1 Chapter 1: State Laws, Regulations & CCWP Certification

1.1 CDPHE CCWP Program & Regulatory Framework (Regulation 100 / 5 CCR 1003-2) 1.2 Facility Classification & Operator in Responsible Charge (ORC) Requirements 1.3 Certification Levels, Education, Experience & Exam Eligibility (Class D-A, Grade 1-4, Class S/T) 1.4 License Renewal, Training Units (TUs) & Mandatory Regulatory Training 1.5 Colorado Primary Drinking Water Regulations (Regulation 11) & Compliance 1.6 Colorado Discharge Permit System (Regulations 61/62), DMRs & Biosolids Reporting

2 Chapter 2: Source Water & Drinking Water Treatment Processes

2.1 Raw Water Sources, High-Altitude Characteristics & Reservoir Quality 2.2 Coagulation Chemistry, Rapid Mixing & Chemical Dosing (Alum, Ferric, Polymers) 2.3 Flocculation & Sedimentation Basin Design, Operation & Settling Zones 2.4 Granular Media Filtration, Backwash Procedures & Turbidity Standards 2.5 Advanced Treatment: Membranes, Softening, GAC/PAC Adsorption & Aeration 2.6 Groundwater Sources, Well Hydraulics, Static and Pumping Levels & Specific Capacity 2.7 Source Water Characteristics, Contaminant Categories & Watershed Protection Plans 2.8 Pretreatment: Presedimentation, Aeration, Algae Control & Taste-and-Odor Management 2.9 Direct, In-Line, Pressure, Cartridge & Diatomaceous Earth Filtration 2.10 Lime-Soda Softening, Ion Exchange & Water Stabilization 2.11 Water Treatment Plant Residuals: Lagoons, Drying Beds, Land Application & Recycle

3 Chapter 3: Disinfection & Chemical Addition

3.1 Chlorine Chemistry: Hypochlorous Acid, Free/Combined Residual & Breakpoint Chlorination 3.2 Disinfection Kinetics, Baffle Factors, T10 & CT Compliance Calculations 3.3 Disinfection Byproducts (TTHMs, HAA5s) & Stage 1/2 DBP Rules 3.4 Alternative Disinfection: Chloramination, Ultraviolet (UV) Light & Chlorine Dioxide 3.5 Corrosion Control, Lead & Copper Rule Revisions (LCRR) & Fluoridation Practices

4 Chapter 4: Water Treatment Plant Equipment, Instrumentation & Maintenance

4.1 Raw Water Intakes, Screening Equipment & Raw Water Pumping 4.2 Chemical Feed Equipment: Feeders, Day Tanks, Carrier Water & Feed-Rate Calibration 4.3 Chlorination Equipment: Gas Systems, Vacuum Regulators, Hypochlorite Storage & Onsite Generation 4.4 Filter Underdrains, Support Gravel, Surface Wash, Air Scour & Filter-to-Waste 4.5 Plant Process Control, SCADA and PLC Systems, Alarm Management & Records of Operation 4.6 Preventive, Corrective and Predictive Maintenance, Work Orders & Asset Management

5 Chapter 5: Wastewater Treatment Principles & Biological Processes

5.1 Preliminary Treatment: Bar Screens, Shredders, Grit Chambers & Flow Equalization 5.2 Primary Clarification, Solids Separation & Scum Removal Mechanics 5.3 Activated Sludge Fundamentals: Aerobic Microbiology, DO Control & Biomass Growth 5.4 Return & Waste Activated Sludge Management (RAS/WAS Operations & Sludge Age) 5.5 Activated Sludge Troubleshooting: Bulking, Nocardia Foaming, Rising Sludge & Pin Floc 5.6 Wastewater Characteristics, Organic and Hydraulic Loading, Diurnal Flow & Septicity 5.7 Activated Sludge Arrangements: Conventional, Complete Mix, Step Feed, Contact Stabilization, Extended Aeration, Oxidation Ditch, SBR & MBR 5.8 Aeration Systems: Blowers, Diffusers, Surface Aerators, Oxygen Transfer & Altitude Effects

6 Chapter 6: Advanced Wastewater Treatment & Solids Management

6.1 Biological Nutrient Removal: Nitrification, Denitrification & Anoxic Zones 6.2 Biological & Chemical Phosphorus Removal (EBPR & Coagulant Precipitation) 6.3 Sludge Thickening, Aerobic & Anaerobic Digestion (Mesophilic/Thermophilic) 6.4 Dewatering Equipment (Centrifuges, Belt Filter Presses) & Biosolids Standards (Reg 64) 6.5 Pond & Lagoon Operations, Trickling Filters & Rotating Biological Contactors (RBCs) 6.6 Secondary Clarification: Overflow and Solids Loading Rates, RAS Rate Setting & Clarifier Diagnostics 6.7 Tertiary Filtration, Effluent Polishing & Wastewater Disinfection with Chlorine, Dechlorination and UV 6.8 Effluent Disposal, Rapid Infiltration Basins, Colorado Water Reuse Law & Regulation 84

7 Chapter 7: Water Distribution Systems

7.1 Distribution Hydraulics, Pressure Zones, Static Head & Friction Headloss 7.2 Finished Water Storage Tanks, Standpipes, Mixing & Water Age Control 7.3 Distribution Piping, Valves (Gate, Butterfly, PRV), Hydrants & Main Flushing 7.4 Cross-Connection Control, Hazard Assessment & Backflow Preventers (RPZ, DCVA, PVB, Air Gap) 7.5 Water Main Installation, Trenching, Repair, Pressure Testing & Disinfection (AWWA C651) 7.6 Network Layout, Pressure Zones, Demand Patterns, Fire Flow & the Hydraulic Grade Line 7.7 Fire Hydrants, Dry Barrel Operation, Fire Flow Testing & Unidirectional Flushing 7.8 Booster Pump Stations, Hydropneumatic Systems, Controls & Surge Protection 7.9 Customer and Master Metering, Meter Sizing, Accuracy Testing, AMR & AMI 7.10 System Mapping, GIS, As-Builts, Operational Analysis & the AWWA Water Audit 7.11 Service Line Installation, Wet Tapping, Curb Stops & the Lead Service Line Inventory 7.12 Leak Detection, District Metered Areas, Minimum Night Flow & Pressure Management 7.13 Storage Facility Inspection, Sanitary Defects, Water Age Control, Cleaning & AWWA C652 Disinfection 7.14 Utility Locating, Colorado 811 Damage Prevention, the APWA Color Code & New Construction Inspection 7.15 Well and Wellhead Maintenance, Sanitary Condition, Rehabilitation & AWWA C654 Disinfection 7.16 Booster Chlorination, Remote Chemical Feed, Chemical Storage, Security & Supply Management 7.17 Distribution Sampling Technique, Chlorine Residual Monitoring & Nitrification Control in Chloraminated Systems

8 Chapter 8: Wastewater Collection Systems

8.1 Gravity Collection Systems: Flow Velocities, Slopes, Pipe Materials & Manholes 8.2 Wastewater Lift Stations: Wet Wells, Submersible Pumps, Level Controls & Force Mains 8.3 Inflow and Infiltration (I&I) Sources, Flow Monitoring, Smoke Testing & CCTV Inspection 8.4 Collection Maintenance: Hydraulic Jetting, Mechanical Rodding & FOG/Root Mitigation 8.5 Sanitary Sewer Overflows (SSOs): Root Causes, Containment, Reporting & Mitigation 8.6 Lift Station Electrical Devices, Level Detection, Telemetry, Gas Detection & Capacity Adjustment 8.7 Lift Station Configurations, Preventive Maintenance, Wet Well Cleaning, Troubleshooting & Emergency Bypass Pumping 8.8 Collection System Rehabilitation: CIPP, Pipe Bursting, Sliplining, Grouting, Manhole Repair & Tap Defects 8.9 Excavation, Hydro Excavation, Bedding and Haunching, Grade Control & Sewer Acceptance Testing 8.10 Collection System Flow Monitoring, Area-Velocity Metering, Weirs and Flumes & Capacity Assessment

9 Chapter 9: Pumps, Motors & Utility Mechanics

9.1 Centrifugal Pumps: Volutes, Impellers, Packing Seals & Mechanical Seals 9.2 Positive Displacement Pumps (Peristaltic, Diaphragm, Progressive Cavity) & Dosing Systems 9.3 Pump Performance Curves, System Head Curves, Cavitation & NPSH Calculations 9.4 Electric Motors (Single/Three Phase), Controls, Variable Frequency Drives (VFDs) & Power 9.5 Flow Meters (Venturi, Magnetic, Ultrasonic), Online Analyzers, PLCs & SCADA Telemetry 9.6 Air Compressors, Conveyors, Hoists and Cranes, Service Piping & Standby Power Generation 9.7 Valve Types and Duties, Air Release and Air-Vacuum Valves, Water Hammer & Surge Control

10 Chapter 10: Laboratory Analysis & Water Quality Monitoring

10.1 Regulatory Sampling Procedures, Chain of Custody, Holding Times & Preservation Techniques 10.2 Physical & Chemical Drinking Water Testing: Turbidity, pH, Alkalinity, Hardness & Chlorine (DPD) 10.3 Wastewater Laboratory Analysis: BOD5, COD, Total Suspended Solids (TSS) & Settleometry 10.4 Microbiological Testing: Total Coliform, E. coli (Colilert, Membrane Filtration) & QA/QC 10.5 Bench-Scale Jar Testing, Coagulant Optimization & Streaming Current Monitoring 10.6 Laboratory Equipment, Calibration and Verification, QA/QC Program & Certified Laboratory Requirements 10.7 Nutrient Series, Metals Sampling, Whole Effluent Toxicity & Electrode Measurements (DO, pH, ORP, H2S)

11 Chapter 11: Operator Mathematics & Applied Calculations

11.1 Core Conversions, Geometric Area, Pipe Volume & Continuous Flow Rate (MGD, GPM, cfs) 11.2 Chemical Dosage, The Standard "Pounds Formula", Active Chemical & Solution Purity 11.3 Hydraulic Retention Time (HRT), Surface Overflow Rate (SOR) & Weir Overflow Rates 11.4 Process Control Calculations: F/M Ratio, MCRT/Solids Retention Time (SRT) & Sludge Volume Index (SVI) 11.5 Distribution Pressure, Static vs Dynamic Head, Water Horsepower & Wire-to-Water Efficiency 11.6 CT Calculations: Baffling Factors, T10, Temperature and pH Corrections & Multi-Segment Compliance

12 Chapter 12: Safety, Emergency Operations & Compliance

12.1 Permit-Required Confined Space (PRCS) Entry, Atmospheric Testing (O2/LEL/H2S/CO) & Rescue 12.2 Control of Hazardous Energy: Lockout/Tagout (LOTO), Arc Flash & Electrical Safety 12.3 Chemical Safety: Chlorine Gas Handling, Ton Cylinders, Sulfur Dioxide, Ammonia & SDS/GHS 12.4 Trenching & Excavation: Soil Classification, Sloping, Shoring, Shielding & Competent Person Rules 12.5 Emergency Action Plans, Security Vulnerability, Spill Containment & CDPHE Tier 1/2/3 Public Notice 12.6 Work Zone Traffic Control, PPE, Fall Protection, Fire Extinguishers, First Aid & Bloodborne Pathogens 12.7 Standard Operating Procedures, Operating Records, Regulatory Reporting, Customer Complaints & Supervisory Duties

7.6 Network Layout, Pressure Zones, Demand Patterns, Fire Flow & the Hydraulic Grade Line

Key Takeaways Explain This Topic AI

Every 2.31 feet of elevation equals 1 psi, so 300 feet of Colorado terrain spans about 130 psi and forces a system into multiple pressure zones.

Systems maintain roughly 40 to 80 psi normally and must not fall below 20 psi at any point during peak hour or fire flow.

Regulation 100 raises a distribution system to Class 2 for 3 to 5 pressure zones and to Class 3 for 6 or more, or for normal pressures above 150 psi.

Maximum day demand runs about 1.5 to 3 times average day and peak hour about 1.5 to 2 times maximum day, with summer irrigation driving Colorado peaks.

The hydraulic grade line equals elevation plus pressure head, so at zero flow it is simply the tank water surface elevation and water always moves from higher to lower HGL.

Last updated: August 2026

Laying out a system that delivers water everywhere

The WPI Water Distribution outline's largest content area, Distribution System Components at 35 percent , opens with aiding in the design of water distribution projects, assessing water production against demand, adjusting production to meet demand, and understanding schematic diagrams and flow characteristics. Those tasks all rest on system layout.

Network configurations

Layout Description Strengths Weaknesses

Tree (branch, dead-end) Mains branch outward with no loops Cheap, simple Single feed to each customer; dead ends stagnate; a break isolates everything beyond it

Grid (looped) Mains interconnected so water reaches any point by multiple paths Redundancy, better fire flow, lower headloss, fewer stagnation zones Higher cost, more valves

Combination Grid in the core, branches at the fringe Practical compromise Fringe retains dead-end problems

Looping is a water quality decision as much as a hydraulic one. Dead ends accumulate sediment, lose chlorine residual, grow biofilm, and generate the taste, odor, and discolored water complaints that dominate customer contact. Where looping is impossible, dead ends need blow-off or flushing hydrants and a routine flushing schedule.

Valving determines how much of the system must be shut down for a repair. Good practice is enough valves that any single break isolates a short segment: commonly valves at every intersection, with a target of no more than one or two blocks and a limited number of customers out of service. Valve exercising is what keeps this true; an unexercised valve that will not close turns a one-block outage into a ten-block outage.

Pressure zones

Colorado's terrain makes pressure zones unavoidable. Every 2.31 feet of elevation change is 1 psi, so a 300-foot hillside spans about 130 psi from top to bottom. A pressure zone is an area served within an acceptable pressure band, bounded by closed valves , pressure reducing valves , booster pump stations , and its own storage .

Design targets in general practice:

Normal working pressure of roughly 40 to 80 psi at the service connection.

Minimum 20 psi at all points during peak hour and fire flow. Falling below 20 psi is the trigger for a pressure loss event and potential backsiphonage, and it is the threshold Colorado uses in Regulation 11 for pressure-related notifications and disinfection requirements after repairs.

Maximum around 100 psi , with individual pressure reducing valves at services above that.

Regulation 100's Step 2 distribution table converts these realities into classification: 3 to 5 pressure zones raises a system to at least Class 2, 6 or more raises it to Class 3, and normal operating pressure above 150 psi raises it to Class 3. A pressure zone must serve at least 15 service connections to be counted.

Zone boundaries are enforced by closed boundary valves , and the most common cause of a mysterious pressure or water quality problem is a boundary valve found open , cross-feeding two zones. Valve position records and periodic verification matter.

Demand

Average day demand (ADD) — total annual volume divided by 365.

Maximum day demand (MDD) — the highest single day, typically 1.5 to 3.0 times ADD , and higher in Colorado communities with heavy summer irrigation.

Peak hour demand (PHD) — typically 1.5 to 2 times MDD , or 3 to 6 times ADD.

Fire flow — added on top of maximum day demand for design.

Colorado adds a specific wrinkle: outdoor irrigation dominates summer peaks , so a mountain or Front Range system may deliver three times as much water in July as in January, and the distribution system, storage, and source capacity must all be sized on maximum day plus fire flow, not on average day. Watering restrictions are a demand-management tool that operators help enforce, and WPI lists "assess water production, including water restrictions and demand" as a job task.

Fire flow

Fire flow requirements come from the fire authority and the applicable fire code, based on building construction, area, occupancy, and sprinklering. Typical needed fire flows run from about 500 to 1,000 gpm for single-family residential up to several thousand gpm for commercial and industrial areas, delivered for a specified duration of 1 to 4 hours while maintaining at least 20 psi .

Fire flow is usually the controlling design criterion for main size in residential areas: domestic demand alone might be met by a 4-inch main, but fire flow requires 6- or 8-inch minimum, with 8-inch and larger on grid mains. That oversizing has a water quality cost — long detention time and low velocity in mains sized for a fire that may never occur — which is precisely why flushing programs exist.

Reading a system schematic

WPI lists "understand schematic diagrams" and "interpret plans, maps, and system standard specifications" as job tasks. A distribution schematic shows sources, treatment, storage, pump stations, pressure reducing stations, zone boundaries, and main sizes, with hydraulic grade elevations.

The single most useful concept for reading one is the hydraulic grade line (HGL) . The HGL at any point is the elevation to which water would rise in an open tube at that point — that is, elevation plus pressure head. Key consequences:

In a tank-fed zone with no flow, the HGL is the water surface elevation in the tank , and pressure at any point is simply (tank water surface elevation minus point elevation) divided by 2.31.

When water flows, the HGL slopes downward in the direction of flow, and the slope is the friction loss per unit length.

Water flows from higher HGL to lower HGL , regardless of ground elevation. This is why a customer at a high elevation can have good pressure while a customer lower down has poor pressure, if they are on different zones.

Worked example. A storage tank has a water surface elevation of 5,480 ft. A service connection sits at ground elevation 5,340 ft. With no flow, the static pressure at that service is:

(5,480 − 5,340) ÷ 2.31 = 140 ÷ 2.31 = 60.6 psi

If, during peak hour, friction losses between the tank and that service total 18 feet, the HGL at the service drops to 5,462 ft and the pressure becomes (5,462 − 5,340) ÷ 2.31 = 52.8 psi .

Matching production to demand

WPI lists "adjust the water production to meet the demand (start pumps, adjust flow valves)" and "perform operational analysis." In practice the distribution system is controlled by storage level , not by instantaneous demand:

Storage floats on the system, absorbing the difference between steady production and variable demand.

Pumps and treatment output are staged on tank level setpoints — start at a low level, stop at a high level, with a deadband to prevent short cycling.

Overnight, when demand is low and electricity is cheaper, the system fills storage. During the morning and evening peaks, storage supplements production.

During a fire, storage supplies the surge that no plant could produce.

The operator's daily analysis is straightforward: compare production, consumption, and tank level trends. If tanks are not recovering overnight, either production is inadequate, a large leak has developed, or a boundary valve is cross-feeding another zone. If tanks fill too fast and overflow, the level control or the setpoint is wrong. WPI's phrasing — "analyze operational data, meet performance objectives, document operating conditions" — describes exactly this loop.