8.7 Lift Station Configurations, Preventive Maintenance, Wet Well Cleaning, Troubleshooting & Emergency Bypass Pumping
Colorado Water/Wastewater Operator Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: State Laws, Regulations & CCWP Certification
1.1 CDPHE CCWP Program & Regulatory Framework (Regulation 100 / 5 CCR 1003-2) 1.2 Facility Classification & Operator in Responsible Charge (ORC) Requirements 1.3 Certification Levels, Education, Experience & Exam Eligibility (Class D-A, Grade 1-4, Class S/T) 1.4 License Renewal, Training Units (TUs) & Mandatory Regulatory Training 1.5 Colorado Primary Drinking Water Regulations (Regulation 11) & Compliance 1.6 Colorado Discharge Permit System (Regulations 61/62), DMRs & Biosolids Reporting
2 Chapter 2: Source Water & Drinking Water Treatment Processes
2.1 Raw Water Sources, High-Altitude Characteristics & Reservoir Quality 2.2 Coagulation Chemistry, Rapid Mixing & Chemical Dosing (Alum, Ferric, Polymers) 2.3 Flocculation & Sedimentation Basin Design, Operation & Settling Zones 2.4 Granular Media Filtration, Backwash Procedures & Turbidity Standards 2.5 Advanced Treatment: Membranes, Softening, GAC/PAC Adsorption & Aeration 2.6 Groundwater Sources, Well Hydraulics, Static and Pumping Levels & Specific Capacity 2.7 Source Water Characteristics, Contaminant Categories & Watershed Protection Plans 2.8 Pretreatment: Presedimentation, Aeration, Algae Control & Taste-and-Odor Management 2.9 Direct, In-Line, Pressure, Cartridge & Diatomaceous Earth Filtration 2.10 Lime-Soda Softening, Ion Exchange & Water Stabilization 2.11 Water Treatment Plant Residuals: Lagoons, Drying Beds, Land Application & Recycle
3 Chapter 3: Disinfection & Chemical Addition
3.1 Chlorine Chemistry: Hypochlorous Acid, Free/Combined Residual & Breakpoint Chlorination 3.2 Disinfection Kinetics, Baffle Factors, T10 & CT Compliance Calculations 3.3 Disinfection Byproducts (TTHMs, HAA5s) & Stage 1/2 DBP Rules 3.4 Alternative Disinfection: Chloramination, Ultraviolet (UV) Light & Chlorine Dioxide 3.5 Corrosion Control, Lead & Copper Rule Revisions (LCRR) & Fluoridation Practices
4 Chapter 4: Water Treatment Plant Equipment, Instrumentation & Maintenance
4.1 Raw Water Intakes, Screening Equipment & Raw Water Pumping 4.2 Chemical Feed Equipment: Feeders, Day Tanks, Carrier Water & Feed-Rate Calibration 4.3 Chlorination Equipment: Gas Systems, Vacuum Regulators, Hypochlorite Storage & Onsite Generation 4.4 Filter Underdrains, Support Gravel, Surface Wash, Air Scour & Filter-to-Waste 4.5 Plant Process Control, SCADA and PLC Systems, Alarm Management & Records of Operation 4.6 Preventive, Corrective and Predictive Maintenance, Work Orders & Asset Management
5 Chapter 5: Wastewater Treatment Principles & Biological Processes
5.1 Preliminary Treatment: Bar Screens, Shredders, Grit Chambers & Flow Equalization 5.2 Primary Clarification, Solids Separation & Scum Removal Mechanics 5.3 Activated Sludge Fundamentals: Aerobic Microbiology, DO Control & Biomass Growth 5.4 Return & Waste Activated Sludge Management (RAS/WAS Operations & Sludge Age) 5.5 Activated Sludge Troubleshooting: Bulking, Nocardia Foaming, Rising Sludge & Pin Floc 5.6 Wastewater Characteristics, Organic and Hydraulic Loading, Diurnal Flow & Septicity 5.7 Activated Sludge Arrangements: Conventional, Complete Mix, Step Feed, Contact Stabilization, Extended Aeration, Oxidation Ditch, SBR & MBR 5.8 Aeration Systems: Blowers, Diffusers, Surface Aerators, Oxygen Transfer & Altitude Effects
6 Chapter 6: Advanced Wastewater Treatment & Solids Management
6.1 Biological Nutrient Removal: Nitrification, Denitrification & Anoxic Zones 6.2 Biological & Chemical Phosphorus Removal (EBPR & Coagulant Precipitation) 6.3 Sludge Thickening, Aerobic & Anaerobic Digestion (Mesophilic/Thermophilic) 6.4 Dewatering Equipment (Centrifuges, Belt Filter Presses) & Biosolids Standards (Reg 64) 6.5 Pond & Lagoon Operations, Trickling Filters & Rotating Biological Contactors (RBCs) 6.6 Secondary Clarification: Overflow and Solids Loading Rates, RAS Rate Setting & Clarifier Diagnostics 6.7 Tertiary Filtration, Effluent Polishing & Wastewater Disinfection with Chlorine, Dechlorination and UV 6.8 Effluent Disposal, Rapid Infiltration Basins, Colorado Water Reuse Law & Regulation 84
7 Chapter 7: Water Distribution Systems
7.1 Distribution Hydraulics, Pressure Zones, Static Head & Friction Headloss 7.2 Finished Water Storage Tanks, Standpipes, Mixing & Water Age Control 7.3 Distribution Piping, Valves (Gate, Butterfly, PRV), Hydrants & Main Flushing 7.4 Cross-Connection Control, Hazard Assessment & Backflow Preventers (RPZ, DCVA, PVB, Air Gap) 7.5 Water Main Installation, Trenching, Repair, Pressure Testing & Disinfection (AWWA C651) 7.6 Network Layout, Pressure Zones, Demand Patterns, Fire Flow & the Hydraulic Grade Line 7.7 Fire Hydrants, Dry Barrel Operation, Fire Flow Testing & Unidirectional Flushing 7.8 Booster Pump Stations, Hydropneumatic Systems, Controls & Surge Protection 7.9 Customer and Master Metering, Meter Sizing, Accuracy Testing, AMR & AMI 7.10 System Mapping, GIS, As-Builts, Operational Analysis & the AWWA Water Audit 7.11 Service Line Installation, Wet Tapping, Curb Stops & the Lead Service Line Inventory 7.12 Leak Detection, District Metered Areas, Minimum Night Flow & Pressure Management 7.13 Storage Facility Inspection, Sanitary Defects, Water Age Control, Cleaning & AWWA C652 Disinfection 7.14 Utility Locating, Colorado 811 Damage Prevention, the APWA Color Code & New Construction Inspection 7.15 Well and Wellhead Maintenance, Sanitary Condition, Rehabilitation & AWWA C654 Disinfection 7.16 Booster Chlorination, Remote Chemical Feed, Chemical Storage, Security & Supply Management 7.17 Distribution Sampling Technique, Chlorine Residual Monitoring & Nitrification Control in Chloraminated Systems
8 Chapter 8: Wastewater Collection Systems
8.1 Gravity Collection Systems: Flow Velocities, Slopes, Pipe Materials & Manholes 8.2 Wastewater Lift Stations: Wet Wells, Submersible Pumps, Level Controls & Force Mains 8.3 Inflow and Infiltration (I&I) Sources, Flow Monitoring, Smoke Testing & CCTV Inspection 8.4 Collection Maintenance: Hydraulic Jetting, Mechanical Rodding & FOG/Root Mitigation 8.5 Sanitary Sewer Overflows (SSOs): Root Causes, Containment, Reporting & Mitigation 8.6 Lift Station Electrical Devices, Level Detection, Telemetry, Gas Detection & Capacity Adjustment 8.7 Lift Station Configurations, Preventive Maintenance, Wet Well Cleaning, Troubleshooting & Emergency Bypass Pumping 8.8 Collection System Rehabilitation: CIPP, Pipe Bursting, Sliplining, Grouting, Manhole Repair & Tap Defects 8.9 Excavation, Hydro Excavation, Bedding and Haunching, Grade Control & Sewer Acceptance Testing 8.10 Collection System Flow Monitoring, Area-Velocity Metering, Weirs and Flumes & Capacity Assessment
9 Chapter 9: Pumps, Motors & Utility Mechanics
9.1 Centrifugal Pumps: Volutes, Impellers, Packing Seals & Mechanical Seals 9.2 Positive Displacement Pumps (Peristaltic, Diaphragm, Progressive Cavity) & Dosing Systems 9.3 Pump Performance Curves, System Head Curves, Cavitation & NPSH Calculations 9.4 Electric Motors (Single/Three Phase), Controls, Variable Frequency Drives (VFDs) & Power 9.5 Flow Meters (Venturi, Magnetic, Ultrasonic), Online Analyzers, PLCs & SCADA Telemetry 9.6 Air Compressors, Conveyors, Hoists and Cranes, Service Piping & Standby Power Generation 9.7 Valve Types and Duties, Air Release and Air-Vacuum Valves, Water Hammer & Surge Control
10 Chapter 10: Laboratory Analysis & Water Quality Monitoring
10.1 Regulatory Sampling Procedures, Chain of Custody, Holding Times & Preservation Techniques 10.2 Physical & Chemical Drinking Water Testing: Turbidity, pH, Alkalinity, Hardness & Chlorine (DPD) 10.3 Wastewater Laboratory Analysis: BOD5, COD, Total Suspended Solids (TSS) & Settleometry 10.4 Microbiological Testing: Total Coliform, E. coli (Colilert, Membrane Filtration) & QA/QC 10.5 Bench-Scale Jar Testing, Coagulant Optimization & Streaming Current Monitoring 10.6 Laboratory Equipment, Calibration and Verification, QA/QC Program & Certified Laboratory Requirements 10.7 Nutrient Series, Metals Sampling, Whole Effluent Toxicity & Electrode Measurements (DO, pH, ORP, H2S)
11 Chapter 11: Operator Mathematics & Applied Calculations
11.1 Core Conversions, Geometric Area, Pipe Volume & Continuous Flow Rate (MGD, GPM, cfs) 11.2 Chemical Dosage, The Standard "Pounds Formula", Active Chemical & Solution Purity 11.3 Hydraulic Retention Time (HRT), Surface Overflow Rate (SOR) & Weir Overflow Rates 11.4 Process Control Calculations: F/M Ratio, MCRT/Solids Retention Time (SRT) & Sludge Volume Index (SVI) 11.5 Distribution Pressure, Static vs Dynamic Head, Water Horsepower & Wire-to-Water Efficiency 11.6 CT Calculations: Baffling Factors, T10, Temperature and pH Corrections & Multi-Segment Compliance
12 Chapter 12: Safety, Emergency Operations & Compliance
12.1 Permit-Required Confined Space (PRCS) Entry, Atmospheric Testing (O2/LEL/H2S/CO) & Rescue 12.2 Control of Hazardous Energy: Lockout/Tagout (LOTO), Arc Flash & Electrical Safety 12.3 Chemical Safety: Chlorine Gas Handling, Ton Cylinders, Sulfur Dioxide, Ammonia & SDS/GHS 12.4 Trenching & Excavation: Soil Classification, Sloping, Shoring, Shielding & Competent Person Rules 12.5 Emergency Action Plans, Security Vulnerability, Spill Containment & CDPHE Tier 1/2/3 Public Notice 12.6 Work Zone Traffic Control, PPE, Fall Protection, Fire Extinguishers, First Aid & Bloodborne Pathogens 12.7 Standard Operating Procedures, Operating Records, Regulatory Reporting, Customer Complaints & Supervisory Duties
8.7 Lift Station Configurations, Preventive Maintenance, Wet Well Cleaning, Troubleshooting & Emergency Bypass Pumping
Key Takeaways Explain This Topic AI
Low motor amperage with low discharge pressure means an unloaded pump, while high amperage means a bound pump, and high discharge pressure with low flow means a downstream obstruction.
Air accumulating at force main high points without air release valves is a classic cause of a station that gradually stops keeping up.
Wet wells are cleaned from outside with a vacuum truck, and any entry requires a full permit-required confined space entry because hydrogen sulfide and oxygen deficiency have killed entrants and rescuers alike.
Reduced atmospheric pressure at Colorado elevations lowers the maximum practical suction lift, so bypass pumps that prime easily near sea level may not at 8,000 feet.
Testing the high-level alarm and verifying that pump alternation is actually rotating duty are routine checks, because a standby pump that never runs is not a standby.
Last updated: August 2026
Keeping the station running and getting flow around it when it does not
WPI's collection outline lists "rehabilitate and repair collection system: lift station (wet wells, fittings, and piping)", "inspect equipment or monitor operating conditions, meters, and gauges to determine load requirements and detect malfunctions of the lift station", "perform preventative maintenance including repair, replacement, and installation of equipment: motors, pumps, valves, engines, generators, level sensing equipment", "clean and maintain tanks (wet wells, chemical, holding)", and "operate pumping equipment during emergency bypass operations."
Station configurations and their maintenance implications
Configuration Description Maintenance character
Submersible Pump and motor submerged in the wet well, removed on guide rails No dry well to enter; pump lifted for service; the wet well is a permit-required confined space
Dry pit / dry well Pumps in an adjacent dry chamber, suction piped from the wet well Pumps accessible while running; the dry well is itself a confined space in most designs
Wet pit / dry pit combination Vertical pumps with motors above and wet-end below Long shafts and intermediate bearings
Suction lift (self-priming) Pumps at grade drawing from the wet well Easiest access; priming and suction-line air leaks are the recurring problem
Vacuum and pressure (grinder) systems Small-diameter collection with grinder pumps or vacuum valves Many distributed units; valve and grinder maintenance dominates
Routine preventive maintenance
Daily or per visit: record runtime hours and starts for each pump, wet well level behavior, discharge pressure, motor amperage on all three legs, and any alarms since the last visit. Look and listen. Note odor, unusual noise, vibration, and any sign of surcharge above the normal high-water mark.
Weekly to monthly: exercise the standby pump and confirm alternation is actually rotating duty; test the high-level alarm by lifting the float and confirming the alarm reaches the answering point; inspect and clean float switches and level transducers of grease and rags; check the ventilation fan operates; verify the standby generator exercises and the transfer switch operates.
Quarterly to annually: pull and inspect pumps for wear, rag accumulation, and impeller clearance; inspect check valves and exercise isolation valves ; service seals and packing ; lubricate bearings per the schedule; megger motor insulation; inspect the wet well interior for corrosion, benching condition, and structural deterioration; clean the wet well.
Wet well cleaning is a job of its own. Grease mats float on the surface and harden; grit settles in corners the pumps cannot reach and gradually reduces the working volume; rags rope together and blind the pump intake. Cleaning uses a vacuum truck to remove the accumulation, followed by washdown. Never enter to clean without a permit-required confined space entry with atmospheric testing, forced ventilation, an attendant, and retrieval equipment. Hydrogen sulfide and oxygen deficiency in a wet well have killed operators and, repeatedly, the would-be rescuers who followed them in.
Diagnosing a station that is not keeping up
Work the list in order rather than jumping to the pump:
Is this a flow problem or a pump problem? Compare current inflow with historical. A wet-weather inflow spike is an I&I problem, not a pump failure.
Amperage. Low amperage with low discharge pressure means the pump is not loaded: a blocked or air-bound suction, a lost prime, a broken shaft, or a worn impeller. High amperage means the pump is bound: rags, a seized bearing, or a closed discharge valve.
Discharge pressure. High discharge pressure with low flow means an obstruction downstream — a partly closed valve, a failed check valve seated shut, or a blocked force main.
Check valve behavior. A check valve stuck open lets flow return between pump starts, causing short cycling and false level readings.
Air in the force main. High points without air release valves accumulate gas from septic wastewater and progressively reduce capacity. This is a classic cause of a station that "used to keep up."
Impeller wear and clearance. Adjustable wear plates on solids-handling pumps are reset to specification; excessive clearance destroys capacity.
Level control error. A drifting transducer changes the working volume and masquerades as a capacity problem.
Emergency bypass pumping
Bypass pumping keeps flow moving when a station is down, a force main is being repaired, or a gravity segment is being rehabilitated. It is an explicit WPI job task and is planned in advance rather than improvised.
Elements of a bypass plan:
Sizing for the expected peak flow, not the average, with standby capacity.
Suction access — a manhole or wet well opening that can be reached and will not collapse under the suction hose.
Pump selection. Diesel or electric trash pumps or vacuum-assisted self-priming units capable of passing solids. Suction lift is limited by atmospheric pressure and by elevation, which matters in Colorado: at 8,000 feet the maximum practical suction lift is meaningfully less than at sea level , so a pump that primes easily on the Front Range may not at altitude.
Discharge routing to a downstream manhole with hose or pipe secured against movement, protected at road crossings by ramps or by boring, and restrained at the discharge so it cannot whip.
Containment and spill response materials staged in case a hose fails.
Continuous attendance or remote monitoring with alarms , plus fuel management for extended operation.
Notification. Any bypass that results in a discharge is a sanitary sewer overflow and is reported to CDPHE and, where applicable, under the CDPS permit's 24-hour reporting condition.
Documentation — start and stop times, flows, personnel, and any spillage.