiltration Basins, Colorado Water Reuse Law & Regulation 84
7 Chapter 7: Water Distribution Systems
7.1 Distribution Hydraulics, Pressure Zones, Static Head & Friction Headloss 7.2 Finished Water Storage Tanks, Standpipes, Mixing & Water Age Control 7.3 Distribution Piping, Valves (Gate, Butterfly, PRV), Hydrants & Main Flushing 7.4 Cross-Connection Control, Hazard Assessment & Backflow Preventers (RPZ, DCVA, PVB, Air Gap) 7.5 Water Main Installation, Trenching, Repair, Pressure Testing & Disinfection (AWWA C651) 7.6 Network Layout, Pressure Zones, Demand Patterns, Fire Flow & the Hydraulic Grade Line 7.7 Fire Hydrants, Dry Barrel Operation, Fire Flow Testing & Unidirectional Flushing 7.8 Booster Pump Stations, Hydropneumatic Systems, Controls & Surge Protection 7.9 Customer and Master Metering, Meter Sizing, Accuracy Testing, AMR & AMI 7.10 System Mapping, GIS, As-Builts, Operational Analysis & the AWWA Water Audit 7.11 Service Line Installation, Wet Tapping, Curb Stops & the Lead Service Line Inventory 7.12 Leak Detection, District Metered Areas, Minimum Night Flow & Pressure Management 7.13 Storage Facility Inspection, Sanitary Defects, Water Age Control, Cleaning & AWWA C652 Disinfection 7.14 Utility Locating, Colorado 811 Damage Prevention, the APWA Color Code & New Construction Inspection 7.15 Well and Wellhead Maintenance, Sanitary Condition, Rehabilitation & AWWA C654 Disinfection 7.16 Booster Chlorination, Remote Chemical Feed, Chemical Storage, Security & Supply Management 7.17 Distribution Sampling Technique, Chlorine Residual Monitoring & Nitrification Control in Chloraminated Systems
8 Chapter 8: Wastewater Collection Systems
8.1 Gravity Collection Systems: Flow Velocities, Slopes, Pipe Materials & Manholes 8.2 Wastewater Lift Stations: Wet Wells, Submersible Pumps, Level Controls & Force Mains 8.3 Inflow and Infiltration (I&I) Sources, Flow Monitoring, Smoke Testing & CCTV Inspection 8.4 Collection Maintenance: Hydraulic Jetting, Mechanical Rodding & FOG/Root Mitigation 8.5 Sanitary Sewer Overflows (SSOs): Root Causes, Containment, Reporting & Mitigation 8.6 Lift Station Electrical Devices, Level Detection, Telemetry, Gas Detection & Capacity Adjustment 8.7 Lift Station Configurations, Preventive Maintenance, Wet Well Cleaning, Troubleshooting & Emergency Bypass Pumping 8.8 Collection System Rehabilitation: CIPP, Pipe Bursting, Sliplining, Grouting, Manhole Repair & Tap Defects 8.9 Excavation, Hydro Excavation, Bedding and Haunching, Grade Control & Sewer Acceptance Testing 8.10 Collection System Flow Monitoring, Area-Velocity Metering, Weirs and Flumes & Capacity Assessment
9 Chapter 9: Pumps, Motors & Utility Mechanics
9.1 Centrifugal Pumps: Volutes, Impellers, Packing Seals & Mechanical Seals 9.2 Positive Displacement Pumps (Peristaltic, Diaphragm, Progressive Cavity) & Dosing Systems 9.3 Pump Performance Curves, System Head Curves, Cavitation & NPSH Calculations 9.4 Electric Motors (Single/Three Phase), Controls, Variable Frequency Drives (VFDs) & Power 9.5 Flow Meters (Venturi, Magnetic, Ultrasonic), Online Analyzers, PLCs & SCADA Telemetry 9.6 Air Compressors, Conveyors, Hoists and Cranes, Service Piping & Standby Power Generation 9.7 Valve Types and Duties, Air Release and Air-Vacuum Valves, Water Hammer & Surge Control
10 Chapter 10: Laboratory Analysis & Water Quality Monitoring
10.1 Regulatory Sampling Procedures, Chain of Custody, Holding Times & Preservation Techniques 10.2 Physical & Chemical Drinking Water Testing: Turbidity, pH, Alkalinity, Hardness & Chlorine (DPD) 10.3 Wastewater Laboratory Analysis: BOD5, COD, Total Suspended Solids (TSS) & Settleometry 10.4 Microbiological Testing: Total Coliform, E. coli (Colilert, Membrane Filtration) & QA/QC 10.5 Bench-Scale Jar Testing, Coagulant Optimization & Streaming Current Monitoring 10.6 Laboratory Equipment, Calibration and Verification, QA/QC Program & Certified Laboratory Requirements 10.7 Nutrient Series, Metals Sampling, Whole Effluent Toxicity & Electrode Measurements (DO, pH, ORP, H2S)
11 Chapter 11: Operator Mathematics & Applied Calculations
11.1 Core Conversions, Geometric Area, Pipe Volume & Continuous Flow Rate (MGD, GPM, cfs) 11.2 Chemical Dosage, The Standard "Pounds Formula", Active Chemical & Solution Purity 11.3 Hydraulic Retention Time (HRT), Surface Overflow Rate (SOR) & Weir Overflow Rates 11.4 Process Control Calculations: F/M Ratio, MCRT/Solids Retention Time (SRT) & Sludge Volume Index (SVI) 11.5 Distribution Pressure, Static vs Dynamic Head, Water Horsepower & Wire-to-Water Efficiency 11.6 CT Calculations: Baffling Factors, T10, Temperature and pH Corrections & Multi-Segment Compliance
12 Chapter 12: Safety, Emergency Operations & Compliance
12.1 Permit-Required Confined Space (PRCS) Entry, Atmospheric Testing (O2/LEL/H2S/CO) & Rescue 12.2 Control of Hazardous Energy: Lockout/Tagout (LOTO), Arc Flash & Electrical Safety 12.3 Chemical Safety: Chlorine Gas Handling, Ton Cylinders, Sulfur Dioxide, Ammonia & SDS/GHS 12.4 Trenching & Excavation: Soil Classification, Sloping, Shoring, Shielding & Competent Person Rules 12.5 Emergency Action Plans, Security Vulnerability, Spill Containment & CDPHE Tier 1/2/3 Public Notice 12.6 Work Zone Traffic Control, PPE, Fall Protection, Fire Extinguishers, First Aid & Bloodborne Pathogens 12.7 Standard Operating Procedures, Operating Records, Regulatory Reporting, Customer Complaints & Supervisory Duties
12.5 Emergency Action Plans, Security Vulnerability, Spill Containment & CDPHE Tier 1/2/3 Public Notice
Key Takeaways Explain This Topic AI
America's Water Infrastructure Act (AWIA) mandates Community Water Systems serving >3,300 persons to complete and certify Risk and Resilience Assessments (RRA) and Emergency Response Plans (ERP) every 5 years.
Under the Incident Command System (ICS/NIMS), optimal span of control is 1 supervisor to 5 subordinates (operating range 3 to 7).
Colorado CDPHE Regulation 11 Tier 1 Public Notice requires public broadcast and agency notification within 24 hours for acute threats: E. coli fecal contamination, nitrate/nitrite exceedances, waterborne outbreaks, and high turbidity.
Tier 2 Public Notice covers non-acute MCL and treatment technique violations requiring notification within 30 days; Tier 3 covers monitoring/reporting violations requiring notice within 12 months.
Uncontrolled wastewater spills and SSOs must be reported to the CDPHE 24-hour hotline within 24 hours, followed by a formal written noncompliance report within 5 days.
Last updated: August 2026
America's Water Infrastructure Act (AWIA) Compliance
Municipal water systems face complex operational threats ranging from extreme weather events to physical intrusion and sophisticated cyberattacks on Industrial Control Systems (ICS/SCADA). Section 2013 of America's Water Infrastructure Act (AWIA) of 2018 mandates that all Community Water Systems (CWS) serving more than 3,300 people develop or update two foundational security documents every 5 years:
Risk and Resilience Assessment (RRA): A comprehensive evaluation assessing the vulnerability of physical assets (raw water intakes, pump stations, treatment plants, distribution storage tanks, chemical feed systems) and cyber infrastructure (SCADA, automated telemetry, business networks). The RRA evaluates malevolent acts (vandalism, cyber intrusions, terrorism), natural disasters (wildfires, floods, earthquakes, severe blizzards), hazardous chemical releases, and supply chain vulnerabilities.
Emergency Response Plan (ERP): Actionable operational protocols, resource staging plans, and emergency standard operating procedures (SOPs) designed to maintain or rapidly restore critical water service during an emergency. The ERP integrates emergency power generation, cybersecurity incident mitigation, alternate water supply interconnections, and coordination protocols with Local Emergency Planning Committees (LEPC), first responders, and the Colorado Department of Public Health and Environment (CDPHE).
Incident Command System (ICS / NIMS) Structure
During large-scale utility emergencies (e.g., major transmission main ruptures, treatment plant inundation, widespread electrical blackouts), utilities manage operations using the National Incident Management System (NIMS) Incident Command System (ICS) . ICS provides a standardized, modular, scalable on-scene command architecture. +-------------------------------------------------------------------------+
- | INCIDENT COMMAND SYSTEM (ICS) |
- +-------------------------------------------------------------------------+
- | INCIDENT COMMANDER (IC) |
- | (Overall Incident Strategy, Tactical Goals, Life Safety) |
- | |
- | +--------------------+---------------------+--------------------+ |
- | | PUBLIC INFO (PIO) | SAFETY OFFICER | LIAISON OFFICER | |
- | | (Media & Public) | (Absolute Stop-Work)| (External Agencies)| |
- | +--------------------+---------------------+--------------------+ |
- | |
- | +---------------+---------------+---------------+ |
- | | | | | |
- | +-----------+ +-----------+ +-----------+ +-----------+ |
- | |OPERATIONS | | PLANNING | | LOGISTICS | | FINANCE/ | |
- | | Tactical | | Resources | | Material, | | ADMIN | |
- | | Field Ops | | Docs, IAP | | Comms, Eq | | Cost/Time | |
- | +-----------+ +-----------+ +-----------+ +-----------+ |
- +-------------------------------------------------------------------------+
- ICS Command & General Staff Roles
Incident Commander (IC): Holds ultimate tactical and legal authority over on-scene incident operations, life safety, resource prioritization, and approving the Incident Action Plan (IAP).
Command Staff:
Safety Officer: Assesses hazardous environments, monitors responder safety, and possesses absolute authority to immediately alter, suspend, or terminate any unsafe tactical operation .
Public Information Officer (PIO): Serves as the sole authorized voice for media releases, community public notifications, and press briefings.
Liaison Officer: Coordinates inter-agency communication between the utility, county emergency management, fire/police departments, CDPHE inspectors, and the EPA.
General Staff Sections:
Operations Section: Executes tactical field directives (e.g., isolating broken mains, operating bypass pumps, deploying repair clamps, performing emergency superchlorination).
Planning Section: Collects incident intelligence, tracks resource status, documents operational maps, and formulates the written IAP for upcoming operational periods.
Logistics Section: Procures equipment, tools, emergency diesel generators, fuel, replacement ductile iron pipe, contracted vacuum trucks, food, and communication hardware.
Finance / Administration Section: Tracks personnel overtime hours, vendor invoices, equipment rental expenses, worker compensation claims, and compiles documentation for FEMA disaster reimbursement.
Span of Control: Under NIMS guidelines, an effective supervisor-to-subordinate ratio must be maintained between 1:3 and 1:7 , with 1:5 considered optimal .
Drinking Water Contamination Emergencies & Tactical Actions
When microbial, chemical, or physical contamination enters the distribution system, operators must execute rapid tactical response measures: +-------------------------------------------------------------------------+
- | DISTRIBUTION CONTAMINATION TACTICAL ACTIONS |
- +-------------------------------------------------------------------------+
- | 1. PRESSURE LOSS (< 20 psi) : Isolate affected pressure zones; close |
- | boundary gate valves to prevent back-siphonage cross-contamination. |
- | 2. BOIL WATER ADVISORY (BWA): High-altitude Colorado standard requires |
- | a vigorous ROLLING BOIL for a minimum of 3 MINUTES (altitudes >5,000 ft)|
- | (EPA baseline is 1 minute at sea level). |
- | 3. DO NOT DRINK / DO NOT USE: Issued for volatile chemicals, petroleum, |
- | or toxic chemical spills where boiling could concentrate or vaporize |
- | toxic contaminants into indoor air. |
- | 4. EMERGENCY SUPERCHLORINATION (AWWA C651): Flush contaminated lines |
- | with 25 to 50 mg/L chlorine for 24 hours (or 200 mg/L for 3 hours). |
- | 5. DECHLORINATION PRIOR TO DISCHARGE: Treat chlorinated flush water |
- | with sodium bisulfite, sodium thiosulfate, or ascorbic acid to 0 mg/L|
- | residual before discharging to storm drains to prevent fish kills. |
- +-------------------------------------------------------------------------+
- Colorado CDPHE Regulation 11: Public Notification (PN) Rule
Under Colorado Regulation 11 (5 CCR 1002-11) and the federal Safe Drinking Water Act, public water systems must notify consumers whenever a regulatory violation or waterborne emergency occurs. Violations are classified into Three Distinct Regulatory Tiers based on the severity of public health risk: +-------------------------------------------------------------------------+
- | CDPHE REGULATION 11 PUBLIC NOTIFICATION TIERS |
- +-------------------------------------------------------------------------+
- | TIER 1: IMMEDIATE ACUTE HEALTH HAZARD |
- | Notification Required: WITHIN 24 HOURS |
- | Channels: Broadcast TV/Radio, Door-to-Door, Automated Calls, |
- | Social Media, CDPHE 24-hr Notification. |
- | |
- | TIER 2: NON-ACUTE CHEMICAL / TREATMENT TECHNIQUE EXCEEDANCES |
- | Notification Required: WITHIN 30 DAYS |
- | Channels: Direct Mail, Local Newspaper, Direct Delivery. |
- | |
- | TIER 3: OPERATIONAL, MONITORING & TESTING VIOLATIONS |
- | Notification Required: WITHIN 12 MONTHS |
- | Channels: Annual Consumer Confidence Report (CCR), Direct Mail. |
- +-------------------------------------------------------------------------+
- Tier-by-Tier Regulatory Breakdown
Tier Level Compliance Deadline Triggering Water Quality Violations & Conditions Mandatory Delivery Methods
Tier 1 (Acute Risk) Within 24 Hours - Fecal coliform or E. coli positive coliform repeat violation.; - Nitrate ( N O 3 > 10 mg/L NO_3 > 10\text{ mg/L} N O 3 > 10 mg/L ) or Nitrite ( N O 2 > 1.0 mg/L NO_2 > 1.0\text{ mg/L} N O 2 > 1.0 mg/L ) acute MCL exceedance.; - Chlorine dioxide MRDL exceedance at entry point with distribution booster exceedance.; - Exceedance of maximum allowable turbidity standard ( > 1.0 NTU >1.0\text{ NTU} > 1.0 NTU / > 5.0 NTU >5.0\text{ NTU} > 5.0 NTU ) with direct pathogen risk.; - Confirmed waterborne disease outbreak. Broadcast radio and television, door-to-door hand delivery, automated emergency phone reverse-911, website posting. Must consult with CDPHE within 24 hours.
Tier 2 (Non-Acute Risk) Within 30 Days - Total Trihalomethanes (TTHM > 0.080 mg/L > 0.080\text{ mg/L} > 0.080 mg/L ) or Haloacetic Acids (HAA5 > 0.060 mg/L > 0.060\text{ mg/L} > 0.060 mg/L ) running annual average exceedance.; - Inorganic/radiological chemical MCL exceedances (Arsenic, Lead/Copper treatment technique failure).; - Secondary disinfectant residual at entry point ( < 0.2 mg/L <0.2\text{ mg/L} < 0.2 mg/L ) not restored within 4 hours. Direct mail billing insert, published notice in local newspaper of general circulation, direct hand delivery. Repeat notices required quarterly.
Tier 3 (Monitoring Risk) Within 12 Months - Failure to collect required monthly bacteriological distribution samples.; - Failure to perform required chemical monitoring on schedule.; - Late submission of Monthly Operating Reports (MORs).; - Operation under an approved state variance or exemption. Published within the annual Consumer Confidence Report (CCR) delivered to all customers by July 1, or direct billing insert.
Wastewater Spill Containment & 24-Hour Reporting Protocol
Domestic wastewater collection and treatment facilities are subject to strict spill reporting under Colorado discharge permits (CDPS) and Water Quality Control Division guidelines:
Immediate Containment & Mitigation: Deploy spill containment booms, construct earth/sandbag berms, block downstream storm sewer inlets, engage vacuum pumper trucks, and initiate bypass pumping around sewer collapses to prevent raw sewage from entering surface waters.
Environmental Water Quality Sampling: Collect immediate representative samples from three critical locations:
- Point A: Upstream of the discharge point (unaffected baseline);
- Point B: The direct point of discharge / outfall;
Point C: Downstream of the discharge point (to evaluate the mixing zone and downstream environmental impact).
Test samples for E. coli density, Biochemical Oxygen Demand ( B O D 5 BOD_5 BO D 5 ), Total Suspended Solids ( T S S TSS TSS ), and Ammonia ( N H 3 NH_3 N H 3 ).
Mandatory CDPHE 24-Hour Hotline Notification: Facility management or the Operator in Responsible Charge (ORC) must verbally notify the CDPHE 24-Hour Environmental Emergency Hotline (1-877-518-5608) within 24 hours of discovering the spill or sanitary sewer overflow (SSO).
Written 5-Day Noncompliance Report: A comprehensive written spill report must be submitted to the CDPHE Water Quality Control Division within 5 calendar days . The report must detail the root cause, estimated total gallons released, volume recovered, receiving water body affected, sampling lab results, cleanup measures, and long-term preventative corrective actions taken.