13.2 Replenishment and DRP

APICS CPIM Certified in Planning and Inventory Management Exam

Track your progress as you read

Finished sections get a check mark.

1 Introduction & Exam Overview

1.1 Current Exam Facts 1.2 ECM 9.0 Domains and Weights 1.3 How to Study for CPIM

2 Supply Chain Strategy Foundations

2.1 Supply Chains, the Environment, and Strategy 2.2 Environment Analysis and Strategic Scope 2.3 Developing and Managing Organizational Strategy 2.4 Competitive Analysis: Five Forces, Benchmarking, and Value Chain

3 Strategy Performance and Operations Choices

3.1 Performance Monitoring and KPIs 3.2 Functional and Operational Strategies 3.3 Environments, Types, and Layouts 3.4 Service Process Design and Product-Process Trade-offs

4 Sales and Operations Planning

4.1 S&OP Purpose and Process 4.2 Aggregate Demand and Supply Plans 4.3 Reconciling S&OP Plans 4.4 Portfolio, New Product Introduction, and Life-Cycle Planning in S&OP 4.5 Strategic Buffers, Bottlenecks, and Capacity-Constrained Resources

5 Plan and Manage Demand

5.1 Demand Management 5.2 Sources of Demand and Forecasting 5.3 Forecast Performance 5.4 Marketing, Promotions, and Product Management 5.5 Qualitative, Associative, and AI-Driven Forecasting

6 Master Scheduling

6.1 Creating the Master Schedule 6.2 Rough-Cut Capacity Planning and MPS Validation 6.3 Using and Maintaining the Master Schedule 6.4 Planning Bills and Two-Level Master Scheduling 6.5 NPI, DFMA, Prototype, and End-of-Life Schedules

7 MRP, CRP, and Supply Disruptions

7.1 Material Requirements Planning 7.2 CRP, Order Promising, and Final Assembly Scheduling 7.3 Changes and Supply Disruptions 7.4 Product Costing and Variance Analysis for Planners

8 External Supply Sources

8.1 Suppliers and Procurement 8.2 Purchasing and Maintenance 8.3 Supply Chain Risk Management 8.4 Sourcing Footprint and Supplier Relationship Types 8.5 Supplier Release Mechanics and Inbound Logistics

9 Sustainability and Reverse Logistics

9.1 Sustainability Strategies 9.2 Waste Hierarchy and Reverse Logistics 9.3 Sustainability Standards, Reporting, and Life-Cycle Assessment

10 Inventory Planning and Costs

10.1 Inventory Planning 10.2 Inventory Costs, Accounting, Costing, and Metrics 10.3 EOQ, Reorder Point, and Safety Stock

11 Inventory Management and Control

11.1 Inventory Management Policies 11.2 Inventory Control 11.3 Service Levels and Inventory Tradeoffs 11.4 MRO Inventory and Maintenance Planning Inputs 11.5 Traceability Standards and Off-Site Inventory

12 Detailed Schedules and PAC

12.1 Planning Detailed Schedules 12.2 Scheduling and PAC Methods 12.3 Creating Production and Service Schedules 12.4 Managing Detailed Schedules and Scheduling Materials 12.5 Sequencing Rules, Lot Splitting, and Overlapped Scheduling 12.6 Capacity Types, Safety Capacity, and Labor Scheduling 12.7 Process Batches, Transfer Batches, and Backflushing

13 Plan and Manage Distribution

13.1 Planning Distribution 13.2 Replenishment and DRP 13.3 Order Management, Trace/Track, and KPIs

14 Quality and Business Investments

14.1 Quality Systems and Tools 14.2 Capital Equipment and Facilities 14.3 Technology in Planning and Inventory 14.4 The Seven Basic and Seven New Quality Tools 14.5 SPC Charts and Variation Types 14.6 Systems Requirements, Master Data, and Emerging Technologies

15 Continuous Improvement

15.1 Continuous Improvement Overview 15.2 Lean, JIT, and the Seven Wastes 15.3 Six Sigma, Kaizen, and Root Cause Tools 15.4 TPM, SMED, Standardized Work, and Visual Management

16 Integration and Exam Readiness

16.1 Planning Hierarchy Integration 16.2 High-Yield Calculations Drill 16.3 Exam Day, Scoring, and Credential Maintenance

13.2 Replenishment and DRP

Key Takeaways Explain This Topic AI

Distribution Requirements Planning (DRP) time-phases gross requirements, scheduled receipts, projected on-hand, and planned orders at each DC much like MRP does for components

DRP planned order releases at a DC become gross requirements (or supply demand) for the supplying plant or upstream DC

Fair-share allocation divides scarce supply among DCs by a rule such as equal days of supply; it is not a full time-phased requirements explosion

Time-Phased Order Point (TPOP) applies order-point thinking across a planning horizon using forecasted demand by period rather than a single static reorder point alone

DRP parameters—lead time, lot size, safety stock, and firm planned orders—drive whether DCs stay in stock without excess inventory

Last updated: July 2026

13.2 Replenishment and DRP

Quick Answer: Distribution Requirements Planning (DRP) is the time-phased planning technique that calculates when and how much to replenish each distribution center. Like MRP, it uses gross requirements, scheduled receipts, projected available, and planned order releases—except the “bill of distribution” links DCs and plants for finished goods rather than components.

After the network and push/pull philosophy are set, planners need a systematic way to replenish stocking locations. Domain VIII expects fluency with DRP , how it differs from simple fair-share allocation, and related time-phased order point (TPOP) ideas used when forecasts replace or supplement pure historical reorder points.

From Reorder Point to Time-Phased Replenishment

A classic reorder point (ROP) triggers a fixed or EOQ-sized replenishment when on-hand + on-order falls to a trigger level. That works for independent demand with stable lead time, but multi-echelon distribution with promotions, seasonality, and shared plant capacity needs visibility across periods .

Time-phased methods place demand and supply in buckets (days/weeks) so you can see future projected shortages before they hit. DRP is the distribution analog of MRP:

Element MRP (materials) DRP (distribution)

Independent demand Master schedule / customer orders for end items Forecasts and/or customer orders at DC/ship-from points

  • Structure Bill of materials Bill of distribution (sourcing paths plant ↔ DC ↔ DC)
  • Output Planned orders for components/manufacturing Planned replenishment orders for DCs / transfer orders
  • Lead time Manufacturing or purchasing LT Transit + receiving/processing LT between nodes
  • DRP Logic — Bucket by Bucket

For each SKU at each DC, DRP typically maintains:

Gross requirements — forecast, customer orders, or dependent demand from a downstream DC.

Scheduled receipts — open replenishment orders already released (in transit or firm).

Projected on-hand (projected available) — ending inventory each period after applying receipts and requirements, often after safety stock logic.

Net requirements — shortage relative to safety stock or zero policy.

Planned order receipts — lot-sized quantity planned to arrive to cover net needs.

Planned order releases — receipt date offset by replenishment lead time; these become the supply signal to the upstream source.

Bill of distribution

If Regional DC East is sourced from Central DC, then East’s planned order releases become gross requirements at Central for that SKU. Central’s releases become demand on the plant. This explosion is why DRP can overload a plant if every DC plans independently without capacity or allocation checks—S&OP and master scheduling must still reconcile total supply.

  • Worked DRP-Style Numeric Sketch
  • SKU: FG-100
  • Location: Regional DC West
  • Order quantity (lot size): 200 units
  • Safety stock: 40 units
  • Replenishment lead time: 1 week
  • Beginning on-hand (start of Week 1): 120 units
  • Scheduled receipt: 200 units arriving Week 1 (already released)

Weekly gross requirements (forecast):

  • Week 1 2 3 4 5
  • Gross requirements 90 100 95 110 100
  • Step-through (planner logic)
  • Week 1
  • Start: 120
  • Scheduled receipt 200 → available before demand = 320
  • − Gross requirements 90 → Projected on-hand = 230
  • 230 ≥ safety stock 40 → no new planned receipt
  • Week 2
  • Start 230 − 100 = 130 projected on-hand
  • Still above SS → no action
  • Week 3
  • Start 130 − 95 = 35 projected on-hand

35 < SS 40 → net need appears. Plan a planned order receipt of 200 (lot size) in Week 3 so projected on-hand becomes 35 + 200 = 235

  • Lead time 1 week → planned order release in Week 2 for 200
  • Week 4 (after applying the Week 3 receipt in the plan)
  • From 235 − 110 = 125 → above SS
  • Week 5
  • 125 − 100 = 25 → below SS → planned order receipt 200 in Week 5 → release in Week 4
  • Compact DRP grid (exam-style)
  • Row W1 W2 W3 W4 W5
  • Gross requirements 90 100 95 110 100
  • Scheduled receipts 200
  • Projected on-hand 230 130 235* 125 225*
  • Planned order receipts 200 200
  • Planned order releases 200 200

*After planned receipts covering safety stock policy.

Upstream implication: The plant (or central DC) must be able to ship 200 in Week 2 and Week 4. If plant capacity cannot, planners firm, reschedule, or allocate—DRP reveals the conflict early.

Common calculation traps

Forgetting to offset receipt by lead time (planning a same-week release when LT ≥ 1).

Ignoring safety stock (treating net requirements only when projected on-hand goes negative).

Changing lot size mid-horizon without restating prior planned orders.

Double-counting a scheduled receipt and a planned receipt for the same need.

  • Fair-Share vs DRP
  • Fair-share allocation answers: “We have limited supply now —how do we divide it among DCs?”
  • DRP answers: “Over the horizon, when will each DC need replenishment, and what should we release?”
  • Aspect Fair-share DRP
  • Time view Usually current constrained supply event Multi-period time-phased plan
  • Trigger Shortage / allocation meeting Ongoing planning run

Rule example Give each DC equal days of supply, or pro-rata to forecast Explode requirements with LT offset and lot sizing

  • Strength Equitable under scarcity; simple Anticipates future needs; links echelons
  • Weakness Not a full replenishment schedule Can overstate needs if forecasts poor; needs discipline

Example fair-share (days of supply): Available to allocate = 600. DC A forecast use/day = 40; DC B = 20. To equalize days of supply, give A twice what B gets (400 and 200) so both reach about 10 days. Fair-share does not replace DRP’s Week 3/Week 5 planned releases; it is a shortage response overlay.

Exam tip: if the vignette is about dividing today’s scarce stock , think fair-share. If it is about time-phased DC requirements and plant load , think DRP.

Time-Phased Order Point (TPOP)

TPOP blends order-point control with a planning horizon. Instead of watching only current inventory against a static ROP, the planner (or system) looks at projected inventory using period forecasts and plans replenishments so the projected balance does not breach the order point / safety level in future buckets.

Useful when demand is independent at the DC but varies by period (seasonality).

Still typically single-level (this location), whereas full DRP nests locations through the bill of distribution.

Relates to “planning without a BOM explosion” for distribution independent demand, while still gaining time-phased visibility.

Think of TPOP as: ROP logic + forecast buckets + lead-time offset . DRP extends further when multiple DCs and supplying DCs/plants must be synchronized.

Replenishment Parameters Planners Own

  • Parameter Effect if set too low Effect if set too high
  • Safety stock Stockouts, expedites Excess inventory, clogged DC
  • Lead time Late receipts, false urgency Early releases, excess pipeline
  • Lot size / FOQ Extra orders, high freight/setup Lumpy inventory, storage pressure
  • Forecast (gross req.) Chronic shortages Chronic overstock
  • Firm planned orders Needed for known events; over-firming reduces DRP flexibility
  • Push, Pull, and DRP Together

DRP can support pull-like behavior when gross requirements are heavily order-driven, or push-like behavior when forecasts and central planned orders dominate. Many systems run DRP, then apply fair-share when the summed DC planned releases exceed available plant supply for a period—DRP proposes need; allocation resolves conflict.

Study Focus

Be able to walk a small DRP table , state where the planned order release lands after lead-time offset, contrast fair-share (scarce supply split) with DRP (time-phased multi-echelon plan), and place TPOP as time-phased independent-demand replenishment without necessarily exploding a full distribution network.