6.2 Rough-Cut Capacity Planning and MPS Validation
APICS CPIM Certified in Planning and Inventory Management Exam
Track your progress as you read
Finished sections get a check mark.
1 Introduction & Exam Overview
1.1 Current Exam Facts 1.2 ECM 9.0 Domains and Weights 1.3 How to Study for CPIM
2 Supply Chain Strategy Foundations
2.1 Supply Chains, the Environment, and Strategy 2.2 Environment Analysis and Strategic Scope 2.3 Developing and Managing Organizational Strategy 2.4 Competitive Analysis: Five Forces, Benchmarking, and Value Chain
3 Strategy Performance and Operations Choices
3.1 Performance Monitoring and KPIs 3.2 Functional and Operational Strategies 3.3 Environments, Types, and Layouts 3.4 Service Process Design and Product-Process Trade-offs
4 Sales and Operations Planning
4.1 S&OP Purpose and Process 4.2 Aggregate Demand and Supply Plans 4.3 Reconciling S&OP Plans 4.4 Portfolio, New Product Introduction, and Life-Cycle Planning in S&OP 4.5 Strategic Buffers, Bottlenecks, and Capacity-Constrained Resources
5 Plan and Manage Demand
5.1 Demand Management 5.2 Sources of Demand and Forecasting 5.3 Forecast Performance 5.4 Marketing, Promotions, and Product Management 5.5 Qualitative, Associative, and AI-Driven Forecasting
6 Master Scheduling
6.1 Creating the Master Schedule 6.2 Rough-Cut Capacity Planning and MPS Validation 6.3 Using and Maintaining the Master Schedule 6.4 Planning Bills and Two-Level Master Scheduling 6.5 NPI, DFMA, Prototype, and End-of-Life Schedules
7 MRP, CRP, and Supply Disruptions
7.1 Material Requirements Planning 7.2 CRP, Order Promising, and Final Assembly Scheduling 7.3 Changes and Supply Disruptions 7.4 Product Costing and Variance Analysis for Planners
8 External Supply Sources
8.1 Suppliers and Procurement 8.2 Purchasing and Maintenance 8.3 Supply Chain Risk Management 8.4 Sourcing Footprint and Supplier Relationship Types 8.5 Supplier Release Mechanics and Inbound Logistics
9 Sustainability and Reverse Logistics
9.1 Sustainability Strategies 9.2 Waste Hierarchy and Reverse Logistics 9.3 Sustainability Standards, Reporting, and Life-Cycle Assessment
10 Inventory Planning and Costs
10.1 Inventory Planning 10.2 Inventory Costs, Accounting, Costing, and Metrics 10.3 EOQ, Reorder Point, and Safety Stock
11 Inventory Management and Control
11.1 Inventory Management Policies 11.2 Inventory Control 11.3 Service Levels and Inventory Tradeoffs 11.4 MRO Inventory and Maintenance Planning Inputs 11.5 Traceability Standards and Off-Site Inventory
12 Detailed Schedules and PAC
12.1 Planning Detailed Schedules 12.2 Scheduling and PAC Methods 12.3 Creating Production and Service Schedules 12.4 Managing Detailed Schedules and Scheduling Materials 12.5 Sequencing Rules, Lot Splitting, and Overlapped Scheduling 12.6 Capacity Types, Safety Capacity, and Labor Scheduling 12.7 Process Batches, Transfer Batches, and Backflushing
13 Plan and Manage Distribution
13.1 Planning Distribution 13.2 Replenishment and DRP 13.3 Order Management, Trace/Track, and KPIs
14 Quality and Business Investments
14.1 Quality Systems and Tools 14.2 Capital Equipment and Facilities 14.3 Technology in Planning and Inventory 14.4 The Seven Basic and Seven New Quality Tools 14.5 SPC Charts and Variation Types 14.6 Systems Requirements, Master Data, and Emerging Technologies
15 Continuous Improvement
15.1 Continuous Improvement Overview 15.2 Lean, JIT, and the Seven Wastes 15.3 Six Sigma, Kaizen, and Root Cause Tools 15.4 TPM, SMED, Standardized Work, and Visual Management
16 Integration and Exam Readiness
16.1 Planning Hierarchy Integration 16.2 High-Yield Calculations Drill 16.3 Exam Day, Scoring, and Credential Maintenance
6.2 Rough-Cut Capacity Planning and MPS Validation
Key Takeaways Explain This Topic AI
Rough-cut capacity planning (RCCP) tests whether a candidate MPS is approximately feasible on critical resources before the schedule is released to MRP.
Common RCCP methods include capacity planning using overall factors (CPOF), bill of resources (BOR), and resource profile approaches.
A bill of resources lists critical work centers (or other key resources) and the hours (or units of capacity) required per MPS item.
RCCP is faster and less detailed than capacity requirements planning (CRP); it validates the MPS, while CRP validates detailed open orders after MRP.
If RCCP shows overload, revise the MPS (or capacity) before exploding requirements—do not push an infeasible master schedule into MRP.
Last updated: July 2026
6.2 Rough-Cut Capacity Planning and MPS Validation
Quick Answer: Rough-cut capacity planning (RCCP) checks whether the proposed MPS overloads critical resources. It uses simplified load models—overall factors, bills of resources , or resource profiles—not the full routing detail of CRP. Fail RCCP → revise MPS or capacity; pass RCCP → release to MRP.
Section 6.1 produced a candidate master schedule that satisfied inventory and ATP logic. That is necessary but not sufficient. A schedule that books 500 units in a week when the bottleneck cell can only finish 320 is a fiction. RCCP is the bridge between master scheduling and material requirements planning: it asks, "Can the factory (and other critical resources) roughly absorb this MPS?"
Why Validate Before MRP?
MRP assumes the MPS is a valid statement of independent demand for the scheduled items. If the MPS is capacity-infeasible:
Component orders will be released on dates the plant cannot use.
Work-in-process and queues will explode at bottlenecks.
Planners will thrash priorities daily.
Customer promises based on ATP will fail even though ATP looked fine on paper.
CPIM framing: RCCP validates the MPS; CRP validates the detailed material plan / open shop orders. Mixing the two levels is a common exam trap.
Technique Planning level Detail Typical question
RCCP MPS Critical resources only; simplified Can we build this master schedule?
CRP After MRP Full routings, open orders, work centers Are released/ planned orders load-feasible?
- RCCP Methods You Must Recognize
- 1. Capacity Planning Using Overall Factors (CPOF)
CPOF is the simplest approach. Historical or engineered standard hours per unit (often a single plant-wide or family factor) are multiplied by MPS quantities, then spread to key resources using historical percentage splits.
Example: Family X historically needs 1.2 standard hours per unit , of which 40% hits Work Center 10 (WC10) and 25% hits WC20.
If MPS for Week 5 = 400 units:
- Total load = 400 × 1.2 = 480 hours
- WC10 load = 480 × 0.40 = 192 hours
- WC20 load = 480 × 0.25 = 120 hours
Compare each to available capacity (shifts × hours × utilization × efficiency, or demonstrated capacity). CPOF is fast but crude: it ignores product mix changes that alter the true resource split.
2. Bill of Resources (BOR)
A bill of resources (sometimes called a bill of capacity) lists, for each MPS item, the critical resources and the capacity required per unit —usually hours at bottleneck work centers, but sometimes key machines, labor grades, or even warehouse dock slots.
Example BOR for finished good FG-200:
- Critical resource Hours per FG-200
- WC10 (CNC cell) 0.50
- WC40 (Final assembly) 0.35
- Test bench T2 0.20
If the Week 6 MPS for FG-200 is 300 and for FG-300 (0.80 h on WC10, 0.25 h assembly, 0.15 h test) is 100 :
- WC10 load Week 6 = 300×0.50 + 100×0.80 = 150 + 80 = 230 hours
- Assembly load = 300×0.35 + 100×0.25 = 105 + 25 = 130 hours
- Test load = 300×0.20 + 100×0.15 = 60 + 15 = 75 hours
Suppose demonstrated weekly capacities are WC10 = 200 h, Assembly = 160 h, Test = 90 h. Then:
- Resource Load Capacity Status
- WC10 230 200 Overload 30 h (15%)
- Assembly 130 160 OK (81% load)
- Test 75 90 OK
Validation decision: The MPS is not feasible as written. Options include moving 60 FG-200 units to Week 7, overtime on WC10, alternate routing, or reducing FG-300 in Week 6. Only after the overload is cleared should the MPS be firmed.
3. Resource Profile Approach
Resource profiles extend the bill of resources across lead-time offsets . Capacity is not all consumed in the MPS completion week; fabrication hours may load two or three weeks earlier than final assembly.
If FG-200 needs 0.50 h on WC10 two weeks before completion and 0.35 h assembly in the completion week , then an MPS receipt of 300 in Week 8 loads:
- WC10 in Week 6 : 300 × 0.50 = 150 h
- Assembly in Week 8 : 300 × 0.35 = 105 h
This prevents the false comfort of looking only at the finish week when the bottleneck was already overloaded upstream.
Available Capacity in RCCP
Load is meaningless without a capacity definition. CPIM-relevant capacity ideas include:
- Theoretical capacity — clocks × machines, ignoring losses
- Rated / available capacity — adjusted for utilization
- Demonstrated capacity — what the resource has actually produced recently (often preferred for RCCP realism)
A compact formula often used:
Available hours = (machines) × (shifts) × (hours/shift) × (utilization) × (efficiency)
Example: 2 machines, 2 shifts, 8 hours, utilization 0.90, efficiency 0.95:
2 × 2 × 8 × 0.90 × 0.95 = 27.36 hours per day ; times 5 days ≈ 136.8 hours/week.
If MPS-driven load is 150 hours, RCCP flags overload even before detailed CRP.
Validation Workflow (MPS Gate)
Freeze a candidate MPS (quantities by item/period).
Select critical resources (Pareto: bottlenecks, constrained labor, long setups).
Explode MPS through CPOF, BOR, or resource profiles into load by period.
Compare load to available/demonstrated capacity.
If overloads exist: replan MPS (move mix, level load, change lot timing) or authorize capacity actions (overtime, extra shift, subcontract).
If balanced: approve MPS, update ATP, release to MRP.
Numeric Leveling Mini-Scenario
Weeks 5–7 MPS for a single bottleneck item (1.0 h each on WC10; capacity 200 h/week):
- Week Original MPS Load Capacity Action
- 5 260 260 200 Move 60 to Week 6
- 6 180 180→240 200 Move 40 to Week 7
- 7 100 100→140 200 OK
After moves: Week 5 = 200, Week 6 = 200, Week 7 = 140—all within capacity. Inventory and ATP must be recomputed after leveling because moving supply changes balances and promises.
What RCCP Does Not Do
It does not explode the full BOM or create purchase requisitions.
It does not schedule individual operations with setup matrices.
It does not replace finite scheduling on the shop floor.
It does not guarantee that every work center is feasible—only that selected critical resources look acceptable.
Those limitations are why CRP still exists later. For Domain IV master-scheduling questions, the scoring idea is: never release an obviously capacity-infeasible MPS to MRP .
Linking Back to ATP and Forward to MRP
After RCCP-driven MPS changes, recalculate ATP . A move of 60 units from Week 5 to Week 6 may free near-term ATP or create a promising hole. Once the MPS is capacity-validated and ATP refreshed, MRP can explode dependent demand with confidence that the independent-demand statement is operationally credible.
Master scheduling without RCCP is inventory arithmetic. Master scheduling with RCCP is operations management.