15.4 TPM, SMED, Standardized Work, and Visual Management
APICS CPIM Certified in Planning and Inventory Management Exam
Track your progress as you read
Finished sections get a check mark.
1 Introduction & Exam Overview
1.1 Current Exam Facts 1.2 ECM 9.0 Domains and Weights 1.3 How to Study for CPIM
2 Supply Chain Strategy Foundations
2.1 Supply Chains, the Environment, and Strategy 2.2 Environment Analysis and Strategic Scope 2.3 Developing and Managing Organizational Strategy 2.4 Competitive Analysis: Five Forces, Benchmarking, and Value Chain
3 Strategy Performance and Operations Choices
3.1 Performance Monitoring and KPIs 3.2 Functional and Operational Strategies 3.3 Environments, Types, and Layouts 3.4 Service Process Design and Product-Process Trade-offs
4 Sales and Operations Planning
4.1 S&OP Purpose and Process 4.2 Aggregate Demand and Supply Plans 4.3 Reconciling S&OP Plans 4.4 Portfolio, New Product Introduction, and Life-Cycle Planning in S&OP 4.5 Strategic Buffers, Bottlenecks, and Capacity-Constrained Resources
5 Plan and Manage Demand
5.1 Demand Management 5.2 Sources of Demand and Forecasting 5.3 Forecast Performance 5.4 Marketing, Promotions, and Product Management 5.5 Qualitative, Associative, and AI-Driven Forecasting
6 Master Scheduling
6.1 Creating the Master Schedule 6.2 Rough-Cut Capacity Planning and MPS Validation 6.3 Using and Maintaining the Master Schedule 6.4 Planning Bills and Two-Level Master Scheduling 6.5 NPI, DFMA, Prototype, and End-of-Life Schedules
7 MRP, CRP, and Supply Disruptions
7.1 Material Requirements Planning 7.2 CRP, Order Promising, and Final Assembly Scheduling 7.3 Changes and Supply Disruptions 7.4 Product Costing and Variance Analysis for Planners
8 External Supply Sources
8.1 Suppliers and Procurement 8.2 Purchasing and Maintenance 8.3 Supply Chain Risk Management 8.4 Sourcing Footprint and Supplier Relationship Types 8.5 Supplier Release Mechanics and Inbound Logistics
9 Sustainability and Reverse Logistics
9.1 Sustainability Strategies 9.2 Waste Hierarchy and Reverse Logistics 9.3 Sustainability Standards, Reporting, and Life-Cycle Assessment
10 Inventory Planning and Costs
10.1 Inventory Planning 10.2 Inventory Costs, Accounting, Costing, and Metrics 10.3 EOQ, Reorder Point, and Safety Stock
11 Inventory Management and Control
11.1 Inventory Management Policies 11.2 Inventory Control 11.3 Service Levels and Inventory Tradeoffs 11.4 MRO Inventory and Maintenance Planning Inputs 11.5 Traceability Standards and Off-Site Inventory
12 Detailed Schedules and PAC
12.1 Planning Detailed Schedules 12.2 Scheduling and PAC Methods 12.3 Creating Production and Service Schedules 12.4 Managing Detailed Schedules and Scheduling Materials 12.5 Sequencing Rules, Lot Splitting, and Overlapped Scheduling 12.6 Capacity Types, Safety Capacity, and Labor Scheduling 12.7 Process Batches, Transfer Batches, and Backflushing
13 Plan and Manage Distribution
13.1 Planning Distribution 13.2 Replenishment and DRP 13.3 Order Management, Trace/Track, and KPIs
14 Quality and Business Investments
14.1 Quality Systems and Tools 14.2 Capital Equipment and Facilities 14.3 Technology in Planning and Inventory 14.4 The Seven Basic and Seven New Quality Tools 14.5 SPC Charts and Variation Types 14.6 Systems Requirements, Master Data, and Emerging Technologies
15 Continuous Improvement
15.1 Continuous Improvement Overview 15.2 Lean, JIT, and the Seven Wastes 15.3 Six Sigma, Kaizen, and Root Cause Tools 15.4 TPM, SMED, Standardized Work, and Visual Management
16 Integration and Exam Readiness
16.1 Planning Hierarchy Integration 16.2 High-Yield Calculations Drill 16.3 Exam Day, Scoring, and Credential Maintenance
15.4 TPM, SMED, Standardized Work, and Visual Management
Key Takeaways Explain This Topic AI
Overall equipment effectiveness (OEE) = Availability x Performance x Quality; 87.5% x 90.5% x 97.4% = about 77%, so an eight-hour resource really delivers about 6.2 hours of good output and available capacity must be derated by utilization and efficiency to a rated figure before you load a schedule
Internal setup can only be done while the machine is stopped; external setup can be done while it is still running - SMED converts internal to external first, then streamlines whatever internal work remains
Cutting setup cost from $225 to $50 drops the economic order quantity from 1,342 to 632 units because lot size moves with the square root of setup cost, halving cycle stock while annual setup hours still fall from 27 to 12.7
Standardized work is takt time plus work sequence plus standard work-in-process; an unstandardized process cannot be improved because there is no baseline to measure a change against
5S is sort, set in order, shine, standardize, sustain, and sustain is where most programmes fail because the first four are an event and the fifth is a habit
Last updated: July 2026
A lean programme is only real when a shop-floor tool changes a number the planning system uses. ECM Section IX.B names the tools; the exam tests what each does to a planning parameter. Four carry most of the weight: total productive maintenance, quick changeover, standardized work, and work-area design.
Total Productive Maintenance
Total productive maintenance (TPM) treats maintenance as an operator-owned reliability programme, not a repair department you telephone after a breakdown. Two pillars carry the exam items:
Autonomous maintenance - operators own cleaning, lubrication, inspection, and fastener checks on their own equipment. Cleaning is inspection: the operator who wipes the machine down finds the leak while it is still a leak.
Planned (preventive) maintenance - service intervals driven by time or usage, scheduled into the capacity plan as a known load instead of arriving as random downtime.
The planning consequence is blunt. An unplanned breakdown on a constraint is throughput you never recover: an hour lost on a non-constraint is absorbed by protective capacity, but an hour lost on the constraint is an hour lost by the whole plant. TPM is therefore a capacity tool, and preventive maintenance windows belong on the constraint's available-capacity calendar before work is loaded to it.
Overall equipment effectiveness
Overall equipment effectiveness (OEE) = Availability x Performance x Quality rolls the three loss families - downtime, speed, and defects - into one percentage.
A work center has 480 minutes of planned production time and loses 60 minutes to a die failure and a material stockout. It runs 380 units in the time left, against an ideal cycle time of 1.0 minute per unit, and 370 pass inspection.
- Factor Calculation Result
- Availability = operating time / planned production time (480 - 60) / 480 = 420 / 480 87.5%
- Performance = (ideal cycle time x units) / operating time (1.0 x 380) / 420 90.5%
- Quality = good units / total units 370 / 380 97.4%
- OEE 0.875 x 0.905 x 0.974 about 77%
Cross-check it: in 480 minutes at a 1.0-minute cycle the resource could have made 480 good units and made 370, and 370 / 480 = 77.1%. OEE is good output as a fraction of theoretical output.
Now the exam point. A 77% OEE means that eight-hour resource really delivers about 6.2 hours of good output (8 x 0.771), so loading it with eight standard hours overloads it by roughly 30% before the first schedule change. That is why available capacity must be derated by utilization and efficiency factors to reach rated capacity before you load it in capacity requirements planning; OEE is where the evidence for those factors comes from. (Where real output history exists, load against demonstrated capacity instead — that figure is measured from past earned hours, not calculated by derating.) The three factors multiply : averaging them gives a comfortable and wrong 92%.
Single-Minute Exchange of Die
Single-minute exchange of die (SMED) , also called quick changeover , drives setup time toward single digits of minutes. The distinction the exam tests is:
Internal setup - work that can only be done while the machine is stopped: unbolting the old die, mounting and aligning the new one, first-article verification.
External setup - work that can be done while the machine still runs the previous order: staging dies at the machine, pre-heating, pre-kitting fasteners, pre-setting tool holders offline.
The method runs in that order: separate internal from external, convert internal work to external , then streamline what internal work remains with quick clamps, standardized shut heights, and no trial-and-adjust cycles.
Worked before and after
A press changeover takes 90 minutes, and video study shows 60 of them are fetching dies, hunting tools, staging material, and pre-heating - all doable while the press still runs. Converting that work to external leaves 30 minutes internal ; quick clamps and killing the adjustment trials remove another 10, giving a 20-minute changeover . Setup is valued at $150 per hour, annual demand is 24,000 units, carrying cost is $6 per unit per year.
- Measure Before After
- Setup time 90 minutes 20 minutes
- Setup cost S $225 $50
- EOQ = square root of (2DS / H) root of 1,800,000 = 1,342 units root of 400,000 = 632 units
- Runs per year 18 38
- Average cycle stock (EOQ / 2) 671 units 316 units
- Annual setup hours consumed 27.0 12.7
Read the last two rows together: you more than doubled the number of runs and still cut annual setup hours nearly in half, while average cycle stock fell 53%. Shorter setups make smaller lots economic , and smaller lots shorten manufacturing lead time, release cash tied up in cycle stock, and make mixed-model and level schedules feasible at all. That is why SMED is a planning tool and not a maintenance trick: setup time feeds lot sizing, available capacity, and the setup element of the routing. Named trap - lot size moves with the square root of setup cost, so cutting S by a factor of 4.5 cuts EOQ by only about 2.1, never proportionally.
Standardized Work
Standardized work is the documented current best sequence for a task, built from three elements:
Takt time - the customer demand rate the work content is paced to.
Work sequence - the exact order of the operator's steps.
Standard work-in-process (SWIP) - the minimum in-process quantity needed to run that sequence without stopping.
The principle the exam wants: you cannot improve an unstandardized process , because there is no baseline to measure against. If three operators run three different sequences, a claimed 12% gain is indistinguishable from operator variation. Standardized work is not a straitjacket - it is the object kaizen improves, and each improvement becomes the new standard, which is also what makes the run times in your routings credible.
- Designing the Workflow and Work Area
- 5S
Sort - remove what current work does not need, so dead tooling and obsolete work-in-process stop consuming space and cycle-count time.
Set in order - a marked location for everything, turning retrieval time from a variable into a constant inside your standard time.
Shine - clean as inspection; this is where 5S meets autonomous maintenance and protects availability.
Standardize - one written convention across every cell, so the layout of one machine predicts the next and cross-training gets cheaper.
Sustain - audits and discipline that hold the gain. Sustain is where most programmes fail , because the first four S's are an event and the fifth is a habit.
Visual management, andon, and jidoka
Visual management makes the state of the process readable in seconds by anyone standing in the area: min and max lines, kanban squares, colour-coded status boards, an hourly plan-versus-actual chart. The test is whether a stranger can tell the area is behind without asking.
An andon is the escalation half: a light, board, or cord signals an abnormality and calls help at the moment of the problem , not at the end of the shift when the count comes up short. The value is response time, not the light.
Jidoka , or autonomation , is automation with a human touch: equipment built to detect an abnormal condition and stop itself . The defect is contained instead of repeating through the batch, and because the machine no longer needs watching, one operator can tend several. The machine stops, the andon calls, and the problem gets root-caused with the tools in section 15.3.
Poka-yoke (mistake-proofing) is covered in section 14.1, and the exam puts the two in one answer set: poka-yoke prevents or detects the error at the point of work, while jidoka is the machine stopping itself. Automation and layout selection (section 3.3) support flow rather than create it - automating a process you have not first standardized and mistake-proofed only produces defects faster.
What Each Tool Actually Moves
Tool Problem it attacks Measurable planning effect
TPM and OEE Unplanned downtime, speed loss, defect loss Raises availability and demonstrated capacity; supplies the derating factor for rated capacity
SMED Long, costly changeovers Cuts setup time and setup cost; lowers EOQ, cycle stock, and lead time; enables mixed-model scheduling
Standardized work Variation between operators and shifts Credible standard run times; stable routing data
5S Searching, motion, and space waste Shorter, repeatable handling elements; better location and count accuracy
Visual management and andon Problems surfacing too late Faster response, less scrap, hourly schedule adherence
Jidoka Defects repeated across a batch Higher first-pass yield; smaller scrap allowance; lower operator-to-machine ratio
Every row ends in a number you already use: setup time, run rate, yield, available capacity, lead time. A lean gain is banked only when it is re-entered into the item master, the routing, and the resource calendar - a 20-minute changeover still shown as 90 minutes keeps generating 1,342-unit orders, and a 77% OEE work center loaded as though it delivers eight clean hours keeps missing dates. Lean results show up as changed MRP and capacity parameters, not as posters on a wall.