12.4 Trenching & Excavation: Soil Classification, Sloping, Shoring, Shielding & Competent Person Rules
Colorado Water/Wastewater Operator Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: State Laws, Regulations & CCWP Certification
1.1 CDPHE CCWP Program & Regulatory Framework (Regulation 100 / 5 CCR 1003-2) 1.2 Facility Classification & Operator in Responsible Charge (ORC) Requirements 1.3 Certification Levels, Education, Experience & Exam Eligibility (Class D-A, Grade 1-4, Class S/T) 1.4 License Renewal, Training Units (TUs) & Mandatory Regulatory Training 1.5 Colorado Primary Drinking Water Regulations (Regulation 11) & Compliance 1.6 Colorado Discharge Permit System (Regulations 61/62), DMRs & Biosolids Reporting
2 Chapter 2: Source Water & Drinking Water Treatment Processes
2.1 Raw Water Sources, High-Altitude Characteristics & Reservoir Quality 2.2 Coagulation Chemistry, Rapid Mixing & Chemical Dosing (Alum, Ferric, Polymers) 2.3 Flocculation & Sedimentation Basin Design, Operation & Settling Zones 2.4 Granular Media Filtration, Backwash Procedures & Turbidity Standards 2.5 Advanced Treatment: Membranes, Softening, GAC/PAC Adsorption & Aeration 2.6 Groundwater Sources, Well Hydraulics, Static and Pumping Levels & Specific Capacity 2.7 Source Water Characteristics, Contaminant Categories & Watershed Protection Plans 2.8 Pretreatment: Presedimentation, Aeration, Algae Control & Taste-and-Odor Management 2.9 Direct, In-Line, Pressure, Cartridge & Diatomaceous Earth Filtration 2.10 Lime-Soda Softening, Ion Exchange & Water Stabilization 2.11 Water Treatment Plant Residuals: Lagoons, Drying Beds, Land Application & Recycle
3 Chapter 3: Disinfection & Chemical Addition
3.1 Chlorine Chemistry: Hypochlorous Acid, Free/Combined Residual & Breakpoint Chlorination 3.2 Disinfection Kinetics, Baffle Factors, T10 & CT Compliance Calculations 3.3 Disinfection Byproducts (TTHMs, HAA5s) & Stage 1/2 DBP Rules 3.4 Alternative Disinfection: Chloramination, Ultraviolet (UV) Light & Chlorine Dioxide 3.5 Corrosion Control, Lead & Copper Rule Revisions (LCRR) & Fluoridation Practices
4 Chapter 4: Water Treatment Plant Equipment, Instrumentation & Maintenance
4.1 Raw Water Intakes, Screening Equipment & Raw Water Pumping 4.2 Chemical Feed Equipment: Feeders, Day Tanks, Carrier Water & Feed-Rate Calibration 4.3 Chlorination Equipment: Gas Systems, Vacuum Regulators, Hypochlorite Storage & Onsite Generation 4.4 Filter Underdrains, Support Gravel, Surface Wash, Air Scour & Filter-to-Waste 4.5 Plant Process Control, SCADA and PLC Systems, Alarm Management & Records of Operation 4.6 Preventive, Corrective and Predictive Maintenance, Work Orders & Asset Management
5 Chapter 5: Wastewater Treatment Principles & Biological Processes
5.1 Preliminary Treatment: Bar Screens, Shredders, Grit Chambers & Flow Equalization 5.2 Primary Clarification, Solids Separation & Scum Removal Mechanics 5.3 Activated Sludge Fundamentals: Aerobic Microbiology, DO Control & Biomass Growth 5.4 Return & Waste Activated Sludge Management (RAS/WAS Operations & Sludge Age) 5.5 Activated Sludge Troubleshooting: Bulking, Nocardia Foaming, Rising Sludge & Pin Floc 5.6 Wastewater Characteristics, Organic and Hydraulic Loading, Diurnal Flow & Septicity 5.7 Activated Sludge Arrangements: Conventional, Complete Mix, Step Feed, Contact Stabilization, Extended Aeration, Oxidation Ditch, SBR & MBR 5.8 Aeration Systems: Blowers, Diffusers, Surface Aerators, Oxygen Transfer & Altitude Effects
6 Chapter 6: Advanced Wastewater Treatment & Solids Management
6.1 Biological Nutrient Removal: Nitrification, Denitrification & Anoxic Zones 6.2 Biological & Chemical Phosphorus Removal (EBPR & Coagulant Precipitation) 6.3 Sludge Thickening, Aerobic & Anaerobic Digestion (Mesophilic/Thermophilic) 6.4 Dewatering Equipment (Centrifuges, Belt Filter Presses) & Biosolids Standards (Reg 64) 6.5 Pond & Lagoon Operations, Trickling Filters & Rotating Biological Contactors (RBCs) 6.6 Secondary Clarification: Overflow and Solids Loading Rates, RAS Rate Setting & Clarifier Diagnostics 6.7 Tertiary Filtration, Effluent Polishing & Wastewater Disinfection with Chlorine, Dechlorination and UV 6.8 Effluent Disposal, Rapid Infiltration Basins, Colorado Water Reuse Law & Regulation 84
7 Chapter 7: Water Distribution Systems
7.1 Distribution Hydraulics, Pressure Zones, Static Head & Friction Headloss 7.2 Finished Water Storage Tanks, Standpipes, Mixing & Water Age Control 7.3 Distribution Piping, Valves (Gate, Butterfly, PRV), Hydrants & Main Flushing 7.4 Cross-Connection Control, Hazard Assessment & Backflow Preventers (RPZ, DCVA, PVB, Air Gap) 7.5 Water Main Installation, Trenching, Repair, Pressure Testing & Disinfection (AWWA C651) 7.6 Network Layout, Pressure Zones, Demand Patterns, Fire Flow & the Hydraulic Grade Line 7.7 Fire Hydrants, Dry Barrel Operation, Fire Flow Testing & Unidirectional Flushing 7.8 Booster Pump Stations, Hydropneumatic Systems, Controls & Surge Protection 7.9 Customer and Master Metering, Meter Sizing, Accuracy Testing, AMR & AMI 7.10 System Mapping, GIS, As-Builts, Operational Analysis & the AWWA Water Audit 7.11 Service Line Installation, Wet Tapping, Curb Stops & the Lead Service Line Inventory 7.12 Leak Detection, District Metered Areas, Minimum Night Flow & Pressure Management 7.13 Storage Facility Inspection, Sanitary Defects, Water Age Control, Cleaning & AWWA C652 Disinfection 7.14 Utility Locating, Colorado 811 Damage Prevention, the APWA Color Code & New Construction Inspection 7.15 Well and Wellhead Maintenance, Sanitary Condition, Rehabilitation & AWWA C654 Disinfection 7.16 Booster Chlorination, Remote Chemical Feed, Chemical Storage, Security & Supply Management 7.17 Distribution Sampling Technique, Chlorine Residual Monitoring & Nitrification Control in Chloraminated Systems
8 Chapter 8: Wastewater Collection Systems
8.1 Gravity Collection Systems: Flow Velocities, Slopes, Pipe Materials & Manholes 8.2 Wastewater Lift Stations: Wet Wells, Submersible Pumps, Level Controls & Force Mains 8.3 Inflow and Infiltration (I&I) Sources, Flow Monitoring, Smoke Testing & CCTV Inspection 8.4 Collection Maintenance: Hydraulic Jetting, Mechanical Rodding & FOG/Root Mitigation 8.5 Sanitary Sewer Overflows (SSOs): Root Causes, Containment, Reporting & Mitigation 8.6 Lift Station Electrical Devices, Level Detection, Telemetry, Gas Detection & Capacity Adjustment 8.7 Lift Station Configurations, Preventive Maintenance, Wet Well Cleaning, Troubleshooting & Emergency Bypass Pumping 8.8 Collection System Rehabilitation: CIPP, Pipe Bursting, Sliplining, Grouting, Manhole Repair & Tap Defects 8.9 Excavation, Hydro Excavation, Bedding and Haunching, Grade Control & Sewer Acceptance Testing 8.10 Collection System Flow Monitoring, Area-Velocity Metering, Weirs and Flumes & Capacity Assessment
9 Chapter 9: Pumps, Motors & Utility Mechanics
9.1 Centrifugal Pumps: Volutes, Impellers, Packing Seals & Mechanical Seals 9.2 Positive Displacement Pumps (Peristaltic, Diaphragm, Progressive Cavity) & Dosing Systems 9.3 Pump Performance Curves, System Head Curves, Cavitation & NPSH Calculations 9.4 Electric Motors (Single/Three Phase), Controls, Variable Frequency Drives (VFDs) & Power 9.5 Flow Meters (Venturi, Magnetic, Ultrasonic), Online Analyzers, PLCs & SCADA Telemetry 9.6 Air Compressors, Conveyors, Hoists and Cranes, Service Piping & Standby Power Generation 9.7 Valve Types and Duties, Air Release and Air-Vacuum Valves, Water Hammer & Surge Control
10 Chapter 10: Laboratory Analysis & Water Quality Monitoring
10.1 Regulatory Sampling Procedures, Chain of Custody, Holding Times & Preservation Techniques 10.2 Physical & Chemical Drinking Water Testing: Turbidity, pH, Alkalinity, Hardness & Chlorine (DPD) 10.3 Wastewater Laboratory Analysis: BOD5, COD, Total Suspended Solids (TSS) & Settleometry 10.4 Microbiological Testing: Total Coliform, E. coli (Colilert, Membrane Filtration) & QA/QC 10.5 Bench-Scale Jar Testing, Coagulant Optimization & Streaming Current Monitoring 10.6 Laboratory Equipment, Calibration and Verification, QA/QC Program & Certified Laboratory Requirements 10.7 Nutrient Series, Metals Sampling, Whole Effluent Toxicity & Electrode Measurements (DO, pH, ORP, H2S)
11 Chapter 11: Operator Mathematics & Applied Calculations
11.1 Core Conversions, Geometric Area, Pipe Volume & Continuous Flow Rate (MGD, GPM, cfs) 11.2 Chemical Dosage, The Standard "Pounds Formula", Active Chemical & Solution Purity 11.3 Hydraulic Retention Time (HRT), Surface Overflow Rate (SOR) & Weir Overflow Rates 11.4 Process Control Calculations: F/M Ratio, MCRT/Solids Retention Time (SRT) & Sludge Volume Index (SVI) 11.5 Distribution Pressure, Static vs Dynamic Head, Water Horsepower & Wire-to-Water Efficiency 11.6 CT Calculations: Baffling Factors, T10, Temperature and pH Corrections & Multi-Segment Compliance
12 Chapter 12: Safety, Emergency Operations & Compliance
12.1 Permit-Required Confined Space (PRCS) Entry, Atmospheric Testing (O2/LEL/H2S/CO) & Rescue 12.2 Control of Hazardous Energy: Lockout/Tagout (LOTO), Arc Flash & Electrical Safety 12.3 Chemical Safety: Chlorine Gas Handling, Ton Cylinders, Sulfur Dioxide, Ammonia & SDS/GHS 12.4 Trenching & Excavation: Soil Classification, Sloping, Shoring, Shielding & Competent Person Rules 12.5 Emergency Action Plans, Security Vulnerability, Spill Containment & CDPHE Tier 1/2/3 Public Notice 12.6 Work Zone Traffic Control, PPE, Fall Protection, Fire Extinguishers, First Aid & Bloodborne Pathogens 12.7 Standard Operating Procedures, Operating Records, Regulatory Reporting, Customer Complaints & Supervisory Duties
12.4 Trenching & Excavation: Soil Classification, Sloping, Shoring, Shielding & Competent Person Rules
Key Takeaways Explain This Topic AI
Under OSHA 29 CFR 1926 Subpart P, all excavations 5 feet or deeper require an approved protective system (sloping, benching, shoring, or shielding).
A designated Competent Person must possess specialized training in soil mechanics, identify existing/predictable hazards, perform daily inspections, and hold absolute Stop-Work authority.
Soil is classified into Type A (>= 1.5 tsf), Type B (0.5 to 1.5 tsf), and Type C (< 0.5 tsf, submerged, or previously disturbed); benching is strictly prohibited in Type C soils.
Maximum allowable sloping angles are: Type A = 3/4:1 (53°), Type B = 1:1 (45°), and Type C = 1.5:1 (34°).
Excavations 4 feet or deeper require a stairway, ladder, or ramp with maximum lateral travel distance not exceeding 25 feet, with ladders extending 3 feet above the trench lip; spoils must be set back at least 2 feet.
Last updated: August 2026
OSHA Trenching & Excavation Standard (29 CFR 1926 Subpart P)
Utility distribution main breaks, sewer lateral repairs, and valve replacements require municipal operators to perform extensive trenching and excavation work. Trench collapses represent one of the most fatal hazards in construction and utility maintenance. A single cubic yard of soil weighs between 2,700 and 3,000 pounds (1.35 to 1.5 tons) —equivalent to the weight of a midsize automobile. Entrapment under even two feet of soil exerts crushing forces that cause rapid traumatic asphyxiation within minutes.
Fundamental OSHA Definitions
Excavation: Any man-made cut, cavity, trench, or depression in an earth surface formed by earth removal.
Trench: A narrow excavation (in relation to its length) made below the surface of the ground. In general, the depth is greater than the width, but the width at the bottom is not greater than 15 feet (4.6 m) .
The Competent Person: Authority & Mandatory Duties
Under OSHA standards, every excavation jobsite must have an employer-designated Competent Person on-site. OSHA defines a competent person as "one who is capable of identifying existing and predictable hazards in the surroundings, or working conditions which are unsanitary, hazardous, or dangerous to employees, and who has authorization to take prompt corrective measures to eliminate them." +-------------------------------------------------------------------------+
- | COMPETENT PERSON MANDATORY RESPONSIBILITIES |
- | (29 CFR 1926 Subpart P) |
- +-------------------------------------------------------------------------+
- | 1. Perform visual and manual soil classification tests on-site. |
- | 2. Select, evaluate, and inspect protective systems (slopes/shields). |
- | 3. Conduct daily inspections before the start of every work shift. |
- | 4. Re-inspect after every rainstorm, freeze/thaw cycle, vibration event, |
- | seismic event, or any occurrence that increases cave-in risk. |
- | 5. Exercise absolute STOP-WORK AUTHORITY to immediately remove workers |
- | from any excavation exhibiting indications of instability. |
- | 6. Ensure proper ladder access, spoils setbacks, and atmospheric testing|
- | in trenches deeper than 4 feet near landfills or chemical lines. |
- +-------------------------------------------------------------------------+
- OSHA Soil Classification System
Soil stability is categorized into three primary soil types (Types A, B, and C) based on cohesive properties and Unconfined Compressive Strength (UCS) measured in tons per square foot (tsf) or kilograms per square centimeter ( k g / c m 2 kg/cm^2 k g / c m 2 ): +-------------------------------------------------------------------------+
- | OSHA SOIL CLASSIFICATION HIERARCHY |
- +-------------------------------------------------------------------------+
- | SOLID ROCK : Intact natural solid rock formation; vertical walls stable.|
- | |
- | TYPE A : Cohesive soil with UCS >= 1.5 tsf (144 kPa). |
- | (Clay, silty clay, sandy clay, clay loam). |
- | CANNOT be Type A if fissured, subject to heavy vibration, |
- | previously disturbed, or if water is seeping. |
- | |
- | TYPE B : Cohesive soil with UCS > 0.5 tsf but < 1.5 tsf. |
- | (Silt, angular gravel, loam, fissured Type A soils, |
- | soil subject to heavy traffic vibration). |
- | |
- | TYPE C : Cohesive soil with UCS <= 0.5 tsf (48 kPa). |
- | (Granular sand, loamy sand, gravel, submerged soil, |
- | soil with weeping water). ALL submerged soils are Type C. |
- +-------------------------------------------------------------------------+
- Disqualification Rules for Type A Soil
Even if a cohesive clay exhibits an unconfined compressive strength ≥ 1.5 tsf \ge 1.5\text{ tsf} ≥ 1.5 tsf , the competent person MUST downgrade the soil to Type B or Type C if any of the following conditions exist:
The soil is fissured or contains internal cleavage planes;
The soil is subject to mechanical vibration from heavy vehicular traffic, pile driving, railroads, or heavy equipment;
The soil has been previously excavated or disturbed (e.g., utility trenches backfilled with native soils—a standard condition throughout urban streets);
The soil is part of a layered system that slopes into the excavation at a slope of 4:1 (horizontal to vertical) or steeper; or
Free water is seeping or weeping from the trench walls.
Field Soil Testing Methods
The Competent Person must perform at least one visual test (observing particle size, soil layering, weeping water, fissures) and at least one manual test :
Pocket Penetrometer: Calibrated spring-loaded piston pressed into a fresh soil chunk to directly read unconfined compressive strength in tsf.
Thumb Penetration Test: Type A soil can be indented by the thumb only with very great effort; Type B soil can be indented with moderate effort up to the thumbnail; Type C soil is easily penetrated several inches by the thumb.
Plasticity / Ribbon Test: Rolling moist soil between palms into a long, thin thread ( 1 / 8 inch 1/8\text{ inch} 1/8 inch diameter). Highly cohesive clay (Type A) forms a 2- to 3-inch intact ribbon without breaking; cohesionless granular sand (Type C) will not roll into a ribbon.
Protective Systems: Sloping, Benching, Shoring & Shielding
Under OSHA regulations, an approved protective system is mandatory for any excavation 5 feet (1.52 m) or deeper , or in any excavation shallower than 5 feet if the competent person detects signs of potential wall failure or sloughing. +-------------------------------------------------------------------------+
- | MAXIMUM ALLOWABLE SLOPING & BENCHING SPECIFICATIONS |
- +-------------------------------------------------------------------------+
- | Soil Type | Max Slope Angle (H:V) | Angle from Horizontal | Benching? |
- +------------+-----------------------+-----------------------+------------+
- | Solid Rock | Vertical (90°) | 90° | Allowed |
- | Type A | 3/4 : 1 | 53° | Allowed |
- | Type B | 1 : 1 | 45° | Allowed |
- | Type C | 1.5 : 1 | 34° | PROHIBITED |
+-------------------------------------------------------------------------+ Sloping Geometry Examples:
Type A (3/4 : 1 / 53°): Type B (1 : 1 / 45°): Type C (1.5 : 1 / 34°):
- 3/4 H 1 H 1.5 H
- +--------+ +----------+ +--------------+
- | / | / | /
- 1 V| / 1 V| / 1 V| /
- | / | / | /
- +----+ +------+ +----------+
- Shoring vs. Shielding Systems
Hydraulic Aluminum Shoring: An active protective system utilizing hydraulic cylinders (wales and struts) pressurized to 750 – 1 , 500 psi 750\text{--}1,500\text{ psi} 750 – 1 , 500 psi against vertical aluminum rails. Shoring applies continuous active lateral force against trench walls to prevent initial soil movement.
Shielding Systems (Trench Boxes): A passive protective system designed to withstand and deflect the catastrophic forces of a cave-in, protecting workers inside the steel/aluminum shield chamber.
Top Clearance Rule: Trench boxes must extend at least 18 inches (0.46 m) above the surrounding ground level (or above the toe of any sloped bench above the box) to prevent rolling rocks and debris from falling into the trench.
Bottom Clearance Rule: Excavation below the bottom of the trench box cannot exceed a maximum of 2 feet (0.61 m) , and is only permitted if the soil shows no indications of lateral heaving or base boiling.
Workers must remain inside the shield at all times; climbing onto the top of the shield or working outside its lateral protection is strictly prohibited.
Egress, Spoil Placement & Colorado 811 Rules +-------------------------------------------------------------------------+
- | EXCAVATION ACCESS, EGRESS & SPOIL RULES |
- +-------------------------------------------------------------------------+
- | EGRESS MANDATE : Required in all trenches >= 4 FEET (1.22 m) deep. |
- | LATERAL TRAVEL : Maximum 25 FEET (7.62 m) of lateral travel distance |
- | to an egress ladder, ramp, or stairway. |
- | LADDER EXTENSION : Ladders must extend at least 3 FEET (0.91 m / 36 in)|
- | above the top of the trench landing and be tied off.|
- | SPOILS SETBACK : Excavated spoils, tools, and heavy equipment must |
- | be set back at least 2 FEET (0.61 m / 24 inches) |
- | from the edge of the excavation lip. |
- +-------------------------------------------------------------------------+
- Colorado 811 (UNCC / "Call Before You Dig")
Under Colorado law (C.R.S. Title 9, Article 1.5), excavators must contact Colorado 811 (Utility Notification Center of Colorado - UNCC) at least 2 full business days (not including weekends/holidays) prior to any excavation. Utilities mark underground infrastructure following the American Public Works Association (APWA) uniform color code:
- APWA Utility Color Code Utility Infrastructure Type
- Safety Precaution Blue Potable Drinking Water Systems
- Safety Green Sanitary Sewers, Storm Drains, and Wastewater Collection Piping
- High Visibility Safety Yellow Natural Gas, Oil, Steam, Petroleum, and Gaseous Energy Lines
- Safety Precaution Red Electric Power Lines, Cables, Conduit, and Lighting Cables
- Safety Alert Orange Telecommunications, Fiber Optics, Cable TV, and Signal Wires
- Purple Reclaimed Water, Irrigation, and Slurry Lines
- White Proposed Excavation Boundaries and Work Limits