9.2 Earned Value Management (EVM) & Project Control

CPA Program — Strategic Management Accounting Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Role of Strategic Management Accounting & Value Creation

1.1 Evolution & Role of the Strategic Management Accountant 1.2 Defining & Creating Multi-Stakeholder Value 1.3 The Strategic Management Process & Strategy Formation

2 Chapter 2: Strategic Analysis, Environmental Scanning & Professional Ethics

2.1 External Environmental Scanning: PESTEL & Porter's Five Forces 2.2 Internal Capability Analysis, VRIO & Core Competencies 2.3 Professional Ethics, Governance & Risk in Strategic Management Accounting

3 Chapter 3: Information Architecture, Systems & Behavioral Biases

3.1 Data, Information & Knowledge Architecture 3.2 Management Information Systems, ERP & Digital Technologies 3.3 Decision-Making Needs & Cognitive Biases 3.4 Stakeholder Communication, Sources & Information Integration 3.5 Assessing Information-System Deficiencies & Replacement Needs 3.6 Evaluating, Implementing & Reviewing Information Solutions

4 Chapter 4: Relevant Information, Tactical Decisions & Limiting Factors

4.1 Relevant Cost Analysis & Differential Decision-Making 4.2 Short-Term Tactical Decision Scenarios 4.3 Limiting Factors, Theory of Constraints & Throughput Accounting

5 Chapter 5: Strategic Planning, Master Budgets & Budgetary Control

5.1 Master Budget Architecture & Process 5.2 Financial Budgets & Cash Flow Forecasting 5.3 Budgetary Control & Flexible Budgeting 5.4 Service, Not-for-Profit & Departmental Budgets

6 Chapter 6: Modern Budgeting Methodologies & Behavioral Dynamics

6.1 Alternative Budgeting Systems: ZBB, ABB & Rolling Budgets 6.2 Beyond Budgeting Principles & Dynamic Forecasting 6.3 Behavioral Dimensions of Budgeting

7 Chapter 7: Standard Costing & Comprehensive Variance Analysis

7.1 Standard Cost Setting & Direct Cost Variances 7.2 Overhead Variance Analysis 7.3 Sales Variances: Price, Volume, Mix & Quantity 7.4 Planning vs Operational Variances & Variance Investigation

8 Chapter 8: Project Selection, Governance & Financial Appraisal

8.1 Project Fundamentals, Governance & Life Cycle 8.2 Project Selection & Strategic Alignment 8.3 Capital Investment Appraisal Techniques 8.4 Project Structures, Teams, Supplier Contracts & Probity

9 Chapter 9: Project Scheduling, Earned Value Management & Risk

9.1 Project Scheduling, Network Analysis & Resource Management 9.2 Earned Value Management (EVM) & Project Control 9.3 Project Risk Management, Methodologies & Post-Completion Review 9.4 Completion Decisions, Acceptance, Financial Closure & Knowledge

10 Chapter 10: Performance Management Systems & Responsibility Centers

10.1 Management Control Systems & Simons' Levers of Control 10.2 Responsibility Accounting & Organizational Design 10.3 Designing Effective Key Performance Indicators (KPIs)

11 Chapter 11: Divisional Financial Performance & Transfer Pricing

11.1 Return on Investment (ROI) & Residual Income (RI) 11.2 Economic Value Added (EVA) 11.3 Transfer Pricing in Decentralized Organizations

12 Chapter 12: Strategic Performance Frameworks & Executive Incentives

12.1 The Balanced Scorecard Framework 12.2 Strategy Maps & Causal Linkages 12.3 Multidimensional Performance Frameworks 12.4 Executive Compensation, Incentive Systems & Agency Theory

13 Chapter 13: Strategic Cost Management, Value Chains & Activity-Based Costing

13.1 Strategic Cost Management & Value Chain Analysis 13.2 Activity-Based Costing (ABC) Mechanics 13.3 Activity-Based Management (ABM) & Time-Driven ABC

14 Chapter 14: Strategic Pricing, Target Costing & Life-Cycle Costing

14.1 Strategic Pricing Decisions & Policies 14.2 Target Costing & Kaizen Costing 14.3 Life-Cycle Costing & Environmental Management Accounting

15 Chapter 15: Customer Profitability, Lean Supply Chains & Quality Costs

15.1 Customer Profitability Analysis & Cost-to-Serve 15.2 Supply Chain Management & Lean Operations 15.3 Cost of Quality (COQ) Framework & Total Quality Management 15.4 Outsourcing, Offshoring & Downsizing Decisions

9.2 Earned Value Management (EVM) & Project Control

Key Takeaways Explain This Topic AI

Earned Value Management (EVM) integrates project scope, calendar schedule, and actual cost metrics to evaluate genuine operational progress against an integrated baseline.

Variances measure dollar differentials: Schedule Variance (SV = EV - PV) indicates timing alignment, while Cost Variance (CV = EV - AC) indicates budgetary adherence.

Efficiency ratios evaluate performance rates: Schedule Performance Index (SPI = EV / PV) and Cost Performance Index (CPI = EV / AC) signal project efficiency, with values below 1.0 indicating schedule delays or budget overruns.

Forecasting metrics such as Estimate at Completion (EAC) project final costs under varying operational assumptions, while the To-Complete Performance Index (TCPI) determines the efficiency required to achieve target budgets.

Last updated: October 2026

Earned Value Management (EVM) & Project Control

Traditional financial reporting monitors capital expenditure by comparing actual costs incurred against phased financial budget disbursements. In strategic management accounting, this conventional approach is recognized as fundamentally defective: comparing actual expenditure solely against budgeted expenditure creates a dangerous blind spot regarding physical work delivered.

For example, if an enterprise has spent $600,000 against a Year-to-Date budget of $800,000, a traditional accounting report displays an apparently "favorable" variance of $200,000. However, if the project has accomplished only $300,000 worth of actual deliverables, the project is severely delayed and experiencing massive cost overruns. Earned Value Management (EVM) resolves this distortion by integrating scope, schedule, and cost into a unified Performance Measurement Baseline (PMB) .

The Core EVM Building Blocks

Percent-complete figures must reflect the approved budget-weighted scope, rather than an unweighted count of tasks. Apply a consistent earned-value measurement method and recognise incurred costs, including accruals, so uninvoiced work does not falsely improve CPI.

All EVM performance diagnostics originate from three foundational data points and the baseline budget:

Budget at Completion ( B A C BAC B A C ): The total approved baseline budget allocated for completing the entire project scope.

Planned Value ( P V PV P V ) / Budgeted Cost of Work Scheduled ( B C W S BCWS BC W S ): The authorized budget allocated to scheduled work expected to be completed up to a specific measurement date. P V = Planned % Complete × B A C PV = \text{Planned \% Complete} \times BAC P V = Planned % Complete × B A C

Earned Value ( E V EV E V ) / Budgeted Cost of Work Performed ( B C W P BCWP BC W P ): The budgeted value of work physically and verifiable completed up to the measurement date. E V = Actual % Complete × B A C EV = \text{Actual \% Complete} \times BAC E V = Actual % Complete × B A C

Actual Cost ( A C AC A C ) / Actual Cost of Work Performed ( A C W P ACWP A C W P ): The total direct and allocated costs incurred and recorded on the general ledger in executing the work completed up to the measurement date.

Rules for Crediting Earned Value

To eliminate managerial subjectivity, organizations establish formal rules of credit to compute E V EV E V :

0/100 Rule: No earned value is credited until the work package is 100% complete and verified (appropriate for short-duration tasks under 80 hours).

50/50 Rule: 50% of the budget is credited upon task commencement, and the remaining 50% is credited upon formal completion.

Milestone Gates: Earned value is recognized only upon reaching verified, objective intermediate deliverables (e.g., 20% on design freeze, 50% on prototype assembly, 100% on safety certification).

Variance Analysis: Schedule Variance and Cost Variance

Variances in EVM express performance deviations in monetary units:

Schedule Variance ( S V SV S V ) S V = E V − P V SV = EV - PV S V = E V − P V

S V > 0 SV > 0 S V > 0 (Positive): Favorable; the project has completed more work than scheduled (ahead of schedule).

S V < 0 SV < 0 S V < 0 (Negative): Unfavorable; the project has delivered less work than scheduled (behind schedule).

S V = 0 SV = 0 S V = 0 : Exactly on schedule.

Note

The End-of-Project SV Paradox: Because S V SV S V is measured in dollars rather than calendar units, as a project reaches 100% physical completion, E V EV E V inevitably equals B A C BAC B A C , and P V PV P V equals B A C BAC B A C . Consequently, S V SV S V returns to $0 at project conclusion—even if the project finished two years late! Management accountants must supplement S V SV S V with network path analysis.

Cost Variance ( C V CV C V ) C V = E V − A C CV = EV - AC C V = E V − A C

C V > 0 CV > 0 C V > 0 (Positive): Favorable; work completed cost less than budgeted (under budget).

C V < 0 CV < 0 C V < 0 (Negative): Unfavorable; work completed cost more than budgeted (over budget).

C V = 0 CV = 0 C V = 0 : Exactly on budget.

Notice that in EVM, a negative variance is unfavorable, which reverses some traditional management accounting variance sign conventions.

Performance Indices: SPI, CPI, and Critical Ratio

Efficiency ratios provide dimensionless indicators that allow comparisons across projects of disparate scales:

Schedule Performance Index ( S P I SPI SP I ) S P I = E V P V SPI = \frac{EV}{PV} SP I = P V E V ​

S P I > 1.0 SPI > 1.0 SP I > 1.0 : Progressing at a faster rate than planned (e.g., 1.15 1.15 1.15 indicates 115% of scheduled progress accomplished per unit time).

S P I < 1.0 SPI < 1.0 SP I < 1.0 : Progressing slower than planned ( 0.80 0.80 0.80 indicates accomplishing only 80 cents of scheduled work per dollar of time).

Cost Performance Index ( C P I CPI CP I ) C P I = E V A C CPI = \frac{EV}{AC} CP I = A C E V ​

C P I > 1.0 CPI > 1.0 CP I > 1.0 : Performing with superior cost efficiency (e.g., 1.20 1.20 1.20 indicates $1.20 of earned value generated per $1.00 spent).

C P I < 1.0 CPI < 1.0 CP I < 1.0 : Experiencing cost inefficiency (e.g., 0.85 0.85 0.85 indicates $0.85 of value generated per $1.00 spent).

Cumulative CPI provides a useful trend, but its stability and the feasibility of recovery depend on the work remaining. A particular completion percentage or CPI threshold does not establish a universal forecast.

Critical Ratio ( C R CR CR ) C R = C P I × S P I CR = CPI \times SPI CR = CP I × SP I

The Critical Ratio provides an aggregate index of overall project health. Review CPI and SPI separately: their product can equal 1.0 even when cost and schedule deviations offset. Escalation thresholds are project-specific; no universal 0.80 emergency rule applies.

Forecasting Project Completion: EAC, ETC, and VAC

Strategic management accountants use EVM trends to project final project financial outcomes:

Forecasting Assumption Scenario Rationale Estimate at Completion ( E A C EAC E A C ) Formula

1. Historical CPI Trend Continues Current cost inefficiencies or efficiencies are typical and will persist across all remaining deliverables E A C = B A C C P I EAC = \frac{BAC}{CPI} E A C = CP I B A C ​

2. Atypical Variance (Budgeted Rate) Current variances were one-time anomalies (e.g., extreme weather, initial permit delay); future work proceeds at original budgeted rate E A C = A C + ( B A C − E V ) = B A C − C V EAC = AC + (BAC - EV) = BAC - CV E A C = A C + ( B A C − E V ) = B A C − C V

3. Combined CPI and SPI Impact Schedule delays force costly overtime, expediting fees, or dual-contractor acceleration to recover time E A C = A C + B A C − E V C P I × S P I EAC = AC + \frac{BAC - EV}{CPI \times SPI} E A C = A C + CP I × SP I B A C − E V ​

4. Bottom-Up Re-estimate Original baseline assumptions are completely invalid; remaining work packages are re-priced from scratch ( E T C new ETC_{\text{new}} ET C new ​ ) E A C = A C + E T C bottom-up EAC = AC + ETC_{\text{bottom-up}} E A C = A C + ET C bottom-up ​

Estimate to Complete ( E T C ETC ETC ) and Variance at Completion ( V A C VAC V A C )

Estimate to Complete ( E T C ETC ETC ): Expected additional capital outlay required to complete all remaining work: E T C = E A C − A C ETC = EAC - AC ETC = E A C − A C

Variance at Completion ( V A C VAC V A C ): Projected final budget surplus or overrun: V A C = B A C − E A C VAC = BAC - EAC V A C = B A C − E A C

( V A C < 0 VAC < 0 V A C < 0 denotes a forecasted budget blowout).

To-Complete Performance Index (TCPI)

The To-Complete Performance Index (TCPI) evaluates the cost efficiency the remaining project team must achieve to hit a specified financial target. It represents the ratio of remaining work to remaining available budget:

TCPI to achieve original budget ( B A C BAC B A C ) T C P I B A C = Remaining Work Remaining Budget = B A C − E V B A C − A C TCPI_{BAC} = \frac{\text{Remaining Work}}{\text{Remaining Budget}} = \frac{BAC - EV}{BAC - AC} TCP I B A C ​ = Remaining Budget Remaining Work ​ = B A C − A C B A C − E V ​

TCPI to achieve revised forecast ( E A C EAC E A C ) T C P I E A C = Remaining Work Remaining Revised Budget = B A C − E V E A C − A C TCPI_{EAC} = \frac{\text{Remaining Work}}{\text{Remaining Revised Budget}} = \frac{BAC - EV}{EAC - AC} TCP I E A C ​ = Remaining Revised Budget Remaining Work ​ = E A C − A C B A C − E V ​

Strategic Governance Interpretation

If T C P I B A C > 1.0 TCPI_{BAC} > 1.0 TCP I B A C ​ > 1.0 : Remaining work must earn more budgeted value per dollar than the baseline rate of 1.0. Compare the required rate with the actual CPI to assess the change needed.

If T C P I B A C > 1.10 TCPI_{BAC} > 1.10 TCP I B A C ​ > 1.10 : This may be challenging, but 1.10 is not a universal feasibility boundary. Review the remaining work and a bottom-up forecast. Authorise any baseline change formally and preserve the original baseline and variance history; an EAC forecast does not automatically change BAC.

Corporate Application: Queensland Health Systems Ltd

Queensland Health Systems Ltd is undertaking Project Horizon—a 12-month, $2,400,000 digital patient record transformation (baseline spend linear at $200,000 per month). At the end of Month 6 , the strategic management accountant conducted an EVM audit and compiled the following data:

Baseline budget: BAC = $2,400,000.

Scheduled progress at Month 6: 50% (PV = 0.50 × $2,400,000 = $1,200,000).

Verified deliverables complete: 40% (EV = 0.40 × $2,400,000 = $960,000).

Actual costs recorded on ledger: AC = $1,120,000.

Core Metric Calculations Schedule Variance: S V = E V − P V = $ 960 , 000 − $ 1 , 200 , 000 = − $ 240 , 000 (Behind Schedule) \text{Schedule Variance: } SV = EV - PV = \text{\textdollar}960,000 - \text{\textdollar}1,200,000 = -\text{\textdollar}240,000\text{ (Behind Schedule)} Schedule Variance: S V = E V − P V = $ 960 , 000 − $ 1 , 200 , 000 = − $ 240 , 000 (Behind Schedule) Cost Variance: C V = E V − A C = $ 960 , 000 − $ 1 , 120 , 000 = − $ 160 , 000 (Over Budget) \text{Cost Variance: } CV = EV - AC = \text{\textdollar}960,000 - \text{\textdollar}1,120,000 = -\text{\textdollar}160,000\text{ (Over Budget)} Cost Variance: C V = E V − A C = $ 960 , 000 − $ 1 , 120 , 000 = − $ 160 , 000 (Over Budget) Schedule Performance Index: S P I = E V P V = $ 960 , 000 $ 1 , 200 , 000 = 0.80 \text{Schedule Performance Index: } SPI = \frac{EV}{PV} = \frac{\text{\textdollar}960,000}{\text{\textdollar}1,200,000} = 0.80 Schedule Performance Index: SP I = P V E V ​ = $ 1 , 200 , 000 $ 960 , 000 ​ = 0.80 Cost Performance Index: C P I = E V A C = $ 960 , 000 $ 1 , 120 , 000 ≈ 0.8571 \text{Cost Performance Index: } CPI = \frac{EV}{AC} = \frac{\text{\textdollar}960,000}{\text{\textdollar}1,120,000} \approx 0.8571 Cost Performance Index: CP I = A C E V ​ = $ 1 , 120 , 000 $ 960 , 000 ​ ≈ 0.8571 Critical Ratio: C R = C P I × S P I = 0.8571 × 0.80 ≈ 0.6857 \text{Critical Ratio: } CR = CPI \times SPI = 0.8571 \times 0.80 \approx 0.6857 Critical Ratio: CR = CP I × SP I = 0.8571 × 0.80 ≈ 0.6857

Operational Interpretation: The project is accomplishing only 80% of scheduled progress per month and generating only 85.71 cents of verified deliverable value for every dollar expended. The Critical Ratio of 0.6857 signals severe program distress.

Completion Forecasting

Forecast 1 (Typical Performance Continues): E A C 1 = B A C C P I = $ 2 , 400 , 000 0.857143 = $ 2 , 800 , 000 EAC_1 = \frac{BAC}{CPI} = \frac{\text{\textdollar}2,400,000}{0.857143} = \text{\textdollar}2,800,000 E A C 1 ​ = CP I B A C ​ = 0.857143 $ 2 , 400 , 000 ​ = $ 2 , 800 , 000 V A C 1 = B A C − E A C 1 = $ 2 , 400 , 000 − $ 2 , 800 , 000 = − $ 400 , 000 overrun VAC_1 = BAC - EAC_1 = \text{\textdollar}2,400,000 - \text{\textdollar}2,800,000 = -\text{\textdollar}400,000\text{ overrun} V A C 1 ​ = B A C − E A C 1 ​ = $ 2 , 400 , 000 − $ 2 , 800 , 000 = − $ 400 , 000 overrun E T C 1 = E A C 1 − A C = $ 2 , 800 , 000 − $ 1 , 120 , 000 = $ 1 , 680 , 000 ETC_1 = EAC_1 - AC = \text{\textdollar}2,800,000 - \text{\textdollar}1,120,000 = \text{\textdollar}1,680,000 ET C 1 ​ = E A C 1 ​ − A C = $ 2 , 800 , 000 − $ 1 , 120 , 000 = $ 1 , 680 , 000

Forecast 2 (Atypical Anomaly): E A C 2 = A C + ( B A C − E V ) = $ 1 , 120 , 000 + ( $ 2 , 400 , 000 − $ 960 , 000 ) = $ 2 , 560 , 000 EAC_2 = AC + (BAC - EV) = \text{\textdollar}1,120,000 + (\text{\textdollar}2,400,000 - \text{\textdollar}960,000) = \text{\textdollar}2,560,000 E A C 2 ​ = A C + ( B A C − E V ) = $ 1 , 120 , 000 + ( $ 2 , 400 , 000 − $ 960 , 000 ) = $ 2 , 560 , 000 V A C 2 = $ 2 , 400 , 000 − $ 2 , 560 , 000 = − $ 160 , 000 overrun VAC_2 = \text{\textdollar}2,400,000 - \text{\textdollar}2,560,000 = -\text{\textdollar}160,000\text{ overrun} V A C 2 ​ = $ 2 , 400 , 000 − $ 2 , 560 , 000 = − $ 160 , 000 overrun

Forecast 3 (Schedule Delay Drives Escalating Costs): E A C 3 = A C + B A C − E V C P I × S P I = $ 1 , 120 , 000 + $ 1 , 440 , 000 0.685714 = $ 1 , 120 , 000 + $ 2 , 100 , 000 = $ 3 , 220 , 000 EAC_3 = AC + \frac{BAC - EV}{CPI \times SPI} = \text{\textdollar}1,120,000 + \frac{\text{\textdollar}1,440,000}{0.685714} = \text{\textdollar}1,120,000 + \text{\textdollar}2,100,000 = \text{\textdollar}3,220,000 E A C 3 ​ = A C + CP I × SP I B A C − E V ​ = $ 1 , 120 , 000 + 0.685714 $ 1 , 440 , 000 ​ = $ 1 , 120 , 000 + $ 2 , 100 , 000 = $ 3 , 220 , 000 V A C 3 = $ 2 , 400 , 000 − $ 3 , 220 , 000 = − $ 820 , 000 overrun VAC_3 = \text{\textdollar}2,400,000 - \text{\textdollar}3,220,000 = -\text{\textdollar}820,000\text{ overrun} V A C 3 ​ = $ 2 , 400 , 000 − $ 3 , 220 , 000 = − $ 820 , 000 overrun

Projected Completion Time: Estimated Duration = Planned Duration S P I = 12 months 0.80 = 15 months (3-month delay) \text{Estimated Duration} = \frac{\text{Planned Duration}}{SPI} = \frac{12 \text{ months}}{0.80} = 15 \text{ months (3-month delay)} Estimated Duration = SP I Planned Duration ​ = 0.80 12 months ​ = 15 months (3-month delay)

TCPI Feasibility Assessment

To achieve the original $2,400,000 budget: T C P I B A C = B A C − E V B A C − A C = $ 2 , 400 , 000 − $ 960 , 000 $ 2 , 400 , 000 − $ 1 , 120 , 000 = $ 1 , 440 , 000 $ 1 , 280 , 000 = 1.125 TCPI_{BAC} = \frac{BAC - EV}{BAC - AC} = \frac{\text{\textdollar}2,400,000 - \text{\textdollar}960,000}{\text{\textdollar}2,400,000 - \text{\textdollar}1,120,000} = \frac{\text{\textdollar}1,440,000}{\text{\textdollar}1,280,000} = 1.125 TCP I B A C ​ = B A C − A C B A C − E V ​ = $ 2 , 400 , 000 − $ 1 , 120 , 000 $ 2 , 400 , 000 − $ 960 , 000 ​ = $ 1 , 280 , 000 $ 1 , 440 , 000 ​ = 1.125

To achieve the revised EAC of $2,800,000: T C P I E A C = B A C − E V E A C − A C = $ 1 , 440 , 000 $ 2 , 800 , 000 − $ 1 , 120 , 000 = $ 1 , 440 , 000 $ 1 , 680 , 000 ≈ 0.857 TCPI_{EAC} = \frac{BAC - EV}{EAC - AC} = \frac{\text{\textdollar}1,440,000}{\text{\textdollar}2,800,000 - \text{\textdollar}1,120,000} = \frac{\text{\textdollar}1,440,000}{\text{\textdollar}1,680,000} \approx 0.857 TCP I E A C ​ = E A C − A C B A C − E V ​ = $ 2 , 800 , 000 − $ 1 , 120 , 000 $ 1 , 440 , 000 ​ = $ 1 , 680 , 000 $ 1 , 440 , 000 ​ ≈ 0.857

Strategic Recommendation: To hit the original $2,400,000 budget, the team must improve cost efficiency from $0.857 to $1.125 per dollar spent—a 31.3% leap in operational productivity while managing complex healthcare data. The management accountant advised the board that T C P I B A C = 1.125 TCPI_{BAC} = 1.125 TCP I B A C ​ = 1.125 requires evidence of a credible recovery plan. The accountant recommends a $2,800,000 forecast and a schedule review. The 15-month duration is only a rough SPI extrapolation, not a critical-path forecast; any scope or baseline change requires separate approval.

Exam Traps to Avoid

Warning

Common Exam Trap 1: Inverting EVM ratio formulas. Remember that Earned Value ( E V EV E V ) is always the numerator in variance indices: C P I = E V A C CPI = \frac{EV}{AC} CP I = A C E V ​ and S P I = E V P V SPI = \frac{EV}{PV} SP I = P V E V ​ . Never divide actual costs by earned value.

Note

Common Exam Trap 2: Believing a positive Schedule Variance in dollars guarantees critical path compliance. S V SV S V measures overall volume of work delivered against total scheduled work. If high-value non-critical tasks are completed early while an inexpensive critical path software task is stalled, S V SV S V can show positive even as the project's actual launch date is slipping.

Loading diagram... Earned Value S-Curve & Performance Metrics Architecture