Study guide

4.3 Attribute Control Charts

Certified Quality Engineer CQE

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Management and Leadership

1.1 Quality Philosophies & Foundations 1.2 Leadership & Organizational Systems 1.3 ASQ Code of Ethics & Professional Standards 1.4 Strategic Planning & Deployment 1.5 Management Infrastructure & Project Management 1.6 Quality Information Systems & Communication 1.7 Financial & Cost of Quality

2 Chapter 2: The Quality System

2.1 Quality Management System Elements & Standards 2.2 Quality Documentation Architecture 2.3 Quality Auditing Principles & Types 2.4 Audit Planning, Execution & Reporting 2.5 Corrective Action & Preventive Action Systems 2.6 Supplier Quality Management 2.7 Customer Relations & Customer Value 2.8 Quality Training Program Design & Effectiveness

3 Chapter 3: Product, Process, and Service Design

3.1 Design Input & Requirements 3.2 Design Review & Verification 3.3 Failure Mode and Effects Analysis 3.4 Design of Experiments Foundations 3.5 Robust Design & Taguchi Methods 3.6 Reliability & Maintainability Concepts 3.7 Reliability Modeling & System Evaluation 3.8 Technical Drawings, Specifications & GD&T

4 Chapter 4: Product and Process Control

4.1 Statistical Process Control Principles 4.2 Variable Control Charts 4.3 Attribute Control Charts 4.4 Process Capability & Performance Analysis 4.5 Acceptance Sampling Plans & Standards 4.6 Metrology, Calibration & Measurement Uncertainty 4.7 Measurement System Analysis (MSA) 4.8 Material Control, Traceability & MRB

5 Chapter 5: Continuous Improvement

5.1 Continuous Improvement Methodologies 5.2 Classic Quality Tools 5.3 Management & Planning Tools 5.4 Lean Tools & Waste Elimination 5.5 Problem-Solving Methodologies & Root Cause Analysis 5.6 Risk Management & Assessment 5.7 Change Management & Team Facilitation

6 Chapter 6: Quantitative Methods and Tools

6.1 Descriptive Statistics & Data Summarization 6.2 Probability Concepts & Distributions 6.3 Sampling Distributions & Central Limit Theorem 6.4 Point & Interval Estimation 6.5 Hypothesis Testing Fundamentals 6.6 Specific Statistical Tests 6.7 Regression & Correlation Analysis

7 Chapter 7: Risk Management & Advanced Quality Engineering

7.1 Risk Identification & Hazard Analysis 7.2 Quantitative Risk Analysis & Modeling 7.3 Risk Mitigation & Control Planning 7.4 Special Process Control & Advanced SPC 7.5 Advanced Statistical Design & Analysis 7.6 Computer Applications & Quality Engineering Software

4.3 Attribute Control Charts

Key Takeaways Explain This Topic AI

Attribute control charts track discrete qualitative data, divided into nonconforming items / defectives (binomial distribution: p-chart, np-chart) and count of nonconformities / defects (poisson distribution: c-chart, u-chart).

The p-chart measures the proportion of nonconforming units across constant or variable sample sizes, whereas the np-chart measures the total count of nonconforming units for strictly constant sample sizes.

The c-chart monitors nonconformity counts across a constant unit/area of opportunity, whereas the u-chart monitors nonconformities per unit across variable sample sizes or varying areas of opportunity.

If a calculated lower control limit (LCL) yields a negative value for p, np, c, or u charts, it must be truncated to zero (LCL = 0) because discrete attribute counts and proportions cannot be negative.

Last updated: July 2026

4.3 Attribute Control Charts

Attribute control charts evaluate discrete qualitative quality characteristics—such as go/no-go gauging, pass/fail functional tests, surface visual blemishes, or clerical errors. Attribute charts monitor process stability when quantitative variable measurements are either impossible or cost-prohibitive to obtain.

Attribute Classification: Defectives vs. Defects

Selecting the correct attribute chart requires distinguishing between two distinct statistical distributions:

Nonconforming Unit (Defective / Binomial Distribution):

Refers to an entire product or assembly that fails to meet specification requirements (e.g., a cracked casting, a leaking container, an non-functional PCB).

Outcome is binary: conforming (0) or nonconforming (1).

Governed by the Binomial Distribution .

Associated Control Charts: p-chart and np-chart .

Nonconformity (Defect / Poisson Distribution):

Refers to an individual flaw or failure instance on an item (e.g., scratches on an appliance door, solder bridges, paint runs, invoice typos).

A single item can contain multiple nonconformities.

Governed by the Poisson Distribution (counting independent occurrences over a continuous area of opportunity).

Associated Control Charts: c-chart and u-chart .

Attribute Control Chart Selection Framework

Metric Type Underlying Distribution Sample Size ((n)) Chart Type Centerline Standard Error ( σ \sigma σ )

Fraction Nonconforming Binomial Variable or Constant p p ˉ = ∑ d i ∑ n i \bar{p} = \frac{\sum d_i}{\sum n_i} p ˉ ​ = ∑ n i ​ ∑ d i ​ ​ p ˉ ( 1 − p ˉ ) n i \sqrt{\frac{\bar{p}(1-\bar{p})}{n_i}} n i ​ p ˉ ​ ( 1 − p ˉ ​ ) ​ ​

Number Nonconforming Binomial Strictly Constant ( n i = n n_i = n n i ​ = n ) np n p ˉ = ∑ d i k \bar{np} = \frac{\sum d_i}{k} n p ˉ ​ = k ∑ d i ​ ​ n p ˉ ( 1 − p ˉ ) \sqrt{n\bar{p}(1-\bar{p})} n p ˉ ​ ( 1 − p ˉ ​ ) ​

Count of Defects Poisson Strictly Constant Area ((n=1)) c c ˉ = ∑ c i k \bar{c} = \frac{\sum c_i}{k} c ˉ = k ∑ c i ​ ​ c ˉ \sqrt{\bar{c}} c ˉ ​

Defects Per Unit Poisson Variable Area ( n i n_i n i ​ ) u u ˉ = ∑ c i ∑ n i \bar{u} = \frac{\sum c_i}{\sum n_i} u ˉ = ∑ n i ​ ∑ c i ​ ​ u ˉ n i \sqrt{\frac{\bar{u}}{n_i}} n i ​ u ˉ ​ ​

  • Mathematical Formulas and Worked Calculations
  • 1. p-Chart (Fraction Nonconforming)

Monitors the proportion (p) of defective units in samples of size n i n_i n i ​ . When subgroup size n i n_i n i ​ varies, control limits must be calculated individually for each sample size. Centerline: p ˉ = Total Defective Units Total Inspected Units = ∑ i = 1 k d i ∑ i = 1 k n i \text{Centerline: } \bar{p} = \frac{\text{Total Defective Units}}{\text{Total Inspected Units}} = \frac{\sum_{i=1}^k d_i}{\sum_{i=1}^k n_i} Centerline: p ˉ ​ = Total Inspected Units Total Defective Units ​ = ∑ i = 1 k ​ n i ​ ∑ i = 1 k ​ d i ​ ​ U C L p = p ˉ + 3 p ˉ ( 1 − p ˉ ) n i , L C L p = max ⁡ ( 0 , p ˉ − 3 p ˉ ( 1 − p ˉ ) n i ) UCL_p = \bar{p} + 3 \sqrt{\frac{\bar{p}(1-\bar{p})}{n_i}}, \quad LCL_p = \max\left(0, \, \bar{p} - 3 \sqrt{\frac{\bar{p}(1-\bar{p})}{n_i}}\right) U C L p ​ = p ˉ ​ + 3 n i ​ p ˉ ​ ( 1 − p ˉ ​ ) ​ ​ , L C L p ​ = max ​ 0 , p ˉ ​ − 3 n i ​ p ˉ ​ ( 1 − p ˉ ​ ) ​ ​ ​

Worked Example: p-Chart with Constant Sample Size

An electronics plant inspects (k = 20) lots of (n = 500) circuit boards each. A total of (d = 150) defective boards are detected across all lots.

Calculate Average Proportion Defective ( p ˉ \bar{p} p ˉ ​ ): p ˉ = 150 20 × 500 = 150 10 , 000 = 0.0150 \bar{p} = \frac{150}{20 \times 500} = \frac{150}{10,000} = 0.0150 p ˉ ​ = 20 × 500 150 ​ = 10 , 000 150 ​ = 0.0150

Calculate Control Limits: SE p = 0.0150 × ( 1 − 0.0150 ) 500 = 0.014775 500 = 0.00002955 = 0.005436 \text{SE}_p = \sqrt{\frac{0.0150 \times (1 - 0.0150)}{500}} = \sqrt{\frac{0.014775}{500}} = \sqrt{0.00002955} = 0.005436 SE p ​ = 500 0.0150 × ( 1 − 0.0150 ) ​ ​ = 500 0.014775 ​ ​ = 0.00002955 ​ = 0.005436 U C L p = 0.0150 + 3 ( 0.005436 ) = 0.0150 + 0.01631 = 0.03131 (or 3.13%) UCL_p = 0.0150 + 3(0.005436) = 0.0150 + 0.01631 = 0.03131 \text{ (or 3.13\%)} U C L p ​ = 0.0150 + 3 ( 0.005436 ) = 0.0150 + 0.01631 = 0.03131 (or 3.13%) L C L p = 0.0150 − 0.01631 = − 0.00131 → 0.0000 (truncated to zero) LCL_p = 0.0150 - 0.01631 = -0.00131 \rightarrow \mathbf{0.0000} \text{ (truncated to zero)} L C L p ​ = 0.0150 − 0.01631 = − 0.00131 → 0.0000 (truncated to zero)

2. np-Chart (Number Nonconforming)

Monitors actual count of defective items. Subgroup size (n) must be strictly constant across all samples. Centerline: n p ˉ = ∑ d i k \text{Centerline: } \bar{np} = \frac{\sum d_i}{k} Centerline: n p ˉ ​ = k ∑ d i ​ ​ U C L n p = n p ˉ + 3 n p ˉ ( 1 − p ˉ ) , L C L n p = max ⁡ ( 0 , n p ˉ − 3 n p ˉ ( 1 − p ˉ ) ) UCL_{np} = \bar{np} + 3 \sqrt{\bar{np}(1-\bar{p})}, \quad LCL_{np} = \max\left(0, \, \bar{np} - 3 \sqrt{\bar{np}(1-\bar{p})}\right) U C L n p ​ = n p ˉ ​ + 3 n p ˉ ​ ( 1 − p ˉ ​ ) ​ , L C L n p ​ = max ( 0 , n p ˉ ​ − 3 n p ˉ ​ ( 1 − p ˉ ​ ) ​ )

Worked Example: np-Chart

Using data from above ((n = 500), p ˉ = 0.0150 \bar{p} = 0.0150 p ˉ ​ = 0.0150 , n p ˉ = 500 × 0.0150 = 7.50 \bar{np} = 500 \times 0.0150 = 7.50 n p ˉ ​ = 500 × 0.0150 = 7.50 defectives per lot): SE n p = 7.50 × ( 1 − 0.0150 ) = 7.3875 = 2.718 \text{SE}_{np} = \sqrt{7.50 \times (1 - 0.0150)} = \sqrt{7.3875} = 2.718 SE n p ​ = 7.50 × ( 1 − 0.0150 ) ​ = 7.3875 ​ = 2.718 U C L n p = 7.50 + 3 ( 2.718 ) = 7.50 + 8.154 = 15.654 defective units UCL_{np} = 7.50 + 3(2.718) = 7.50 + 8.154 = 15.654 \text{ defective units} U C L n p ​ = 7.50 + 3 ( 2.718 ) = 7.50 + 8.154 = 15.654 defective units L C L n p = 7.50 − 8.154 = − 0.654 → 0 defective units LCL_{np} = 7.50 - 8.154 = -0.654 \rightarrow \mathbf{0} \text{ defective units} L C L n p ​ = 7.50 − 8.154 = − 0.654 → 0 defective units

3. c-Chart (Count of Nonconformities)

Monitors total defect counts (c) in a fixed inspection unit or area of opportunity (e.g., defects per single vehicle body panel). Centerline: c ˉ = ∑ i = 1 k c i k \text{Centerline: } \bar{c} = \frac{\sum_{i=1}^k c_i}{k} Centerline: c ˉ = k ∑ i = 1 k ​ c i ​ ​ U C L c = c ˉ + 3 c ˉ , L C L c = max ⁡ ( 0 , c ˉ − 3 c ˉ ) UCL_c = \bar{c} + 3 \sqrt{\bar{c}}, \quad LCL_c = \max\left(0, \, \bar{c} - 3 \sqrt{\bar{c}}\right) U C L c ​ = c ˉ + 3 c ˉ ​ , L C L c ​ = max ( 0 , c ˉ − 3 c ˉ ​ )

Worked Example: c-Chart

A textile mill inspects (k = 25) standard fabric rolls (1 roll = 1 unit). Total defects observed across all rolls is ∑ c i = 100 \sum c_i = 100 ∑ c i ​ = 100 .

Centerline ( c ˉ \bar{c} c ˉ ): c ˉ = 100 25 = 4.00 defects per roll \bar{c} = \frac{100}{25} = 4.00 \text{ defects per roll} c ˉ = 25 100 ​ = 4.00 defects per roll

Control Limits: U C L c = 4.00 + 3 4.00 = 4.00 + 3 ( 2.00 ) = 10.00 defects UCL_c = 4.00 + 3\sqrt{4.00} = 4.00 + 3(2.00) = 10.00 \text{ defects} U C L c ​ = 4.00 + 3 4.00 ​ = 4.00 + 3 ( 2.00 ) = 10.00 defects L C L c = 4.00 − 3 ( 2.00 ) = 4.00 − 6.00 = − 2.00 → 0 defects LCL_c = 4.00 - 3(2.00) = 4.00 - 6.00 = -2.00 \rightarrow \mathbf{0} \text{ defects} L C L c ​ = 4.00 − 3 ( 2.00 ) = 4.00 − 6.00 = − 2.00 → 0 defects

4. u-Chart (Nonconformities Per Unit)

Monitors average defects per unit (u) when sample size n i n_i n i ​ (number of inspection units per subgroup) varies. Centerline: u ˉ = Total Defects Total Inspected Units = ∑ i = 1 k c i ∑ i = 1 k n i \text{Centerline: } \bar{u} = \frac{\text{Total Defects}}{\text{Total Inspected Units}} = \frac{\sum_{i=1}^k c_i}{\sum_{i=1}^k n_i} Centerline: u ˉ = Total Inspected Units Total Defects ​ = ∑ i = 1 k ​ n i ​ ∑ i = 1 k ​ c i ​ ​ U C L u = u ˉ + 3 u ˉ n i , L C L u = max ⁡ ( 0 , u ˉ − 3 u ˉ n i ) UCL_u = \bar{u} + 3 \sqrt{\frac{\bar{u}}{n_i}}, \quad LCL_u = \max\left(0, \, \bar{u} - 3 \sqrt{\frac{\bar{u}}{n_i}}\right) U C L u ​ = u ˉ + 3 n i ​ u ˉ ​ ​ , L C L u ​ = max ( 0 , u ˉ − 3 n i ​ u ˉ ​ ​ )

Worked Example: u-Chart

An automotive plant inspects painted vehicle panels over (k = 10) shifts. Total inspected panels (= 500), total paint defects (= 250).

Average Defects per Unit ( u ˉ \bar{u} u ˉ ): u ˉ = 250 500 = 0.500 defects per panel \bar{u} = \frac{250}{500} = 0.500 \text{ defects per panel} u ˉ = 500 250 ​ = 0.500 defects per panel

Control Limits for a shift where (n = 50) panels were inspected: U C L u = 0.500 + 3 0.500 50 = 0.500 + 3 0.010 = 0.500 + 3 ( 0.100 ) = 0.800 defects/panel UCL_u = 0.500 + 3 \sqrt{\frac{0.500}{50}} = 0.500 + 3\sqrt{0.010} = 0.500 + 3(0.100) = 0.800 \text{ defects/panel} U C L u ​ = 0.500 + 3 50 0.500 ​ ​ = 0.500 + 3 0.010 ​ = 0.500 + 3 ( 0.100 ) = 0.800 defects/panel L C L u = 0.500 − 0.300 = 0.200 defects/panel LCL_u = 0.500 - 0.300 = 0.200 \text{ defects/panel} L C L u ​ = 0.500 − 0.300 = 0.200 defects/panel