7.5 Water Main Installation, Trenching, Repair, Pressure Testing & Disinfection (AWWA C651)

Colorado Water/Wastewater Operator Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: State Laws, Regulations & CCWP Certification

1.1 CDPHE CCWP Program & Regulatory Framework (Regulation 100 / 5 CCR 1003-2) 1.2 Facility Classification & Operator in Responsible Charge (ORC) Requirements 1.3 Certification Levels, Education, Experience & Exam Eligibility (Class D-A, Grade 1-4, Class S/T) 1.4 License Renewal, Training Units (TUs) & Mandatory Regulatory Training 1.5 Colorado Primary Drinking Water Regulations (Regulation 11) & Compliance 1.6 Colorado Discharge Permit System (Regulations 61/62), DMRs & Biosolids Reporting

2 Chapter 2: Source Water & Drinking Water Treatment Processes

2.1 Raw Water Sources, High-Altitude Characteristics & Reservoir Quality 2.2 Coagulation Chemistry, Rapid Mixing & Chemical Dosing (Alum, Ferric, Polymers) 2.3 Flocculation & Sedimentation Basin Design, Operation & Settling Zones 2.4 Granular Media Filtration, Backwash Procedures & Turbidity Standards 2.5 Advanced Treatment: Membranes, Softening, GAC/PAC Adsorption & Aeration 2.6 Groundwater Sources, Well Hydraulics, Static and Pumping Levels & Specific Capacity 2.7 Source Water Characteristics, Contaminant Categories & Watershed Protection Plans 2.8 Pretreatment: Presedimentation, Aeration, Algae Control & Taste-and-Odor Management 2.9 Direct, In-Line, Pressure, Cartridge & Diatomaceous Earth Filtration 2.10 Lime-Soda Softening, Ion Exchange & Water Stabilization 2.11 Water Treatment Plant Residuals: Lagoons, Drying Beds, Land Application & Recycle

3 Chapter 3: Disinfection & Chemical Addition

3.1 Chlorine Chemistry: Hypochlorous Acid, Free/Combined Residual & Breakpoint Chlorination 3.2 Disinfection Kinetics, Baffle Factors, T10 & CT Compliance Calculations 3.3 Disinfection Byproducts (TTHMs, HAA5s) & Stage 1/2 DBP Rules 3.4 Alternative Disinfection: Chloramination, Ultraviolet (UV) Light & Chlorine Dioxide 3.5 Corrosion Control, Lead & Copper Rule Revisions (LCRR) & Fluoridation Practices

4 Chapter 4: Water Treatment Plant Equipment, Instrumentation & Maintenance

4.1 Raw Water Intakes, Screening Equipment & Raw Water Pumping 4.2 Chemical Feed Equipment: Feeders, Day Tanks, Carrier Water & Feed-Rate Calibration 4.3 Chlorination Equipment: Gas Systems, Vacuum Regulators, Hypochlorite Storage & Onsite Generation 4.4 Filter Underdrains, Support Gravel, Surface Wash, Air Scour & Filter-to-Waste 4.5 Plant Process Control, SCADA and PLC Systems, Alarm Management & Records of Operation 4.6 Preventive, Corrective and Predictive Maintenance, Work Orders & Asset Management

5 Chapter 5: Wastewater Treatment Principles & Biological Processes

5.1 Preliminary Treatment: Bar Screens, Shredders, Grit Chambers & Flow Equalization 5.2 Primary Clarification, Solids Separation & Scum Removal Mechanics 5.3 Activated Sludge Fundamentals: Aerobic Microbiology, DO Control & Biomass Growth 5.4 Return & Waste Activated Sludge Management (RAS/WAS Operations & Sludge Age) 5.5 Activated Sludge Troubleshooting: Bulking, Nocardia Foaming, Rising Sludge & Pin Floc 5.6 Wastewater Characteristics, Organic and Hydraulic Loading, Diurnal Flow & Septicity 5.7 Activated Sludge Arrangements: Conventional, Complete Mix, Step Feed, Contact Stabilization, Extended Aeration, Oxidation Ditch, SBR & MBR 5.8 Aeration Systems: Blowers, Diffusers, Surface Aerators, Oxygen Transfer & Altitude Effects

6 Chapter 6: Advanced Wastewater Treatment & Solids Management

6.1 Biological Nutrient Removal: Nitrification, Denitrification & Anoxic Zones 6.2 Biological & Chemical Phosphorus Removal (EBPR & Coagulant Precipitation) 6.3 Sludge Thickening, Aerobic & Anaerobic Digestion (Mesophilic/Thermophilic) 6.4 Dewatering Equipment (Centrifuges, Belt Filter Presses) & Biosolids Standards (Reg 64) 6.5 Pond & Lagoon Operations, Trickling Filters & Rotating Biological Contactors (RBCs) 6.6 Secondary Clarification: Overflow and Solids Loading Rates, RAS Rate Setting & Clarifier Diagnostics 6.7 Tertiary Filtration, Effluent Polishing & Wastewater Disinfection with Chlorine, Dechlorination and UV 6.8 Effluent Disposal, Rapid Infiltration Basins, Colorado Water Reuse Law & Regulation 84

7 Chapter 7: Water Distribution Systems

7.1 Distribution Hydraulics, Pressure Zones, Static Head & Friction Headloss 7.2 Finished Water Storage Tanks, Standpipes, Mixing & Water Age Control 7.3 Distribution Piping, Valves (Gate, Butterfly, PRV), Hydrants & Main Flushing 7.4 Cross-Connection Control, Hazard Assessment & Backflow Preventers (RPZ, DCVA, PVB, Air Gap) 7.5 Water Main Installation, Trenching, Repair, Pressure Testing & Disinfection (AWWA C651) 7.6 Network Layout, Pressure Zones, Demand Patterns, Fire Flow & the Hydraulic Grade Line 7.7 Fire Hydrants, Dry Barrel Operation, Fire Flow Testing & Unidirectional Flushing 7.8 Booster Pump Stations, Hydropneumatic Systems, Controls & Surge Protection 7.9 Customer and Master Metering, Meter Sizing, Accuracy Testing, AMR & AMI 7.10 System Mapping, GIS, As-Builts, Operational Analysis & the AWWA Water Audit 7.11 Service Line Installation, Wet Tapping, Curb Stops & the Lead Service Line Inventory 7.12 Leak Detection, District Metered Areas, Minimum Night Flow & Pressure Management 7.13 Storage Facility Inspection, Sanitary Defects, Water Age Control, Cleaning & AWWA C652 Disinfection 7.14 Utility Locating, Colorado 811 Damage Prevention, the APWA Color Code & New Construction Inspection 7.15 Well and Wellhead Maintenance, Sanitary Condition, Rehabilitation & AWWA C654 Disinfection 7.16 Booster Chlorination, Remote Chemical Feed, Chemical Storage, Security & Supply Management 7.17 Distribution Sampling Technique, Chlorine Residual Monitoring & Nitrification Control in Chloraminated Systems

8 Chapter 8: Wastewater Collection Systems

8.1 Gravity Collection Systems: Flow Velocities, Slopes, Pipe Materials & Manholes 8.2 Wastewater Lift Stations: Wet Wells, Submersible Pumps, Level Controls & Force Mains 8.3 Inflow and Infiltration (I&I) Sources, Flow Monitoring, Smoke Testing & CCTV Inspection 8.4 Collection Maintenance: Hydraulic Jetting, Mechanical Rodding & FOG/Root Mitigation 8.5 Sanitary Sewer Overflows (SSOs): Root Causes, Containment, Reporting & Mitigation 8.6 Lift Station Electrical Devices, Level Detection, Telemetry, Gas Detection & Capacity Adjustment 8.7 Lift Station Configurations, Preventive Maintenance, Wet Well Cleaning, Troubleshooting & Emergency Bypass Pumping 8.8 Collection System Rehabilitation: CIPP, Pipe Bursting, Sliplining, Grouting, Manhole Repair & Tap Defects 8.9 Excavation, Hydro Excavation, Bedding and Haunching, Grade Control & Sewer Acceptance Testing 8.10 Collection System Flow Monitoring, Area-Velocity Metering, Weirs and Flumes & Capacity Assessment

9 Chapter 9: Pumps, Motors & Utility Mechanics

9.1 Centrifugal Pumps: Volutes, Impellers, Packing Seals & Mechanical Seals 9.2 Positive Displacement Pumps (Peristaltic, Diaphragm, Progressive Cavity) & Dosing Systems 9.3 Pump Performance Curves, System Head Curves, Cavitation & NPSH Calculations 9.4 Electric Motors (Single/Three Phase), Controls, Variable Frequency Drives (VFDs) & Power 9.5 Flow Meters (Venturi, Magnetic, Ultrasonic), Online Analyzers, PLCs & SCADA Telemetry 9.6 Air Compressors, Conveyors, Hoists and Cranes, Service Piping & Standby Power Generation 9.7 Valve Types and Duties, Air Release and Air-Vacuum Valves, Water Hammer & Surge Control

10 Chapter 10: Laboratory Analysis & Water Quality Monitoring

10.1 Regulatory Sampling Procedures, Chain of Custody, Holding Times & Preservation Techniques 10.2 Physical & Chemical Drinking Water Testing: Turbidity, pH, Alkalinity, Hardness & Chlorine (DPD) 10.3 Wastewater Laboratory Analysis: BOD5, COD, Total Suspended Solids (TSS) & Settleometry 10.4 Microbiological Testing: Total Coliform, E. coli (Colilert, Membrane Filtration) & QA/QC 10.5 Bench-Scale Jar Testing, Coagulant Optimization & Streaming Current Monitoring 10.6 Laboratory Equipment, Calibration and Verification, QA/QC Program & Certified Laboratory Requirements 10.7 Nutrient Series, Metals Sampling, Whole Effluent Toxicity & Electrode Measurements (DO, pH, ORP, H2S)

11 Chapter 11: Operator Mathematics & Applied Calculations

11.1 Core Conversions, Geometric Area, Pipe Volume & Continuous Flow Rate (MGD, GPM, cfs) 11.2 Chemical Dosage, The Standard "Pounds Formula", Active Chemical & Solution Purity 11.3 Hydraulic Retention Time (HRT), Surface Overflow Rate (SOR) & Weir Overflow Rates 11.4 Process Control Calculations: F/M Ratio, MCRT/Solids Retention Time (SRT) & Sludge Volume Index (SVI) 11.5 Distribution Pressure, Static vs Dynamic Head, Water Horsepower & Wire-to-Water Efficiency 11.6 CT Calculations: Baffling Factors, T10, Temperature and pH Corrections & Multi-Segment Compliance

12 Chapter 12: Safety, Emergency Operations & Compliance

12.1 Permit-Required Confined Space (PRCS) Entry, Atmospheric Testing (O2/LEL/H2S/CO) & Rescue 12.2 Control of Hazardous Energy: Lockout/Tagout (LOTO), Arc Flash & Electrical Safety 12.3 Chemical Safety: Chlorine Gas Handling, Ton Cylinders, Sulfur Dioxide, Ammonia & SDS/GHS 12.4 Trenching & Excavation: Soil Classification, Sloping, Shoring, Shielding & Competent Person Rules 12.5 Emergency Action Plans, Security Vulnerability, Spill Containment & CDPHE Tier 1/2/3 Public Notice 12.6 Work Zone Traffic Control, PPE, Fall Protection, Fire Extinguishers, First Aid & Bloodborne Pathogens 12.7 Standard Operating Procedures, Operating Records, Regulatory Reporting, Customer Complaints & Supervisory Duties

7.5 Water Main Installation, Trenching, Repair, Pressure Testing & Disinfection (AWWA C651)

Key Takeaways Explain This Topic AI

Colorado design criteria require a minimum 10-foot horizontal separation and an 18-inch vertical separation (water main above sewer) between potable water lines and sanitary or storm sewers.

Hydraulic thrust blocks must be poured against solid, undisturbed trench earth at all directional changes, tees, reducers, and dead-end plugs to prevent pipe joint separation.

Hydrostatic pressure testing of newly laid water mains must be conducted at a minimum of 150 psi or 1.5 times working pressure for at least 2 hours without exceeding allowable leakage limits.

AWWA C651 specifies three primary disinfection methods: Continuous Feed (25 mg/L with >= 10 mg/L residual after 24 hrs), Slug Method (100 mg/L for 3 hrs), and Tablet/Caulking/Swab Method for emergency repairs (200 mg/L).

Newly disinfected mains cannot be placed into service until super-chlorinated water is dechlorinated, flushed, and two consecutive sets of negative coliform samples are collected 24 hours apart.

Last updated: August 2026

Water Main Installation, Trenching, Repair, Pressure Testing & Disinfection (AWWA C651)

Water distribution piping represents the largest capital asset of any drinking water utility. Installing new water mains and repairing broken infrastructure requires rigorous adherence to civil engineering specifications, trench safety mandates, hydrostatic testing protocols, and microbiological disinfection standards to guarantee that water delivered to the public remains pure and uncompromised.

1. Trench Excavation, Bedding & Pipe Laying

Water main installation requires proper trench preparation and structural pipe embedment:

OSHA Excavation Safety: Under OSHA 29 CFR 1926 Subpart P, all trenches 5 feet or deeper must utilize protective systems (sloping, benching, trench shields/boxes, or hydraulic shoring). A designated Competent Person must inspect the excavation daily and after every rain event. Ladders or ramps must be spaced within 25 feet of lateral travel for workers in trenches 4 feet or deeper.

Pipe Bedding & Embedment (Class B Standard): Pipe must be laid on a uniform, compacted bedding cradle (minimum 4 to 6 inches of crushed stone or granular sand). Backfill material must be carefully placed and shovel-sliced into the haunch area beneath the pipe curvature, then compacted in 6-inch lifts up to at least 12 inches above the pipe crown to prevent point loading and ovality distortion.

Pipe Jointing Mechanics: Bell and spigot ends must be wire-brushed clean. Approved NSF-61 food-grade lubricant is applied to the rubber gasket and spigot bevel. Pipe is pushed home until the insertion line matches the bell face. Over-inserting or exceeding allowable angular joint deflection ( > 3 ∘ to 5 ∘ > 3^\circ \text{ to } 5^\circ > 3 ∘ to 5 ∘ ) damages the internal gasket seal. +-------------------------------------------------------------------------+

  • | PIPE EMBEDMENT CROSS-SECTION |
  • +-------------------------------------------------------------------------+
  • | Final Backfill: Native soil compacted in lifts to grade. |
  • | --------------------------------------------------------------------- |
  • | Initial Backfill: Granular material 12 inches above pipe crown. |
  • | Haunching: Compacted crushed stone supporting lower pipe curvature.|
  • | Bedding: 4 to 6 inches compacted granular cradle on trench floor. |
  • +-------------------------------------------------------------------------+
  • 2. Hydraulic Thrust Restraint: Thrust Blocks & Restrained Joints

When water flows under pressure through a closed conduit, internal hydrostatic pressure and momentum changes exert powerful thrust forces at any point where the pipeline changes direction, changes cross-sectional area, or terminates. T = 2 P A sin ⁡ ( θ / 2 ) T = 2 P A \sin(\theta / 2) T = 2 P A sin ( θ /2 )

Where T T T is thrust force (lbs), P P P is internal pressure (psi), A A A is cross-sectional area (sq in), and θ \theta θ is the bend angle.

Thrust Locations & Restraint Methods

Thrust forces occur at: (1) Bends and elbows ( 90 ∘ , 45 ∘ , 22.5 ∘ , 11.25 ∘ 90^\circ, 45^\circ, 22.5^\circ, 11.25^\circ 9 0 ∘ , 4 5 ∘ , 22. 5 ∘ , 11.2 5 ∘ ), (2) Reducers, (3) Tees and crosses, (4) In-line gate valves, and (5) Dead-end caps and plugs.

Concrete Thrust Blocks: Mass concrete ( ≥ 2 , 000 to 3 , 000 psi \ge 2,000\text{ to }3,000\text{ psi} ≥ 2 , 000 to 3 , 000 psi compressive strength) poured between the pipe fitting and the undisturbed virgin trench wall . Concrete must never encase mechanical joint bolts, valve operating nuts, or weep holes.

Restrained Joint Systems: Mechanical joint restraint glands (e.g., Megalug wedging rings) or factory-welded locking gaskets that lock adjacent pipe joints together, transmitting the thrust force into soil skin friction along a calculated length of pipe.

3. Colorado Sanitary Separation Distance Mandates

To prevent contamination of potable water lines by leaking sanitary or storm sewers, the CDPHE Water Quality Control Division enforces strict minimum horizontal and vertical separation distances: +-------------------------------------------------------------------------+

  • | COLORADO SANITARY SEPARATION CRITERIA |
  • +-------------------------------------------------------------------------+
  • | 1. Horizontal Separation: |
  • | - Minimum 10 FEET horizontal clear distance between the outside of |
  • | the potable water main and the outside of any sewer line. |
  • | |
  • | 2. Vertical Crossing Separation: |
  • | - Water main must cross ABOVE the sewer line whenever possible. |
  • | - Minimum 18 INCHES vertical clearance between the bottom of the |
  • | water main and the top of the sewer line. |
  • | |
  • | 3. Substandard Crossing Protections (When 18 in / 10 ft is impossible): |
  • | - Construct the sewer line using pressure-rated pipe (C900 PVC or |
  • | Ductile Iron) pressure-tested to 150 psi. |
  • | - Center a full 20-foot joint of water pipe directly over the sewer |
  • | crossing so that joints are as far from the sewer as possible. |
  • | - Encase either line in a continuous steel or concrete casing pipe |
  • | extending at least 10 feet on each side of the crossing. |
  • +-------------------------------------------------------------------------+

Loading diagram... Water Main Commissioning: Pressure Testing, Disinfection & Coliform Clearance

4. Hydrostatic Pressure and Leakage Testing (AWWA C600 / C605)

Before disinfection and backfilling completion, newly installed water mains must pass a rigorous Hydrostatic Pressure and Leakage Test :

Test Pressure: At least 1.5 times the anticipated maximum working pressure at the lowest point of the pipeline profile, or 150 psi , whichever is greater.

Test Duration: Minimum continuous duration of 2 hours (120 minutes) .

Procedure: The pipeline is slowly filled with potable water, venting all entrapped air through high-point taps. A hydrostatic pressure pump elevates pressure to the test setpoint. The volume of make-up water required to maintain pressure within ± 5 psi \pm 5\text{ psi} ± 5 psi of the test pressure is measured.

AWWA Allowable Leakage Formula

The maximum allowable make-up water leakage is calculated using the AWWA standard formula: Q = S × D × P 148 , 000 Q = \frac{S \times D \times \sqrt{P}}{148,000} Q = 148 , 000 S × D × P ​ ​

Where:

  • Q Q Q = Maximum allowable leakage (gallons per hour, gph)
  • S S S = Length of pipeline tested (feet)
  • D D D = Nominal internal pipe diameter (inches)
  • P P P = Average test pressure during the hydrostatic test (psig)
  • 5. Water Main Disinfection Protocols (AWWA Standard C651)

Newly laid water mains, repaired mains, and re-lined pipes must be disinfected in strict accordance with AWWA Standard C651 and CDPHE rules:

1. Continuous-Feed Method (Standard Method for New Mains)

Procedure: Water entering the main is continuously dosed with chlorine solution (via chemical feed pump through a corporation stop) as the main is filled.

Initial Dose: Dosed to maintain a minimum of 25 mg/L 25\text{ mg/L} 25 mg/L free available chlorine throughout the entire length of the pipe.

Contact Retention Time: Retained undisturbed in the pipe for at least 24 hours .

Clearance Residual: After 24 hours, the free chlorine residual must be at least 10 mg/L 10\text{ mg/L} 10 mg/L at every sampling point. If residual is < 10 mg/L < 10\text{ mg/L} < 10 mg/L , the main must be re-chlorinated.

2. Slug Method (Large Transmission Mains)

Procedure: A concentrated slug of chlorinated water is moved slowly through the pipeline so that all interior surfaces contact the slug.

Initial Dose: Minimum chlorine concentration of 100 mg/L 100\text{ mg/L} 100 mg/L free chlorine .

Contact Retention Time: Every section of pipe must contact the slug for at least 3 hours , maintaining at least 25 mg/L 25\text{ mg/L} 25 mg/L residual at the end of the contact period.

3. Spray / Swab Method (Emergency Repairs & Cut-Ins)

Procedure: When repairing an active main break where trench water is kept away from pipe interiors, replacement pipe spools, couplings, and tapping sleeves must be directly sprayed or swabbed with a concentrated 200 mg/L 200\text{ mg/L} 200 mg/L to 1 , 000 mg/L 1,000\text{ mg/L} 1 , 000 mg/L (1% sodium hypochlorite) chlorine solution immediately prior to installation.

  • 6. Environmental Dechlorination & Bacteriological Clearance Sampling
  • Dechlorination

Highly chlorinated water used for main disinfection ( 10 to 100 + mg/L 10\text{ to }100+\text{ mg/L} 10 to 100 + mg/L ) cannot be discharged to storm sewers or open terrain. The water must be treated through a chemical neutralization diffuser using sodium thiosulfate ( Na 2 S 2 O 3 \text{Na}_2\text{S}_2\text{O}_3 Na 2 ​ S 2 ​ O 3 ​ ), sodium bisulfite ( NaHSO 3 \text{NaHSO}_3 NaHSO 3 ​ ), or ascorbic acid (Vitamin C) until the chlorine residual is reduced to 0.00 mg/L 0.00\text{ mg/L} 0.00 mg/L before entering the environment.

Bacteriological Clearance Sampling

After flushing out super-chlorinated water and refilling the main with standard treated water containing a normal distribution residual ( 0.2 to 1.5 mg/L 0.2\text{ to }1.5\text{ mg/L} 0.2 to 1.5 mg/L ):

Sample Collection Protocol: Dedicated sampling taps (copper whips) must be used. Fire hydrants and garden hoses are strictly prohibited for regulatory coliform clearance sampling.

Sampling Schedule: Under standard CDPHE and AWWA C651 rules, two (2) consecutive sets of bacteriological samples collected at least 24 hours apart (or two sets collected 16 hours apart after standing under pressure) must be analyzed for Total Coliform and E. coli .

Passing Standard: Both sets must show Total Coliform ABSENT (Negative) . If any sample tests coliform positive, the main must be re-flushed, re-sampled, or re-chlorinated before placing into service.

  • 7. Worked Testing & Disinfection Calculations
  • Worked Example 6.5.1: Hydrostatic Allowable Leakage Calculation

A contractor installs 2,000 feet of 12-inch ductile iron water main . The line undergoes a 2-hour hydrostatic pressure test at an average pressure of 150 psi . Calculate the maximum allowable leakage in gallons for the entire 2-hour test duration.

Step 1: Calculate allowable hourly leakage ( Q Q Q in gph): Q = S × D × P 148 , 000 = 2 , 000 ft × 12 in × 150 psi 148 , 000 Q = \frac{S \times D \times \sqrt{P}}{148,000} = \frac{2,000\text{ ft} \times 12\text{ in} \times \sqrt{150\text{ psi}}}{148,000} Q = 148 , 000 S × D × P ​ ​ = 148 , 000 2 , 000 ft × 12 in × 150 psi ​ ​ 150 = 12.2474 \sqrt{150} = 12.2474 150 ​ = 12.2474 Q = 2 , 000 × 12 × 12.2474 148 , 000 = 293 , 938.7 148 , 000 = 1.986 gallons per hour (gph) Q = \frac{2,000 \times 12 \times 12.2474}{148,000} = \frac{293,938.7}{148,000} = 1.986\text{ gallons per hour (gph)} Q = 148 , 000 2 , 000 × 12 × 12.2474 ​ = 148 , 000 293 , 938.7 ​ = 1.986 gallons per hour (gph)

Step 2: Calculate total allowable leakage for the 2-hour test: Total 2-Hr Allowable Leakage = 1.986 gph × 2.0 hours = 3.97 gallons \text{Total 2-Hr Allowable Leakage} = 1.986\text{ gph} \times 2.0\text{ hours} = 3.97\text{ gallons} Total 2-Hr Allowable Leakage = 1.986 gph × 2.0 hours = 3.97 gallons

Conclusion: If the make-up water pumped into the main over 2 hours is ≤ 3.97 gallons \le 3.97\text{ gallons} ≤ 3.97 gallons , the pipeline passes the hydrostatic pressure test.

Worked Example 6.5.2: Disinfection Chemical Feed Calculation

A new 1,500-foot-long, 16-inch diameter water main must be disinfected using the Continuous-Feed Method with an initial free chlorine dose of 25 mg/L . Calculate the volume of water in the pipe and the pounds of 100% pure chlorine gas required to treat the pipeline volume.

Step 1: Calculate pipe volume in gallons ( V = 0.0408 × D 2 × L V = 0.0408 \times D^2 \times L V = 0.0408 × D 2 × L ): V = 0.0408 × ( 16 ) 2 × 1 , 500 = 0.0408 × 256 × 1 , 500 = 15 , 667.2 gallons V = 0.0408 \times (16)^2 \times 1,500 = 0.0408 \times 256 \times 1,500 = 15,667.2\text{ gallons} V = 0.0408 × ( 16 ) 2 × 1 , 500 = 0.0408 × 256 × 1 , 500 = 15 , 667.2 gallons Convert to MGD: 15 , 667.2 gal 1 , 000 , 000 = 0.015667 MG \text{Convert to MGD: } \frac{15,667.2\text{ gal}}{1,000,000} = 0.015667\text{ MG} Convert to MGD: 1 , 000 , 000 15 , 667.2 gal ​ = 0.015667 MG

Step 2: Calculate chlorine required using the standard Pounds Formula: Chemical (lbs) = Volume (MG) × Dose (mg/L) × 8.34 lb/gal \text{Chemical (lbs)} = \text{Volume (MG)} \times \text{Dose (mg/L)} \times 8.34\text{ lb/gal} Chemical (lbs) = Volume (MG) × Dose (mg/L) × 8.34 lb/gal Chemical (lbs) = 0.015667 MG × 25 mg/L × 8.34 lb/gal = 3.27 lbs of pure Cl 2 \text{Chemical (lbs)} = 0.015667\text{ MG} \times 25\text{ mg/L} \times 8.34\text{ lb/gal} = 3.27\text{ lbs of pure } \text{Cl}_2 Chemical (lbs) = 0.015667 MG × 25 mg/L × 8.34 lb/gal = 3.27 lbs of pure Cl 2 ​

Conclusion: The operator must inject 3.27 lbs of pure chlorine gas (or approximately 26.2 lbs of 12.5% sodium hypochlorite solution) as the pipeline is filled.