4.2 Chemical Feed Equipment: Feeders, Day Tanks, Carrier Water & Feed-Rate Calibration
Colorado Water/Wastewater Operator Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: State Laws, Regulations & CCWP Certification
1.1 CDPHE CCWP Program & Regulatory Framework (Regulation 100 / 5 CCR 1003-2) 1.2 Facility Classification & Operator in Responsible Charge (ORC) Requirements 1.3 Certification Levels, Education, Experience & Exam Eligibility (Class D-A, Grade 1-4, Class S/T) 1.4 License Renewal, Training Units (TUs) & Mandatory Regulatory Training 1.5 Colorado Primary Drinking Water Regulations (Regulation 11) & Compliance 1.6 Colorado Discharge Permit System (Regulations 61/62), DMRs & Biosolids Reporting
2 Chapter 2: Source Water & Drinking Water Treatment Processes
2.1 Raw Water Sources, High-Altitude Characteristics & Reservoir Quality 2.2 Coagulation Chemistry, Rapid Mixing & Chemical Dosing (Alum, Ferric, Polymers) 2.3 Flocculation & Sedimentation Basin Design, Operation & Settling Zones 2.4 Granular Media Filtration, Backwash Procedures & Turbidity Standards 2.5 Advanced Treatment: Membranes, Softening, GAC/PAC Adsorption & Aeration 2.6 Groundwater Sources, Well Hydraulics, Static and Pumping Levels & Specific Capacity 2.7 Source Water Characteristics, Contaminant Categories & Watershed Protection Plans 2.8 Pretreatment: Presedimentation, Aeration, Algae Control & Taste-and-Odor Management 2.9 Direct, In-Line, Pressure, Cartridge & Diatomaceous Earth Filtration 2.10 Lime-Soda Softening, Ion Exchange & Water Stabilization 2.11 Water Treatment Plant Residuals: Lagoons, Drying Beds, Land Application & Recycle
3 Chapter 3: Disinfection & Chemical Addition
3.1 Chlorine Chemistry: Hypochlorous Acid, Free/Combined Residual & Breakpoint Chlorination 3.2 Disinfection Kinetics, Baffle Factors, T10 & CT Compliance Calculations 3.3 Disinfection Byproducts (TTHMs, HAA5s) & Stage 1/2 DBP Rules 3.4 Alternative Disinfection: Chloramination, Ultraviolet (UV) Light & Chlorine Dioxide 3.5 Corrosion Control, Lead & Copper Rule Revisions (LCRR) & Fluoridation Practices
4 Chapter 4: Water Treatment Plant Equipment, Instrumentation & Maintenance
4.1 Raw Water Intakes, Screening Equipment & Raw Water Pumping 4.2 Chemical Feed Equipment: Feeders, Day Tanks, Carrier Water & Feed-Rate Calibration 4.3 Chlorination Equipment: Gas Systems, Vacuum Regulators, Hypochlorite Storage & Onsite Generation 4.4 Filter Underdrains, Support Gravel, Surface Wash, Air Scour & Filter-to-Waste 4.5 Plant Process Control, SCADA and PLC Systems, Alarm Management & Records of Operation 4.6 Preventive, Corrective and Predictive Maintenance, Work Orders & Asset Management
5 Chapter 5: Wastewater Treatment Principles & Biological Processes
5.1 Preliminary Treatment: Bar Screens, Shredders, Grit Chambers & Flow Equalization 5.2 Primary Clarification, Solids Separation & Scum Removal Mechanics 5.3 Activated Sludge Fundamentals: Aerobic Microbiology, DO Control & Biomass Growth 5.4 Return & Waste Activated Sludge Management (RAS/WAS Operations & Sludge Age) 5.5 Activated Sludge Troubleshooting: Bulking, Nocardia Foaming, Rising Sludge & Pin Floc 5.6 Wastewater Characteristics, Organic and Hydraulic Loading, Diurnal Flow & Septicity 5.7 Activated Sludge Arrangements: Conventional, Complete Mix, Step Feed, Contact Stabilization, Extended Aeration, Oxidation Ditch, SBR & MBR 5.8 Aeration Systems: Blowers, Diffusers, Surface Aerators, Oxygen Transfer & Altitude Effects
6 Chapter 6: Advanced Wastewater Treatment & Solids Management
6.1 Biological Nutrient Removal: Nitrification, Denitrification & Anoxic Zones 6.2 Biological & Chemical Phosphorus Removal (EBPR & Coagulant Precipitation) 6.3 Sludge Thickening, Aerobic & Anaerobic Digestion (Mesophilic/Thermophilic) 6.4 Dewatering Equipment (Centrifuges, Belt Filter Presses) & Biosolids Standards (Reg 64) 6.5 Pond & Lagoon Operations, Trickling Filters & Rotating Biological Contactors (RBCs) 6.6 Secondary Clarification: Overflow and Solids Loading Rates, RAS Rate Setting & Clarifier Diagnostics 6.7 Tertiary Filtration, Effluent Polishing & Wastewater Disinfection with Chlorine, Dechlorination and UV 6.8 Effluent Disposal, Rapid Infiltration Basins, Colorado Water Reuse Law & Regulation 84
7 Chapter 7: Water Distribution Systems
7.1 Distribution Hydraulics, Pressure Zones, Static Head & Friction Headloss 7.2 Finished Water Storage Tanks, Standpipes, Mixing & Water Age Control 7.3 Distribution Piping, Valves (Gate, Butterfly, PRV), Hydrants & Main Flushing 7.4 Cross-Connection Control, Hazard Assessment & Backflow Preventers (RPZ, DCVA, PVB, Air Gap) 7.5 Water Main Installation, Trenching, Repair, Pressure Testing & Disinfection (AWWA C651) 7.6 Network Layout, Pressure Zones, Demand Patterns, Fire Flow & the Hydraulic Grade Line 7.7 Fire Hydrants, Dry Barrel Operation, Fire Flow Testing & Unidirectional Flushing 7.8 Booster Pump Stations, Hydropneumatic Systems, Controls & Surge Protection 7.9 Customer and Master Metering, Meter Sizing, Accuracy Testing, AMR & AMI 7.10 System Mapping, GIS, As-Builts, Operational Analysis & the AWWA Water Audit 7.11 Service Line Installation, Wet Tapping, Curb Stops & the Lead Service Line Inventory 7.12 Leak Detection, District Metered Areas, Minimum Night Flow & Pressure Management 7.13 Storage Facility Inspection, Sanitary Defects, Water Age Control, Cleaning & AWWA C652 Disinfection 7.14 Utility Locating, Colorado 811 Damage Prevention, the APWA Color Code & New Construction Inspection 7.15 Well and Wellhead Maintenance, Sanitary Condition, Rehabilitation & AWWA C654 Disinfection 7.16 Booster Chlorination, Remote Chemical Feed, Chemical Storage, Security & Supply Management 7.17 Distribution Sampling Technique, Chlorine Residual Monitoring & Nitrification Control in Chloraminated Systems
8 Chapter 8: Wastewater Collection Systems
8.1 Gravity Collection Systems: Flow Velocities, Slopes, Pipe Materials & Manholes 8.2 Wastewater Lift Stations: Wet Wells, Submersible Pumps, Level Controls & Force Mains 8.3 Inflow and Infiltration (I&I) Sources, Flow Monitoring, Smoke Testing & CCTV Inspection 8.4 Collection Maintenance: Hydraulic Jetting, Mechanical Rodding & FOG/Root Mitigation 8.5 Sanitary Sewer Overflows (SSOs): Root Causes, Containment, Reporting & Mitigation 8.6 Lift Station Electrical Devices, Level Detection, Telemetry, Gas Detection & Capacity Adjustment 8.7 Lift Station Configurations, Preventive Maintenance, Wet Well Cleaning, Troubleshooting & Emergency Bypass Pumping 8.8 Collection System Rehabilitation: CIPP, Pipe Bursting, Sliplining, Grouting, Manhole Repair & Tap Defects 8.9 Excavation, Hydro Excavation, Bedding and Haunching, Grade Control & Sewer Acceptance Testing 8.10 Collection System Flow Monitoring, Area-Velocity Metering, Weirs and Flumes & Capacity Assessment
9 Chapter 9: Pumps, Motors & Utility Mechanics
9.1 Centrifugal Pumps: Volutes, Impellers, Packing Seals & Mechanical Seals 9.2 Positive Displacement Pumps (Peristaltic, Diaphragm, Progressive Cavity) & Dosing Systems 9.3 Pump Performance Curves, System Head Curves, Cavitation & NPSH Calculations 9.4 Electric Motors (Single/Three Phase), Controls, Variable Frequency Drives (VFDs) & Power 9.5 Flow Meters (Venturi, Magnetic, Ultrasonic), Online Analyzers, PLCs & SCADA Telemetry 9.6 Air Compressors, Conveyors, Hoists and Cranes, Service Piping & Standby Power Generation 9.7 Valve Types and Duties, Air Release and Air-Vacuum Valves, Water Hammer & Surge Control
10 Chapter 10: Laboratory Analysis & Water Quality Monitoring
10.1 Regulatory Sampling Procedures, Chain of Custody, Holding Times & Preservation Techniques 10.2 Physical & Chemical Drinking Water Testing: Turbidity, pH, Alkalinity, Hardness & Chlorine (DPD) 10.3 Wastewater Laboratory Analysis: BOD5, COD, Total Suspended Solids (TSS) & Settleometry 10.4 Microbiological Testing: Total Coliform, E. coli (Colilert, Membrane Filtration) & QA/QC 10.5 Bench-Scale Jar Testing, Coagulant Optimization & Streaming Current Monitoring 10.6 Laboratory Equipment, Calibration and Verification, QA/QC Program & Certified Laboratory Requirements 10.7 Nutrient Series, Metals Sampling, Whole Effluent Toxicity & Electrode Measurements (DO, pH, ORP, H2S)
11 Chapter 11: Operator Mathematics & Applied Calculations
11.1 Core Conversions, Geometric Area, Pipe Volume & Continuous Flow Rate (MGD, GPM, cfs) 11.2 Chemical Dosage, The Standard "Pounds Formula", Active Chemical & Solution Purity 11.3 Hydraulic Retention Time (HRT), Surface Overflow Rate (SOR) & Weir Overflow Rates 11.4 Process Control Calculations: F/M Ratio, MCRT/Solids Retention Time (SRT) & Sludge Volume Index (SVI) 11.5 Distribution Pressure, Static vs Dynamic Head, Water Horsepower & Wire-to-Water Efficiency 11.6 CT Calculations: Baffling Factors, T10, Temperature and pH Corrections & Multi-Segment Compliance
12 Chapter 12: Safety, Emergency Operations & Compliance
12.1 Permit-Required Confined Space (PRCS) Entry, Atmospheric Testing (O2/LEL/H2S/CO) & Rescue 12.2 Control of Hazardous Energy: Lockout/Tagout (LOTO), Arc Flash & Electrical Safety 12.3 Chemical Safety: Chlorine Gas Handling, Ton Cylinders, Sulfur Dioxide, Ammonia & SDS/GHS 12.4 Trenching & Excavation: Soil Classification, Sloping, Shoring, Shielding & Competent Person Rules 12.5 Emergency Action Plans, Security Vulnerability, Spill Containment & CDPHE Tier 1/2/3 Public Notice 12.6 Work Zone Traffic Control, PPE, Fall Protection, Fire Extinguishers, First Aid & Bloodborne Pathogens 12.7 Standard Operating Procedures, Operating Records, Regulatory Reporting, Customer Complaints & Supervisory Duties
4.2 Chemical Feed Equipment: Feeders, Day Tanks, Carrier Water & Feed-Rate Calibration
Key Takeaways Explain This Topic AI
Volumetric dry feeders meter by volume and are cheaper but less accurate, while gravimetric feeders meter by weight and hold accuracy despite changes in bulk density.
A metering pump's output must be verified against a calibration cylinder rather than trusted from its stroke setting, because backpressure, valve wear, and viscosity all change actual delivery.
Day tanks limit the volume of chemical staged near the feed point, are sized for about one day of use, and require level indication, high-level alarm, and containment.
Chemicals that react must never share piping, containment, or a spill path, and the classic hazard is mixing sodium hypochlorite with acid, which releases chlorine gas.
Feed pumps handling off-gassing solutions such as sodium hypochlorite require a flooded suction, a degassing valve head, or a peristaltic design to prevent vapor lock.
Last updated: August 2026
The equipment that actually delivers the dose
The pounds formula tells you how much chemical to feed. The feed system determines whether that amount actually reaches the water at a steady, verified rate. WPI's outline lists "chemical feed equipment" and "chemical feed pumps" as inspect-maintain-operate items, and separately requires operators to "mix batches of chemical solutions," "add chemicals to hoppers and feed equipment," and "calibrate inline instrumentation."
Dry chemical feeders
Used for lime, soda ash, powdered activated carbon, dry alum, potassium permanganate, and dry polymer.
Volumetric feeders meter a volume of material per unit time using a screw or auger, a rotating disc, a belt with an adjustable gate, or a vibrating pan. They are simple and inexpensive. Their weakness is that they meter volume while the recipe is written in pounds: if the material's bulk density changes because of moisture, compaction, or a different lot, the mass delivered changes even though the setting has not. Accuracy is roughly plus or minus 2 percent at best.
Gravimetric feeders meter by weight using a belt on a load cell or a loss-in-weight hopper. They correct automatically for bulk density and achieve roughly plus or minus 1 percent. They cost more and have more to maintain.
Dry feeders need help staying accurate. Bridging and rat-holing in the hopper starve the feeder; bin activators, vibrators, and air pads break the arch. Hygroscopic materials such as soda ash and some polymers cake with humidity, so hoppers get dehumidified air or heaters. Downstream, the dry chemical drops into a dissolving or slurry chamber where carrier water wets it, and lime slurry lines must be sized and sloped to keep solids moving, because lime scale will close a line completely.
Solution feeders and metering pumps
Used for liquid alum, ferric, sodium hypochlorite, caustic soda, fluoride, phosphate, ammonia, and polymer solutions.
Type Principle Notes
Diaphragm metering pump Reciprocating diaphragm, adjustable stroke length and frequency The workhorse; handles corrosives; needs backpressure and degassing management
Peristaltic (hose) pump Rollers squeeze a flexible tube No valves or seals to foul; ideal for slurries, off-gassing hypochlorite, and polymer; the tube is the wear item
- Progressive cavity Rotor turning in a stator Viscous polymer and sludge
- Rotameter with gravity feed Float in a tapered tube Simple where head is available
Two problems dominate. Vapor lock occurs with sodium hypochlorite, which off-gasses oxygen, increasingly so as it ages and as temperature rises. Gas collects under the pump head and the pump loses prime while continuing to stroke. Remedies are a flooded suction , a degassing or auto-vent valve head , a peristaltic pump, or fresher product. Backpressure problems occur when the injection point pressure is too low or fluctuates, so the pump siphons or over-delivers. A backpressure valve on the discharge and an anti-siphon valve at the injection point correct it.
Storage, day tanks, and containment
Bulk storage is sized for delivery economics and reliable resupply, commonly 15 to 30 days.
A day tank holds roughly one day of usage close to the feeder. It limits the quantity a failure can release, gives a clean volume for volumetric drawdown calibration, and makes daily usage directly measurable.
Every tank needs level indication the operator can read without climbing, high-level alarm and overfill protection during deliveries, and a vent appropriate to the chemical.
Secondary containment must hold the largest tank's volume plus freeboard. Incompatible chemicals must never share containment: sodium hypochlorite and any acid in the same dike will generate chlorine gas if both fail.
Fill connections must be unique and labeled so a delivery driver cannot pump acid into a caustic tank. Cross-connected fill lines have caused fatalities.
Materials of construction matter: 50 percent caustic soda crystallizes below about 55 degrees Fahrenheit and needs heat tracing; hypochlorite degrades with heat, light, and time and should be stored cool and dark; fluorosilicic acid and ferric chloride are aggressive to most metals.
Carrier water and the injection point
The chemical still has to enter the process water correctly.
Carrier water dilutes and transports the chemical from the feeder to the injection point. It must be non-scaling where lime or fluoride is fed, so softened or otherwise conditioned carrier water is often required to keep lines open.
Injection quills extend into the center of the pipe so the chemical enters the turbulent core rather than running down the wall, where it corrodes the pipe and mixes poorly.
The point matters as much as the dose. Coagulant belongs at the rapid mix where energy is highest; permanganate belongs far enough upstream that oxidation finishes before the filters; powdered activated carbon belongs well away from any oxidant; corrosion inhibitor belongs after filtration; fluoride belongs where it will not be lost to sludge.
Chemical incompatibility in the pipe is real: feeding fluoride and lime through the same carrier line produces immediate precipitation and plugging.
Calibrating feed rate
Never trust a dial setting. Two field methods are standard, and both appear on the exam.
1. Volumetric drawdown, for liquid feed. Isolate the day tank and let the pump draw from a graduated calibration cylinder .
Record the starting level, run for a timed interval, and record the ending level.
Volume drawn divided by time gives the actual feed rate in mL/min or gal/hr.
Convert to pounds per day: lbs/day = (gal/day) x (specific gravity x 8.34) x (decimal strength)
Worked example. A hypochlorite pump draws 620 mL in 5.0 minutes from the calibration cylinder. The product is 12.5 percent available chlorine with a specific gravity of 1.20.
- 620 mL divided by 5.0 min = 124 mL/min
- 124 mL/min x 1,440 min/day = 178,560 mL/day, divided by 3,785 mL/gal = 47.2 gal/day
- 47.2 gal/day x (1.20 x 8.34 lb/gal) x 0.125 = 47.2 x 10.008 x 0.125 = 59.0 lbs/day of available chlorine
If the plant treats 4.0 MGD, the delivered dose is 59.0 divided by (4.0 x 8.34), which is 1.77 mg/L . Compare that against the target dose; the difference is your calibration error.
2. Catch and weigh, for dry feed. Divert the feeder discharge into a tared container for a measured time, weigh the catch, and scale up:
lbs/day = (grams caught / 453.6) / (minutes caught) x 1,440
Worked example. A lime feeder discharges 1,260 grams in 4.0 minutes.
- 1,260 divided by 453.6 = 2.778 lbs in 4.0 minutes
- 2.778 divided by 4.0 = 0.6944 lbs/min, times 1,440 = 1,000 lbs/day
Calibration is repeated at several settings to build a calibration curve , and it is repeated after any pump rebuild, valve replacement, chemical lot change, or significant change in injection point pressure. Records of each calibration belong in the equipment file. WPI lists completing equipment maintenance and repair records including work orders as a job task, and a feed calibration record is the document that proves your reported dose was real.
Routine maintenance and safety
Rebuild metering pump check valves and diaphragms on a schedule; worn check balls are the single most common cause of drifting feed rate.
Replace peristaltic tubing before it fails, since failure dumps chemical into the pump housing.
Flush and clean lime and fluoride lines on a schedule to prevent scale closure.
Verify calibration cylinders, rotameters, and mass flow meters against a known volume.
Wear the PPE the safety data sheet specifies, including a face shield, chemical goggles, and gloves and apron of the correct material, for every connection break, and know where the nearest eyewash and safety shower are before you start.