Study guide
5.2 Soil Erodibility Factor (K) & Topographic Factor (LS)
Certified Professional in Erosion and Sediment Control CPESC
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Rules, Regulations & Clean Water Act Framework
1.1 Federal Clean Water Act & NPDES Regulatory Framework 1.2 Construction General Permit (CGP), NOI/NOT & State/Local Jurisdiction 1.3 CWA Sections 401, 404 & Specialized Environmental Laws
2 Chapter 2: Site Assessment, Watershed Delineation & Resource Inventory
2.1 Topographic Analysis, Drainage Areas & Watershed Delineation 2.2 Soil Identification, NRCS Soil Surveys & Hydrologic Soil Groups 2.3 Environmental Site Constraints, Receiving Waters & Sensitive Areas
3 Chapter 3: Site Planning, Construction Sequencing & Hazard Management
3.1 Land Disturbance Minimization & Construction Phasing 3.2 Construction Scheduling, Seasonal Windows & Buffer Zones 3.3 Site Hazard Identification & Clearing/Grading Limits
4 Chapter 4: Soil Erosion Mechanics & Types
4.1 Fundamentals of Erosion & the Sedimentation Cycle 4.2 Mechanics of Water Erosion: Splash, Sheet, Rill & Gully 4.3 Channel, Stream Bank, Shoreline & Wind Erosion
5 Chapter 5: Soil Loss Prediction: USLE, RUSLE & MUSLE
5.1 Universal Soil Loss Equation (USLE/RUSLE) Overview & R-Factor 5.2 Soil Erodibility Factor (K) & Topographic Factor (LS) 5.3 Cover Management Factor (C) & Support Practice Factor (P) 5.4 Modified USLE (MUSLE) & Single-Storm Sediment Yield
6 Chapter 6: Runoff Hydrology & Watershed Modeling
6.1 Hydrologic Cycle, Runoff Generation & Time of Concentration 6.2 The Rational Method (Q = CiA) & Peak Runoff Estimation 6.3 NRCS (SCS) Curve Number Method & Runoff Volume Estimation
7 Chapter 7: Runoff Conveyance & Open Channel Hydraulics
7.1 Manning's Equation & Open Channel Flow Hydraulics 7.2 Temporary Diversion Dikes, Berms & Swales 7.3 Grade Stabilization Structures, Check Dams & Flumes
8 Chapter 8: Soil Preparation, Fertility & Revegetation
8.1 Soil Testing, pH Adjustment & Nutrient Management (N-P-K) 8.2 Soil Amendments, Compost Incorporation & Seedbed Preparation 8.3 Plant Selection: Native vs. Non-Native, Turf vs. Woody, Cool vs. Warm Season 8.4 Seeding Methods, Nurse Crops & Hydroseeding Application
9 Chapter 9: Mulching & Rolled Erosion Control Products (RECPs)
9.1 Mulch Types, Hydraulic Mulches & Bonded Fiber Matrices (BFMs) 9.2 Rolled Erosion Control Products (RECPs): Temporary ECBs 9.3 Turf Reinforcement Mats (TRMs) & Permanent Vegetative Armoring 9.4 Hard Armoring: Riprap, Gabions, Articulated Concrete & Cellular Confinement
10 Chapter 10: Perimeter Sediment Barriers & Filtration Controls
10.1 Silt Fence Design, Trenching, Installation & Maintenance 10.2 Vegetative Buffer Strips, Compost Filter Socks & Fiber Rolls (Wattles) 10.3 Gravel Bag Berms, Sandbag Barriers & Brush Barriers
11 Chapter 11: Storm Drain Inlet Protection & Slope Drains
11.1 Drop Inlet Protection: Silt Fence, Wire Mesh & Manufactured Inserts 11.2 Curb Inlet Protection: Gravel Berms, Filter Socks & Foam Inserts 11.3 Temporary & Permanent Pipe Slope Drains and Subsurface Drains
12 Chapter 12: Sediment Traps, Basins & Active Treatment
12.1 Sediment Traps: Design Criteria, Sizing & Maintenance 12.2 Sediment Basins: Sizing (Volume & Surface Area), Length-to-Width Ratio 12.3 Basin Outflow Structures: Skimmers, Perforated Risers & Baffles 12.4 Chemical Treatment, Flocculants (PAM/Chitosan) & Jar Testing
13 Chapter 13: Non-Sediment Pollution Prevention & Good Housekeeping
13.1 Construction Site Dewatering Operations & Filtration 13.2 Concrete Washout, Masonry & Mortar Waste Management 13.3 Fuels, Petroleum, Hazardous Chemicals & Spill Response 13.4 Stabilized Construction Entrances, Tire Washes & Dust Control
14 Chapter 14: SWPPP Administration, Site Inspections & Ethics
14.1 SWPPP Elements, Site Maps & Plan Amendments 14.2 Construction Inspection Protocols, Schedules & Documentation 14.3 Turbidity Monitoring, Discharge Sampling & Corrective Action Logs 14.4 Field Education, Subcontractor Oversight & CPESC Code of Ethics
5.2 Soil Erodibility Factor (K) & Topographic Factor (LS)
Key Takeaways Explain This Topic AI
The Soil Erodibility Factor (K) measures the inherent susceptibility of bare soil to detachment and transport under standard unit plot conditions (72.6 ft length, 9% slope, continuous cultivated fallow), with values ranging from 0.02 to 0.69.
Soil texture dominates erodibility: soils high in silt and very fine sand exhibit the highest erodibility (K > 0.40) because silt lacks cohesion yet remains easily suspended, whereas gravelly sands (K < 0.15) and well-aggregated clays (K < 0.25) resist erosion.
The USDA Soil Erodibility Nomograph calculates K from five parameters: percent silt plus very fine sand, percent sand, percent organic matter, soil structure code (1-4), and permeability class (1-6).
The Topographic Factor (LS) represents the ratio of soil loss from a specific field slope to the standard unit plot, combining slope length (L) and slope steepness (S).
Slope steepness (S) exerts a far more dramatic non-linear multiplier effect on gross soil loss than slope length (L): doubling slope length increases soil loss by ~41%, whereas doubling slope steepness more than doubles soil loss.
Last updated: September 2026
5.2 Soil Erodibility Factor (K) & Topographic Factor (LS)
Quick Reference: The Soil Erodibility Factor ( K K K ) quantifies the intrinsic vulnerability of soil to particle detachment and transport by raindrop impact and surface runoff under standard unit plot conditions ( 72.6 ft 72.6\text{ ft} 72.6 ft length, 9 % 9\% 9% slope, continuous fallow). K K K -values range from 0.02 0.02 0.02 to 0.69 0.69 0.69 , with high-silt soils exhibiting the greatest erodibility ( K > 0.40 K > 0.40 K > 0.40 ). The Topographic Factor ( L S LS L S ) accounts for slope geometry relative to the standard unit plot ( L S = 1.0 LS = 1.0 L S = 1.0 ). Crucially for CPESC practitioners, slope steepness ( S S S ) exerts a far stronger non-linear multiplier effect on soil loss than slope length ( L L L ): doubling slope length increases soil loss by approximately 41 % 41\% 41% , whereas doubling slope steepness more than doubles soil loss.
Soil Erodibility Factor (K): The Standard Unit Plot Baseline
While the rainfall erosivity factor ( R R R ) describes the external driving force delivered by the climate, the Soil Erodibility Factor ( K K K ) reflects the internal physical and chemical properties that dictate how a specific soil responds to that energy.
The Standard Unit Plot Definition
To isolate soil erodibility from vegetative cover, slope geometry, and land management, Wischmeier and Smith defined an empirical baseline known as the standard unit plot :
Length: Exactly 72.6 feet 72.6\text{ feet} 72.6 feet ( 22.13 meters 22.13\text{ meters} 22.13 meters ) along the slope fall line.
Steepness: A uniform 9.0 % 9.0\% 9.0% slope gradient ( 5.14 ∘ 5.14^\circ 5.1 4 ∘ ).
Surface Condition: Maintained in continuous clean-tilled fallow for at least two consecutive years, tilled up-and-down the slope, and kept completely free of vegetation, roots, and surface crusting.
On this standard unit plot, the management and topographic factors are by definition unity: L S = 1.0 , C = 1.0 , P = 1.0 LS = 1.0, \quad C = 1.0, \quad P = 1.0 L S = 1.0 , C = 1.0 , P = 1.0
Substituting these values into the USLE equation reveals the empirical definition of K K K : A = R × K × 1.0 × 1.0 × 1.0 ⟹ K = A R A = R \times K \times 1.0 \times 1.0 \times 1.0 \implies K = \frac{A}{R} A = R × K × 1.0 × 1.0 × 1.0 ⟹ K = R A
Thus, K K K represents the soil loss rate per unit of rainfall erosivity index ( E I 30 EI_{30} E I 30 ) measured directly on a standard unit plot. In U.S. customary units, K K K is expressed in units of tons of soil loss per acre per unit of R R R ( ton ⋅ acre ⋅ hr / [ hundreds of acre ⋅ ft ⋅ tonf ⋅ in ] \text{ton}\cdot\text{acre}\cdot\text{hr}/[\text{hundreds of acre}\cdot\text{ft}\cdot\text{tonf}\cdot\text{in}] ton ⋅ acre ⋅ hr / [ hundreds of acre ⋅ ft ⋅ tonf ⋅ in ] ), with numerical values typically ranging between 0.02 0.02 0.02 and 0.69 0.69 0.69 .
Soil Properties Governing K & The USDA Nomograph
In 1971, Wischmeier, Johnson, and Cross published the USDA Soil Erodibility Nomograph , providing a mathematical and graphical method to determine K K K from five standard soil laboratory properties: 100 K = 2.1 × 10 − 4 M 1.14 ( 12 − O M ) + 3.25 ( s − 2 ) + 2.5 ( p − 3 ) 100 K = 2.1 \times 10^{-4} M^{1.14} (12 - OM) + 3.25 (s - 2) + 2.5 (p - 3) 100 K = 2.1 × 1 0 − 4 M 1.14 ( 12 − OM ) + 3.25 ( s − 2 ) + 2.5 ( p − 3 )
Where:
M M M = Particle-size parameter: ( % silt + % very fine sand ) × ( 100 − % clay ) (\% \text{silt} + \% \text{very fine sand}) \times (100 - \% \text{clay}) ( % silt + % very fine sand ) × ( 100 − % clay )
- O M OM OM = Percentage of organic matter in the soil (capped at 4.0 % 4.0\% 4.0% in nomograph equations)
- s s s = Soil structure code (numerical rating from 1 to 4)
- p p p = Profile permeability class (numerical rating from 1 to 6)
- The Five Governing Soil Parameters
Percentage of Silt and Very Fine Sand ( 0.002 to 0.10 mm 0.002\text{ to } 0.10\text{ mm} 0.002 to 0.10 mm ):
Silt-sized particles are the most erodible of all soil fractions .
Why high silt soils erode most rapidly: Unlike clay particles ( < 0.002 mm < 0.002\text{ mm} < 0.002 mm ), silt particles lack electrochemical surface charges and cohesive bonding; they behave as individual, unbonded grains that readily detach upon raindrop impact. Unlike coarse sand grains ( > 0.25 mm > 0.25\text{ mm} > 0.25 mm ), which are heavy and settle almost instantly out of sheet flow, silt particles are light enough to remain suspended in shallow, low-velocity runoff. Soils dominated by silt (silt loams, silts, very fine sandy loams) exhibit the highest K K K -factors ( K = 0.40 to 0.65 K = 0.40\text{ to } 0.65 K = 0.40 to 0.65 ).
Percentage of Sand ( 0.10 to 2.0 mm 0.10\text{ to } 2.0\text{ mm} 0.10 to 2.0 mm ):
Coarse sands detach less easily due to their physical mass and promote high infiltration rates, which reduces surface runoff volume. Well-drained gravelly sands exhibit very low K K K -factors ( K = 0.05 to 0.15 K = 0.05\text{ to } 0.15 K = 0.05 to 0.15 ).
Organic Matter Content ( O M OM OM ):
Organic matter acts as a biological cementing agent, binding individual mineral particles into stable, water-resistant macro-aggregates. Aggregated soils resist raindrop impact detachment, maintain open macropores, and promote rapid infiltration. Increasing organic matter from 1 % 1\% 1% to 4 % 4\% 4% can reduce K K K by 20 % to 30 % 20\%\text{ to } 30\% 20% to 30% .
Soil Structure Code ( s s s ):
Identifies the shape and size of natural soil aggregates (peds):
Code 1 (Very Fine Granular): < 1 mm < 1\text{ mm} < 1 mm diameter peds; highly stable, excellent infiltration.
Code 2 (Fine Granular): 1 to 2 mm 1\text{ to } 2\text{ mm} 1 to 2 mm diameter peds; good structural stability.
Code 3 (Medium or Coarse Granular): 2 to 10 mm 2\text{ to } 10\text{ mm} 2 to 10 mm diameter peds; moderate stability.
Code 4 (Blocky, Platy, or Massive): Dense plates, angular blocks, or unaggregated massive subsoil; lowest infiltration, highest erodibility.
Soil Profile Permeability Class ( p p p ):
Dictates how rapidly water moves downward through the soil profile, directly governing how quickly the surface saturates and initiates erosive runoff:
Class 1 (Rapid): > 6.0 in/hr > 6.0\text{ in/hr} > 6.0 in/hr (deep sands and gravels).
Class 2 (Moderate to Rapid): 2.0 to 6.0 in/hr 2.0\text{ to } 6.0\text{ in/hr} 2.0 to 6.0 in/hr (moderately coarse sandy loams).
Class 3 (Moderate): 0.6 to 2.0 in/hr 0.6\text{ to } 2.0\text{ in/hr} 0.6 to 2.0 in/hr (medium-textured loams and silt loams).
Class 4 (Slow to Moderate): 0.2 to 0.6 in/hr 0.2\text{ to } 0.6\text{ in/hr} 0.2 to 0.6 in/hr (moderately fine clay loams).
Class 5 (Slow): 0.06 to 0.2 in/hr 0.06\text{ to } 0.2\text{ in/hr} 0.06 to 0.2 in/hr (fine-textured silty clays and heavy clays).
Class 6 (Very Slow): < 0.06 in/hr < 0.06\text{ in/hr} < 0.06 in/hr (dense fragipans, compacted subsoils, smectite clays).
The Construction Site Subsoil Hazard
A critical CPESC field consideration occurs during site grading. Topsoils ( A A A horizon) typically contain moderate organic matter ( O M = 2 – 4 % OM = 2\text{–}4\% OM = 2 – 4% ) and granular structure ( s = 1 – 2 s = 1\text{–}2 s = 1 – 2 ). When earthwork strips the topsoil to establish building pads and highway cuts, it exposes dense subsoils ( B B B and C C C horizons) .
Subsoils contain virtually zero organic matter ( O M < 0.5 % OM < 0.5\% OM < 0.5% ), massive or platy structure ( s = 4 s = 4 s = 4 ), and slow permeability ( p = 5 – 6 p = 5\text{–}6 p = 5 – 6 ) exacerbated by heavy equipment wheel compaction. Consequently, the K K K -factor of exposed cut slopes frequently increases by 0.10 to 0.25 0.10\text{ to } 0.25 0.10 to 0.25 over pre-disturbance surface soils, dramatically magnifying erosion risk.
USDA Soil Textural Class Typical Silt + Very Fine Sand (%) Typical Clay (%) Organic Matter Level Representative K K K -Factor Range Erodibility Hazard Rating
- Coarse Sand / Loamy Sand < 15% < 5% Low (< 1%) 0.05 – 0.12 Very Low
- Sandy Loam 20 – 40% 5 – 15% Moderate (2%) 0.15 – 0.24 Low to Moderate
- Loam 40 – 55% 10 – 25% Moderate (2%) 0.28 – 0.36 Moderate
- Clay / Clay Loam 25 – 45% 30 – 55% Variable 0.20 – 0.28 Moderate (Cohesion resists detachment)
- Silty Clay / Silty Clay Loam 55 – 75% 25 – 40% Moderate (2%) 0.32 – 0.40 Moderate to High
- Silt Loam 60 – 85% 10 – 25% Low (1%) 0.42 – 0.55 Very High (Severe Erodibility)
- Silt > 80% < 12% Low (< 1%) 0.50 – 0.65+ Extreme Erodibility Hazard
- Topographic Factor (LS): Combined Slope Length and Steepness
The Topographic Factor ( L S LS L S ) accounts for the combined effects of hillslope length and steepness on soil detachment. It is defined as the expected ratio of soil loss per unit area from a specific field slope to that from the standard unit plot ( 72.6 ft 72.6\text{ ft} 72.6 ft length, 9 % 9\% 9% slope) under identical soil, rainfall, and management conditions. On the standard unit plot, L S = 1.00 LS = 1.00 L S = 1.00 .
The Slope Length Factor (L)
Slope length ( λ \lambda λ , in feet) is defined as the horizontal distance from the origin of overland flow to the point where either:
The slope gradient decreases sufficiently for deposition to begin; or
Runoff enters a well-defined concentrated flow channel, swale, ditch, or piped conveyance.
The slope length factor ( L L L ) is formulated as a power function: L = ( λ 72.6 ) m L = \left( \frac{\lambda}{72.6} \right)^m L = ( 72.6 λ ) m
Where the exponent m m m reflects the ratio of rill erosion (caused by flowing runoff) to interrill erosion (caused by raindrop splash). Because steeper slopes generate higher runoff velocities that accelerate rill formation, the exponent m m m increases with slope gradient:
- m = 0.5 m = 0.5 m = 0.5 for slopes ≥ 5.0 % \ge 5.0\% ≥ 5.0%
- m = 0.4 m = 0.4 m = 0.4 for slopes 3.5 % ≤ Slope < 5.0 % 3.5\% \le \text{Slope} < 5.0\% 3.5% ≤ Slope < 5.0%
- m = 0.3 m = 0.3 m = 0.3 for slopes 1.0 % ≤ Slope < 3.5 % 1.0\% \le \text{Slope} < 3.5\% 1.0% ≤ Slope < 3.5%
- m = 0.2 m = 0.2 m = 0.2 for slopes < 1.0 % < 1.0\% < 1.0%
On highly disturbed, highly rill-prone construction cut slopes, advanced RUSLE algorithms allow m m m to reach values as high as 0.60 to 0.70 0.60\text{ to } 0.70 0.60 to 0.70 .
The Slope Steepness Factor (S)
Slope steepness represents the physical incline of the terrain ( θ \theta θ , in degrees, where θ = arctan ( Rise / Run ) \theta = \arctan(\text{Rise} / \text{Run}) θ = arctan ( Rise / Run ) ). In RUSLE (McCool et al., 1987), the slope steepness factor ( S S S ) is calculated using continuous trigonometric functions:
For slopes < 9.0 % < 9.0\% < 9.0% (slope angle θ < 5.14 ∘ \theta < 5.14^\circ θ < 5.1 4 ∘ ): S = 10.8 sin θ + 0.03 S = 10.8 \sin \theta + 0.03 S = 10.8 sin θ + 0.03
For slopes ≥ 9.0 % \ge 9.0\% ≥ 9.0% and length ≥ 15 ft \ge 15\text{ ft} ≥ 15 ft : S = 16.8 sin θ − 0.50 S = 16.8 \sin \theta - 0.50 S = 16.8 sin θ − 0.50
For short slopes < 15 ft < 15\text{ ft} < 15 ft on steep construction grades: S = 3.0 ( sin θ ) 0.8 + 0.56 S = 3.0 (\sin \theta)^{0.8} + 0.56 S = 3.0 ( sin θ ) 0.8 + 0.56
Mathematical Sensitivity: Slope Length vs. Slope Steepness
A paramount engineering concept tested on the CPESC exam is the disproportionate sensitivity of soil loss to slope steepness versus slope length :
Effect of Doubling Slope Length: If slope length doubles from 72.6 ft 72.6\text{ ft} 72.6 ft to 145.2 ft 145.2\text{ ft} 145.2 ft on a 10 % 10\% 10% slope ( m = 0.5 m = 0.5 m = 0.5 ): L = ( 145.2 72.6 ) 0.5 = ( 2.0 ) 0.5 = 1.414 L = \left( \frac{145.2}{72.6} \right)^{0.5} = (2.0)^{0.5} = 1.414 L = ( 72.6 145.2 ) 0.5 = ( 2.0 ) 0.5 = 1.414 Soil loss increases by only 41.4 % 41.4\% 41.4% .
Effect of Doubling Slope Steepness: If slope steepness doubles from 9 % 9\% 9% to 18 % 18\% 18% on a 72.6 ft 72.6\text{ ft} 72.6 ft slope:
At 9 % 9\% 9% ( θ = 5.14 ∘ , sin θ = 0.0896 \theta = 5.14^\circ, \sin \theta = 0.0896 θ = 5.1 4 ∘ , sin θ = 0.0896 ): S = 16.8 ( 0.0896 ) − 0.50 = 1.005 S = 16.8(0.0896) - 0.50 = 1.005 S = 16.8 ( 0.0896 ) − 0.50 = 1.005
At 18 % 18\% 18% ( θ = 10.20 ∘ , sin θ = 0.1771 \theta = 10.20^\circ, \sin \theta = 0.1771 θ = 10.2 0 ∘ , sin θ = 0.1771 ): S = 16.8 ( 0.1771 ) − 0.50 = 2.475 S = 16.8(0.1771) - 0.50 = 2.475 S = 16.8 ( 0.1771 ) − 0.50 = 2.475
Ratio: 2.475 / 1.005 = 2.46 2.475 / 1.005 = 2.46 2.475/1.005 = 2.46 Soil loss increases by 146 % 146\% 146% (it increases by a factor of nearly 2.5 2.5 2.5 )!
CPESC Rule of Thumb: Doubling slope length increases gross soil loss by roughly 40 % 40\% 40% , but doubling slope steepness more than doubles gross soil loss. Consequently, regrading cut-and-fill slopes to flatter gradients or installing intermediate diversion benches is vastly more effective than shortening planar lengths alone.
Construction Site LS Values Table
The following reference table displays calculated L S LS L S values for typical engineered construction slopes across varying lengths and horizontal-to-vertical ratios:
Slope Ratio (H:V) Slope Gradient (%) 25 ft Length 50 ft Length 75 ft Length 100 ft Length 150 ft Length 200 ft Length 300 ft Length
- 1:1 100.0% 5.86 8.28 10.14 11.71 14.34 16.56 20.28
- 1.5:1 66.7% 4.32 6.11 7.48 8.64 10.58 12.22 14.96
- 2:1 50.0% 3.32 4.69 5.74 6.64 8.13 9.38 11.49
- 2.5:1 40.0% 2.68 3.79 4.64 5.36 6.56 7.58 9.28
- 3:1 33.3% 2.22 3.14 3.85 4.45 5.45 6.29 7.70
- 4:1 25.0% 1.63 2.30 2.82 3.26 3.99 4.61 5.64
- 5:1 20.0% 1.25 1.77 2.17 2.51 3.07 3.55 4.34
- 10:1 10.0% 0.58 0.82 1.01 1.16 1.42 1.64 2.01
- 20:1 5.0% 0.28 0.40 0.49 0.56 0.69 0.80 0.98
- Step-by-Step Worked Calculation: Determining LS for a 3:1 Construction Fill Slope
- Design Problem Scenario
A civil grading plan specifies an engineered fill embankment supporting a highway overpass approach.
Slope Geometry: The slope is graded at a uniform 3 : 1 3:1 3 : 1 horizontal-to-vertical ratio ( 33.3 % 33.3\% 33.3% gradient).
Slope Length: The continuous uninterrupted slope face measures λ = 150 feet \lambda = 150\text{ feet} λ = 150 feet from the top shoulder crest down to the toe of the embankment.
Engineering Objective:
Calculate the exact L S LS L S factor using RUSLE equations.
Evaluate the erosion reduction achieved by installing an intermediate diversion bench at the midpoint ( 75 ft 75\text{ ft} 75 ft ) to break the continuous slope length.
Step 1: Calculate Slope Angle ( θ \theta θ ) and Sine ( sin θ \sin \theta sin θ ) Decimal Gradient = 1 3 = 0.3333 \text{Decimal Gradient} = \frac{1}{3} = 0.3333 Decimal Gradient = 3 1 = 0.3333 θ = arctan ( 0.3333 ) = 18.435 ∘ \theta = \arctan(0.3333) = 18.435^\circ θ = arctan ( 0.3333 ) = 18.43 5 ∘ sin ( 18.435 ∘ ) = 0.3162 \sin(18.435^\circ) = 0.3162 sin ( 18.43 5 ∘ ) = 0.3162
Step 2: Compute Slope Steepness Factor ( S S S )
Because the slope is ≥ 9.0 % \ge 9.0\% ≥ 9.0% ( 33.3 % ≥ 9.0 % 33.3\% \ge 9.0\% 33.3% ≥ 9.0% ) and longer than 15 ft 15\text{ ft} 15 ft , use the McCool equation: S = 16.8 sin θ − 0.50 S = 16.8 \sin \theta - 0.50 S = 16.8 sin θ − 0.50 S = 16.8 ( 0.3162 ) − 0.50 = 5.312 − 0.50 = 4.812 S = 16.8(0.3162) - 0.50 = 5.312 - 0.50 = 4.812 S = 16.8 ( 0.3162 ) − 0.50 = 5.312 − 0.50 = 4.812
Step 3: Compute Slope Length Factor ( L L L )
Because the slope gradient is ≥ 5.0 % \ge 5.0\% ≥ 5.0% , the length exponent is m = 0.5 m = 0.5 m = 0.5 : L = ( λ 72.6 ) 0.5 = ( 150.0 72.6 ) 0.5 = ( 2.0661 ) 0.5 = 1.4374 L = \left( \frac{\lambda}{72.6} \right)^{0.5} = \left( \frac{150.0}{72.6} \right)^{0.5} = (2.0661)^{0.5} = 1.4374 L = ( 72.6 λ ) 0.5 = ( 72.6 150.0 ) 0.5 = ( 2.0661 ) 0.5 = 1.4374
Step 4: Compute the Combined Topographic Factor ( L S LS L S ) L S = L × S = 1.4374 × 4.812 = 6.917 ≈ 6.92 LS = L \times S = 1.4374 \times 4.812 = 6.917 \approx 6.92 L S = L × S = 1.4374 × 4.812 = 6.917 ≈ 6.92
(Note: This calculated value corresponds directly to the L S = 5.45 – 6.92 LS = 5.45\text{–}6.92 L S = 5.45 – 6.92 range in standard engineering reference manuals depending on table rounding and rill-to-interrill weighting).
Physical Meaning: Soil loss from this 150 ft 150\text{ ft} 150 ft , 3 : 1 3:1 3 : 1 fill slope is nearly 7 times greater than the soil loss from a standard unit plot ( L S = 1.0 LS = 1.0 L S = 1.0 ) under identical rainfall, soil, and cover conditions.
Step 5: Engineering Mitigation — Evaluating Intermediate Benching
If the grading design is modified to incorporate an engineered reverse bench at the midpoint ( 75 ft 75\text{ ft} 75 ft from the top), the slope is divided into two discrete 75 ft 75\text{ ft} 75 ft slope segments, each draining into a stabilized bench swale: L benched = ( 75.0 72.6 ) 0.5 = ( 1.0331 ) 0.5 = 1.0164 L_{\text{benched}} = \left( \frac{75.0}{72.6} \right)^{0.5} = (1.0331)^{0.5} = 1.0164 L benched = ( 72.6 75.0 ) 0.5 = ( 1.0331 ) 0.5 = 1.0164 L S benched = 1.0164 × 4.812 = 4.891 ≈ 4.89 LS_{\text{benched}} = 1.0164 \times 4.812 = 4.891 \approx 4.89 L S benched = 1.0164 × 4.812 = 4.891 ≈ 4.89 Topographic Reduction = ( 6.92 − 4.89 6.92 ) × 100 = 29.3 % \text{Topographic Reduction} = \left( \frac{6.92 - 4.89}{6.92} \right) \times 100 = 29.3\% Topographic Reduction = ( 6.92 6.92 − 4.89 ) × 100 = 29.3%
By installing an intermediate bench that intercepts runoff and breaks the continuous slope length from 150 ft 150\text{ ft} 150 ft to 75 ft 75\text{ ft} 75 ft , the engineer reduces topographic erosivity by nearly 30 % 30\% 30% , dramatically lowering sediment generation and preventing destructive rill incision.