Study guide

8.9 Excavation, Hydro Excavation, Bedding and Haunching, Grade Control & Sewer Acceptance Testing

Colorado Water/Wastewater Operator Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: State Laws, Regulations & CCWP Certification

1.1 CDPHE CCWP Program & Regulatory Framework (Regulation 100 / 5 CCR 1003-2) 1.2 Facility Classification & Operator in Responsible Charge (ORC) Requirements 1.3 Certification Levels, Education, Experience & Exam Eligibility (Class D-A, Grade 1-4, Class S/T) 1.4 License Renewal, Training Units (TUs) & Mandatory Regulatory Training 1.5 Colorado Primary Drinking Water Regulations (Regulation 11) & Compliance 1.6 Colorado Discharge Permit System (Regulations 61/62), DMRs & Biosolids Reporting

2 Chapter 2: Source Water & Drinking Water Treatment Processes

2.1 Raw Water Sources, High-Altitude Characteristics & Reservoir Quality 2.2 Coagulation Chemistry, Rapid Mixing & Chemical Dosing (Alum, Ferric, Polymers) 2.3 Flocculation & Sedimentation Basin Design, Operation & Settling Zones 2.4 Granular Media Filtration, Backwash Procedures & Turbidity Standards 2.5 Advanced Treatment: Membranes, Softening, GAC/PAC Adsorption & Aeration 2.6 Groundwater Sources, Well Hydraulics, Static and Pumping Levels & Specific Capacity 2.7 Source Water Characteristics, Contaminant Categories & Watershed Protection Plans 2.8 Pretreatment: Presedimentation, Aeration, Algae Control & Taste-and-Odor Management 2.9 Direct, In-Line, Pressure, Cartridge & Diatomaceous Earth Filtration 2.10 Lime-Soda Softening, Ion Exchange & Water Stabilization 2.11 Water Treatment Plant Residuals: Lagoons, Drying Beds, Land Application & Recycle

3 Chapter 3: Disinfection & Chemical Addition

3.1 Chlorine Chemistry: Hypochlorous Acid, Free/Combined Residual & Breakpoint Chlorination 3.2 Disinfection Kinetics, Baffle Factors, T10 & CT Compliance Calculations 3.3 Disinfection Byproducts (TTHMs, HAA5s) & Stage 1/2 DBP Rules 3.4 Alternative Disinfection: Chloramination, Ultraviolet (UV) Light & Chlorine Dioxide 3.5 Corrosion Control, Lead & Copper Rule Revisions (LCRR) & Fluoridation Practices

4 Chapter 4: Water Treatment Plant Equipment, Instrumentation & Maintenance

4.1 Raw Water Intakes, Screening Equipment & Raw Water Pumping 4.2 Chemical Feed Equipment: Feeders, Day Tanks, Carrier Water & Feed-Rate Calibration 4.3 Chlorination Equipment: Gas Systems, Vacuum Regulators, Hypochlorite Storage & Onsite Generation 4.4 Filter Underdrains, Support Gravel, Surface Wash, Air Scour & Filter-to-Waste 4.5 Plant Process Control, SCADA and PLC Systems, Alarm Management & Records of Operation 4.6 Preventive, Corrective and Predictive Maintenance, Work Orders & Asset Management

5 Chapter 5: Wastewater Treatment Principles & Biological Processes

5.1 Preliminary Treatment: Bar Screens, Shredders, Grit Chambers & Flow Equalization 5.2 Primary Clarification, Solids Separation & Scum Removal Mechanics 5.3 Activated Sludge Fundamentals: Aerobic Microbiology, DO Control & Biomass Growth 5.4 Return & Waste Activated Sludge Management (RAS/WAS Operations & Sludge Age) 5.5 Activated Sludge Troubleshooting: Bulking, Nocardia Foaming, Rising Sludge & Pin Floc 5.6 Wastewater Characteristics, Organic and Hydraulic Loading, Diurnal Flow & Septicity 5.7 Activated Sludge Arrangements: Conventional, Complete Mix, Step Feed, Contact Stabilization, Extended Aeration, Oxidation Ditch, SBR & MBR 5.8 Aeration Systems: Blowers, Diffusers, Surface Aerators, Oxygen Transfer & Altitude Effects

6 Chapter 6: Advanced Wastewater Treatment & Solids Management

6.1 Biological Nutrient Removal: Nitrification, Denitrification & Anoxic Zones 6.2 Biological & Chemical Phosphorus Removal (EBPR & Coagulant Precipitation) 6.3 Sludge Thickening, Aerobic & Anaerobic Digestion (Mesophilic/Thermophilic) 6.4 Dewatering Equipment (Centrifuges, Belt Filter Presses) & Biosolids Standards (Reg 64) 6.5 Pond & Lagoon Operations, Trickling Filters & Rotating Biological Contactors (RBCs) 6.6 Secondary Clarification: Overflow and Solids Loading Rates, RAS Rate Setting & Clarifier Diagnostics 6.7 Tertiary Filtration, Effluent Polishing & Wastewater Disinfection with Chlorine, Dechlorination and UV 6.8 Effluent Disposal, Rapid Infiltration Basins, Colorado Water Reuse Law & Regulation 84

7 Chapter 7: Water Distribution Systems

7.1 Distribution Hydraulics, Pressure Zones, Static Head & Friction Headloss 7.2 Finished Water Storage Tanks, Standpipes, Mixing & Water Age Control 7.3 Distribution Piping, Valves (Gate, Butterfly, PRV), Hydrants & Main Flushing 7.4 Cross-Connection Control, Hazard Assessment & Backflow Preventers (RPZ, DCVA, PVB, Air Gap) 7.5 Water Main Installation, Trenching, Repair, Pressure Testing & Disinfection (AWWA C651) 7.6 Network Layout, Pressure Zones, Demand Patterns, Fire Flow & the Hydraulic Grade Line 7.7 Fire Hydrants, Dry Barrel Operation, Fire Flow Testing & Unidirectional Flushing 7.8 Booster Pump Stations, Hydropneumatic Systems, Controls & Surge Protection 7.9 Customer and Master Metering, Meter Sizing, Accuracy Testing, AMR & AMI 7.10 System Mapping, GIS, As-Builts, Operational Analysis & the AWWA Water Audit 7.11 Service Line Installation, Wet Tapping, Curb Stops & the Lead Service Line Inventory 7.12 Leak Detection, District Metered Areas, Minimum Night Flow & Pressure Management 7.13 Storage Facility Inspection, Sanitary Defects, Water Age Control, Cleaning & AWWA C652 Disinfection 7.14 Utility Locating, Colorado 811 Damage Prevention, the APWA Color Code & New Construction Inspection 7.15 Well and Wellhead Maintenance, Sanitary Condition, Rehabilitation & AWWA C654 Disinfection 7.16 Booster Chlorination, Remote Chemical Feed, Chemical Storage, Security & Supply Management 7.17 Distribution Sampling Technique, Chlorine Residual Monitoring & Nitrification Control in Chloraminated Systems

8 Chapter 8: Wastewater Collection Systems

8.1 Gravity Collection Systems: Flow Velocities, Slopes, Pipe Materials & Manholes 8.2 Wastewater Lift Stations: Wet Wells, Submersible Pumps, Level Controls & Force Mains 8.3 Inflow and Infiltration (I&I) Sources, Flow Monitoring, Smoke Testing & CCTV Inspection 8.4 Collection Maintenance: Hydraulic Jetting, Mechanical Rodding & FOG/Root Mitigation 8.5 Sanitary Sewer Overflows (SSOs): Root Causes, Containment, Reporting & Mitigation 8.6 Lift Station Electrical Devices, Level Detection, Telemetry, Gas Detection & Capacity Adjustment 8.7 Lift Station Configurations, Preventive Maintenance, Wet Well Cleaning, Troubleshooting & Emergency Bypass Pumping 8.8 Collection System Rehabilitation: CIPP, Pipe Bursting, Sliplining, Grouting, Manhole Repair & Tap Defects 8.9 Excavation, Hydro Excavation, Bedding and Haunching, Grade Control & Sewer Acceptance Testing 8.10 Collection System Flow Monitoring, Area-Velocity Metering, Weirs and Flumes & Capacity Assessment

9 Chapter 9: Pumps, Motors & Utility Mechanics

9.1 Centrifugal Pumps: Volutes, Impellers, Packing Seals & Mechanical Seals 9.2 Positive Displacement Pumps (Peristaltic, Diaphragm, Progressive Cavity) & Dosing Systems 9.3 Pump Performance Curves, System Head Curves, Cavitation & NPSH Calculations 9.4 Electric Motors (Single/Three Phase), Controls, Variable Frequency Drives (VFDs) & Power 9.5 Flow Meters (Venturi, Magnetic, Ultrasonic), Online Analyzers, PLCs & SCADA Telemetry 9.6 Air Compressors, Conveyors, Hoists and Cranes, Service Piping & Standby Power Generation 9.7 Valve Types and Duties, Air Release and Air-Vacuum Valves, Water Hammer & Surge Control

10 Chapter 10: Laboratory Analysis & Water Quality Monitoring

10.1 Regulatory Sampling Procedures, Chain of Custody, Holding Times & Preservation Techniques 10.2 Physical & Chemical Drinking Water Testing: Turbidity, pH, Alkalinity, Hardness & Chlorine (DPD) 10.3 Wastewater Laboratory Analysis: BOD5, COD, Total Suspended Solids (TSS) & Settleometry 10.4 Microbiological Testing: Total Coliform, E. coli (Colilert, Membrane Filtration) & QA/QC 10.5 Bench-Scale Jar Testing, Coagulant Optimization & Streaming Current Monitoring 10.6 Laboratory Equipment, Calibration and Verification, QA/QC Program & Certified Laboratory Requirements 10.7 Nutrient Series, Metals Sampling, Whole Effluent Toxicity & Electrode Measurements (DO, pH, ORP, H2S)

11 Chapter 11: Operator Mathematics & Applied Calculations

11.1 Core Conversions, Geometric Area, Pipe Volume & Continuous Flow Rate (MGD, GPM, cfs) 11.2 Chemical Dosage, The Standard "Pounds Formula", Active Chemical & Solution Purity 11.3 Hydraulic Retention Time (HRT), Surface Overflow Rate (SOR) & Weir Overflow Rates 11.4 Process Control Calculations: F/M Ratio, MCRT/Solids Retention Time (SRT) & Sludge Volume Index (SVI) 11.5 Distribution Pressure, Static vs Dynamic Head, Water Horsepower & Wire-to-Water Efficiency 11.6 CT Calculations: Baffling Factors, T10, Temperature and pH Corrections & Multi-Segment Compliance

12 Chapter 12: Safety, Emergency Operations & Compliance

12.1 Permit-Required Confined Space (PRCS) Entry, Atmospheric Testing (O2/LEL/H2S/CO) & Rescue 12.2 Control of Hazardous Energy: Lockout/Tagout (LOTO), Arc Flash & Electrical Safety 12.3 Chemical Safety: Chlorine Gas Handling, Ton Cylinders, Sulfur Dioxide, Ammonia & SDS/GHS 12.4 Trenching & Excavation: Soil Classification, Sloping, Shoring, Shielding & Competent Person Rules 12.5 Emergency Action Plans, Security Vulnerability, Spill Containment & CDPHE Tier 1/2/3 Public Notice 12.6 Work Zone Traffic Control, PPE, Fall Protection, Fire Extinguishers, First Aid & Bloodborne Pathogens 12.7 Standard Operating Procedures, Operating Records, Regulatory Reporting, Customer Complaints & Supervisory Duties

8.9 Excavation, Hydro Excavation, Bedding and Haunching, Grade Control & Sewer Acceptance Testing

Key Takeaways Explain This Topic AI

Hydro excavation is the standard method for potholing inside the tolerance zone, working around roots, and cutting frozen Colorado ground, but the water jet can cut and inject beneath the skin.

The haunch zone beneath the lower quadrants of the pipe carries most of the load transfer and is the zone most often installed poorly.

Bell holes are excavated at each joint so the pipe bears on its barrel rather than on the bell, which would create a point load and shear the pipe.

A sag or belly passes an air test but traps water, grease, and grit permanently and is one of the most common reasons new sewer construction is rejected.

Deflection is verified with a go/no-go mandrel, commonly to a 5 percent limit and usually at least 30 days after backfill, and plugs used for air testing must be restrained because a blown plug is lethal.

Last updated: August 2026

Getting the pipe in the ground correctly

WPI lists excavate wastewater lines , hydro excavation , and inspect pipe installation (grade, joints, bedding, backfill, pipe defects, pressure test) as collection job tasks. The distribution outline adds inspecting new construction. Installation quality determines whether a gravity sewer works for eighty years or fails in eight.

Excavation methods

Conventional open cut with a backhoe or excavator remains standard for shallow sewer work. The controls are covered in the trenching and excavation safety section: soil classification, sloping, benching, shoring or shielding, spoil setback, and the competent person.

Hydro excavation (vacuum excavation) uses high-pressure water to cut soil and a vacuum to remove the slurry. It is listed explicitly by WPI because it has become the standard method for:

Potholing (daylighting) to expose an existing utility inside the tolerance zone, where mechanical excavation is prohibited.

Working around tree roots , where blades would sever them.

Frozen ground , using heated water, which is a genuine Colorado advantage.

Precise, narrow excavations that minimize restoration.

Its hazards are specific and are frequently underestimated: the water jet is capable of cutting flesh and injecting water and debris under the skin , so operators use hand and body protection and never place a hand near the nozzle; the spoil tank contains a slurry that is heavy and can shift ; and the debris tank is a confined space . Air vacuum excavation avoids the water-jet injury hazard and keeps the spoil reusable but works poorly in hard or cohesive soil.

Bedding, haunching, and backfill

A buried pipe is a structure that depends on the soil around it. The zones, from the trench bottom upward:

Foundation — the trench bottom. Must be firm and uniform. Soft or unstable material is over-excavated and replaced with crushed rock.

Bedding — graded granular material placed and compacted to grade, on which the pipe rests. The pipe must bear on the barrel , never on the bell , so bell holes are excavated at each joint.

Haunching — the material worked in beneath the lower quadrants of the pipe. This is the zone most commonly done badly and it carries most of the load transfer. Unhaunched pipe deflects and cracks.

Initial backfill — to a specified height above the crown, placed in lifts and compacted, protecting the pipe from the final backfill.

Final backfill — to grade, compacted to the specification appropriate to the surface use.

Flexible pipe — PVC, HDPE — carries load by deflecting and transferring it to the surrounding soil, so bedding and haunching are structural. Deflection is limited by specification, commonly 5 percent , and is verified by pulling a mandrel through the completed line. Rigid pipe — vitrified clay, concrete — carries load in the pipe wall, but still requires uniform support to avoid point loading and shear failure at the bells.

Grade and alignment

Gravity sewers work only if the grade is right. Installation grade is set by laser, by a pipe laser in the line, by grade rod and batter boards, or by machine control.

Too flat , and velocity falls below the scouring minimum of roughly 2 ft/s , so solids deposit and the line becomes a maintenance problem forever.

Too steep is rarely a hydraulic problem but can cause erosion at the invert and requires anchorage on steep slopes.

A sag (belly) holds standing water, collects grease and grit, and generates hydrogen sulfide and chronic blockages. Sags show up on CCTV as standing water and are one of the defects that most often triggers rejection of new construction.

Alignment must be straight between manholes for CCTV, cleaning, and rodding access.

Joints and testing

Joint types include gasketed bell and spigot (the standard for PVC and ductile iron), solvent weld for some small PVC, fusion for HDPE, and compression couplings for repairs. Joints must be clean, lubricated with the approved lubricant, and homed to the reference mark. Overinsertion is as much a defect as underinsertion.

Acceptance testing for gravity sewers, per the specification:

Test Method

Low-pressure air test Isolate a reach with plugs, pressurize to about 4 psig above groundwater pressure, and time the pressure drop against a table based on diameter and length

  • Hydrostatic exfiltration test Fill the reach and measure the loss over time
  • Infiltration test Where groundwater is above the pipe, measure inflow at the downstream manhole

Deflection (mandrel) test Pull a go/no-go mandrel, usually at least 30 days after backfill , to verify deflection is within limits

  • Lamping and CCTV Visual verification of alignment, grade, joints, and absence of sags and debris
  • Manhole vacuum test Draw a vacuum on a plugged manhole and time the decay

Safety note on air testing: a plug that blows out of a pressurized sewer is lethal. Plugs are restrained, no one enters a manhole while a reach is under pressure, and pressure is bled off before plugs are removed. The relatively low 4 psig used for air testing still stores enormous energy in a large-diameter line.

Loading diagram... Pipe Installation Zones, Grade Control, and Acceptance Testing