7.2 CRP, Order Promising, and Final Assembly Scheduling

APICS CPIM Certified in Planning and Inventory Management Exam

Track your progress as you read

Finished sections get a check mark.

1 Introduction & Exam Overview

1.1 Current Exam Facts 1.2 ECM 9.0 Domains and Weights 1.3 How to Study for CPIM

2 Supply Chain Strategy Foundations

2.1 Supply Chains, the Environment, and Strategy 2.2 Environment Analysis and Strategic Scope 2.3 Developing and Managing Organizational Strategy 2.4 Competitive Analysis: Five Forces, Benchmarking, and Value Chain

3 Strategy Performance and Operations Choices

3.1 Performance Monitoring and KPIs 3.2 Functional and Operational Strategies 3.3 Environments, Types, and Layouts 3.4 Service Process Design and Product-Process Trade-offs

4 Sales and Operations Planning

4.1 S&OP Purpose and Process 4.2 Aggregate Demand and Supply Plans 4.3 Reconciling S&OP Plans 4.4 Portfolio, New Product Introduction, and Life-Cycle Planning in S&OP 4.5 Strategic Buffers, Bottlenecks, and Capacity-Constrained Resources

5 Plan and Manage Demand

5.1 Demand Management 5.2 Sources of Demand and Forecasting 5.3 Forecast Performance 5.4 Marketing, Promotions, and Product Management 5.5 Qualitative, Associative, and AI-Driven Forecasting

6 Master Scheduling

6.1 Creating the Master Schedule 6.2 Rough-Cut Capacity Planning and MPS Validation 6.3 Using and Maintaining the Master Schedule 6.4 Planning Bills and Two-Level Master Scheduling 6.5 NPI, DFMA, Prototype, and End-of-Life Schedules

7 MRP, CRP, and Supply Disruptions

7.1 Material Requirements Planning 7.2 CRP, Order Promising, and Final Assembly Scheduling 7.3 Changes and Supply Disruptions 7.4 Product Costing and Variance Analysis for Planners

8 External Supply Sources

8.1 Suppliers and Procurement 8.2 Purchasing and Maintenance 8.3 Supply Chain Risk Management 8.4 Sourcing Footprint and Supplier Relationship Types 8.5 Supplier Release Mechanics and Inbound Logistics

9 Sustainability and Reverse Logistics

9.1 Sustainability Strategies 9.2 Waste Hierarchy and Reverse Logistics 9.3 Sustainability Standards, Reporting, and Life-Cycle Assessment

10 Inventory Planning and Costs

10.1 Inventory Planning 10.2 Inventory Costs, Accounting, Costing, and Metrics 10.3 EOQ, Reorder Point, and Safety Stock

11 Inventory Management and Control

11.1 Inventory Management Policies 11.2 Inventory Control 11.3 Service Levels and Inventory Tradeoffs 11.4 MRO Inventory and Maintenance Planning Inputs 11.5 Traceability Standards and Off-Site Inventory

12 Detailed Schedules and PAC

12.1 Planning Detailed Schedules 12.2 Scheduling and PAC Methods 12.3 Creating Production and Service Schedules 12.4 Managing Detailed Schedules and Scheduling Materials 12.5 Sequencing Rules, Lot Splitting, and Overlapped Scheduling 12.6 Capacity Types, Safety Capacity, and Labor Scheduling 12.7 Process Batches, Transfer Batches, and Backflushing

13 Plan and Manage Distribution

13.1 Planning Distribution 13.2 Replenishment and DRP 13.3 Order Management, Trace/Track, and KPIs

14 Quality and Business Investments

14.1 Quality Systems and Tools 14.2 Capital Equipment and Facilities 14.3 Technology in Planning and Inventory 14.4 The Seven Basic and Seven New Quality Tools 14.5 SPC Charts and Variation Types 14.6 Systems Requirements, Master Data, and Emerging Technologies

15 Continuous Improvement

15.1 Continuous Improvement Overview 15.2 Lean, JIT, and the Seven Wastes 15.3 Six Sigma, Kaizen, and Root Cause Tools 15.4 TPM, SMED, Standardized Work, and Visual Management

16 Integration and Exam Readiness

16.1 Planning Hierarchy Integration 16.2 High-Yield Calculations Drill 16.3 Exam Day, Scoring, and Credential Maintenance

7.2 CRP, Order Promising, and Final Assembly Scheduling

Key Takeaways Explain This Topic AI

Capacity Requirements Planning (CRP) uses MRP planned and open orders to build time-phased load profiles at the work-center level; Rough-Cut Capacity Planning (RCCP) validates the MPS at a higher, bill-of-resources level.

A load profile compares required hours to available capacity by period and highlights overloads, underloads, and leveling opportunities.

Final Assembly Scheduling (FAS) is the short-horizon schedule that configures and completes assemble-to-order (ATO) products from modules and options after the customer order is known.

Order promising uses ATP (and often CTP) logic to commit delivery dates without double-selling scarce supply or capacity.

CRP does not replace finite scheduling; it signals where planners must replan supply, shift lots, authorize overtime, or alternate routings before execution.

Last updated: July 2026

Quick Answer: RCCP checks whether the MPS is roughly feasible using critical resources and a bill of resources. CRP then explodes MRP orders through routings to create detailed, time-phased load profiles by work center. In assemble-to-order environments, final assembly scheduling (FAS) finishes customer-specific configurations, while order promising commits dates using ATP/CTP so sales does not over-allocate supply or capacity.

Material plans that ignore capacity create false due dates. CPIM Domain IV links MRP to capacity validation and to the commercial promise made to the customer. You must know what each capacity tool assumes, how load is calculated, and how ATO fulfillment differs from make-to-stock master scheduling.

CRP versus RCCP

  • Dimension Rough-Cut Capacity Planning (RCCP) Capacity Requirements Planning (CRP)
  • Planning level MPS / end-item oriented MRP / component and open-order oriented

Resource detail Critical work centers or bottleneck families; bill of resources Detailed work centers from routings

Timing precision Approximate buckets; may ignore some lead-time offsets Time-phased using operation lead times and order dates

Purpose Accept or revise the MPS before deep planning Validate or adjust detailed material plans and open orders

Typical trigger After MPS changes in S&OP / master scheduling After MRP regeneration or net change

RCCP asks: “If we build this master schedule, will our key resources survive?” CRP asks: “Given the planned and open orders MRP just produced, where are the work-center overloads by week?” Passing RCCP does not guarantee CRP will be clean—component lot sizes, overlapping orders, and scrap can still stack load into the same bucket.

How CRP Builds Load

For each manufacturing order (planned or released), CRP:

Reads the routing (sequence of operations and work centers).

Multiplies order quantity by setup + run time (and sometimes move/queue estimates, depending on the system’s capacity model).

Places those hours into time buckets based on operation start/due logic derived from the order due date and lead-time offsets.

Sums hours by work center and period into a load profile .

Compares load to available capacity (shifts × crew × efficiency × utilization, minus planned downtime).

Required capacity (hours) ≈ setup time + (run time per piece × order quantity)

Available capacity (hours) ≈ rated hours × utilization × efficiency (definitions vary by firm; exam stems usually give the factors explicitly).

Load Profiles: Reading the Signal

A load profile is a period-by-period chart or table of load versus capacity at a work center.

  • Week Load (hrs) Capacity (hrs) Load percent Planner reading
  • 1 320 400 80% Underload — pull work forward or reduce overtime plans
  • 2 410 400 102% Mild overload — small lot split or minor overtime
  • 3 520 400 130% Significant overload — replan dates, alternate WC, or subcontract
  • 4 280 400 70% Valley — candidate for leveling from week 3

Overload is not automatically “add overtime.” CPIM-consistent responses include revising order dates , splitting lots , using alternate routings , selecting alternate work centers , outsourcing , changing lot sizes , or adjusting the MPS if the overload is structural. Underload may justify pulling firm demand forward only when material ATP and upstream capacity allow it.

Infinite versus Finite Assumptions

Traditional regenerative CRP is often infinite loading : it shows overload rather than automatically delaying orders. Finite scheduling / finite capacity tools sequence operations so load never exceeds capacity, pushing completion dates out. On the exam, if a question describes CRP producing an overload percentage, the system is signaling a problem for planner action—not silently promising the original due date as feasible.

Final Assembly Scheduling (FAS) for ATO

In assemble-to-order (ATO) environments, modules and options are often planned by MRP/MPS as buildable stock or short-horizon supply, while the final customer configuration is completed only after the order arrives. The final assembly schedule (FAS) is that short-term completion schedule.

  • MTS master schedule focus ATO final assembly focus
  • Build finished goods to forecast / demand plan Configure and assemble to customer order
  • End-item MPS drives deep MRP FAS consumes modules/options; MRP still plans lower levels
  • Inventory of finished SKUs Inventory of common modules, options, and hardware
  • Longer freeze on end-item mix Freeze or firm zone on FAS near shipment

FAS responsibilities:

Translate configured sales orders into assembly orders.

Sequence final assembly lines by due date, changeover cost, and material readiness.

Coordinate with order promising so quoted dates match module ATP and line capacity.

Firm near-term FAS entries to stop MRP nervousness from reshuffling the line.

A classic exam contrast: changing the MPS for a make-to-stock end item replans the whole structure; changing an ATO customer options mix primarily hits FAS and the option-level supply, not necessarily every unrelated module if common parts remain stable.

Order Promising: ATP and CTP

Order promising is the process of committing a delivery quantity and date to a customer. Two related calculations dominate CPIM language:

Method Basis When it fits

Available-to-Promise (ATP) Uncommitted finished (or module) supply from MPS receipts / on-hand across the horizon Make-to-stock and module-stocked ATO

Capable-to-Promise (CTP) Checks material and capacity (and sometimes supplier capability) to create a feasible commit Tight capacity, custom ATO/MTO, or when ATP alone would overpromise

Simplified discrete ATP idea for a period:

ATP = on-hand (first bucket) or MPS receipt − sum of actual customer orders already booked until the next MPS receipt

(Exact ATP formulas vary—cumulative ATP versus discrete ATP—but the exam concept is the same: do not promise what is already sold.)

Good promising practice:

Promise against ATP , not against total inventory or total MPS volume.

Escalate to CTP when assembly capacity or critical components constrain the FAS.

Keep a demand time fence / policy so near-term FAS and promises are planner-controlled.

When supply is short, allocate by policy (fair share, priority customers, margin)—do not silently double-book.

Worked Mini-Scenario (ATO Promise)

A configure-to-order pump uses a common motor module. Week 2 ATP for motors is 25 . The final assembly line has 40 hours free in week 2; each pump needs 1 hour of final assembly. A customer requests 30 pumps in week 2.

Material ATP supports only 25 → promise 25 in week 2 unless CTP finds earlier module expediting.

Capacity would allow 30, but material is the constraint → promising 30 would create a FAS that MRP/CRP cannot honestly support.

Planner options: split ship (25 then 5), substitute an alternate motor with its own ATP, or move the order to week 3 where ATP recovers.

Linking CRP, FAS, and Promising

MPS / module plan validated with RCCP .

MRP plans components; CRP flags work-center load issues.

Sales books orders using ATP/CTP .

FAS sequences actual configurations in the short horizon.

Overloads or ATP breaches trigger replanning—not silent overtime assumptions—unless policy authorizes them.

Exam Pitfalls

Treating RCCP and CRP as interchangeable detail levels.

Reading a CRP overload as proof the schedule is impossible without considering alternate routings or date moves.

Promising from on-hand + open orders without subtracting committed customer orders (ATP discipline).

Assuming FAS replaces MRP in ATO—FAS finishes the product; MRP still plans modules and lower levels.