Study guide

DPU, RTY, CoPQ, DPMO & Sigma Level

ASQ Certified Six Sigma Green Belt CSSGB

Track your progress as you read

Finished sections get a check mark.

1 Introduction & Exam Overview

CSSGB Exam Facts & Logistics How to Study for an Open-Book ASQ Exam

2 Six Sigma Foundations

Value of Six Sigma & Quality Leaders Organizational Goals & Six Sigma Projects Organizational Drivers, KPIs & Scorecards

3 Lean Principles in the Organization

Lean Concepts Value Stream Mapping & Waste

4 Design for Six Sigma

DFSS Road Maps: DMADV & IDOV FMEA Basics & Risk Priority Number Design FMEA vs Process FMEA

5 Define: Project Identification

Project Selection & DMAIC Fit Process Elements & Boundaries Benchmarking Types SIPOC & Process Inputs/Outputs

6 Stakeholders & Voice of the Customer

Owners & Stakeholders Customer Identification Customer Data Collection CTQ, QFD & Kano

7 Project Management Core

Agile & Top-Down Project Methods Project Charter & Problem Statements Project Scope Tools Primary & Consequential Metrics

8 Planning, Risk & Closure

WBS, Gantt, CPM, PERT & Tollgates Project Documentation Project Risk Analysis & Management Project Closure & Lessons Learned

9 Management Tools & Business Results

Eight Management & Planning Tools DPU, RTY, CoPQ, DPMO & Sigma Level Organizational Communication

10 Team Dynamics & Performance

Team Stages & Negative Dynamics Six Sigma Roles & RACI Brainstorming, NGT & Multivoting Team Communication

11 Measure: Process & Probability

Process Maps & Documentation Basic Probability Concepts Central Limit Theorem

12 Distributions & Data Collection

Statistical Distributions Data Types & Measurement Scales Sampling & Data Collection Plans Descriptive Statistics

13 Graphical Methods & MSA

Graphical Methods Measurement System Analysis & Gage R&R Bias, Linearity, Stability & P/T

14 Process & Performance Capability

Process Performance vs Specifications Process Capability Studies Cp, Cpk, Pp, Ppk & Cpm Short-Term vs Long-Term Capability & Sigma Shift

15 Analyze: Exploratory Data Analysis

Multi-Vari Studies Correlation & Linear Regression

16 Hypothesis Testing

Hypothesis Testing Basics Tests for Means, Variances & Proportions

17 Gap & Root Cause Analysis

Gap Analysis Root Cause Analysis Tools

18 Design of Experiments

DoE Basic Terms Main Effects & Interaction Plots

19 Implementation Planning & Lean Tools

Implementation Planning & Pilots Waste Elimination Tools Cycle-Time Reduction & SMED Kaizen & Kaizen Blitz

20 Statistical Process Control

SPC Basics: Common vs Special Cause Rational Subgrouping Control Chart Selection & Construction

21 Sustaining Improvements & Lean Control

Control Plans Document Control, Training & Audits Plan-Do-Check-Act (PDCA) TPM & Visual Factory

DPU, RTY, CoPQ, DPMO & Sigma Level

Key Takeaways Explain This Topic AI

DPU equals total defects divided by total units; a unit can have more than one defect.

RTY multiplies step yields (or uses e^(−DPU) for complex flow) to show the probability a unit passes all steps defect-free.

CoPQ is the cost of internal and external failure (and often appraisal/prevention framing in broader COQ models).

DPMO normalizes defects by opportunities so processes with different complexity can be compared; sigma level maps from DPMO.

Capability indices (Cp, Cpk, Pp, Ppk) compare process spread and centering to specifications; track metrics to drive decisions.

Last updated: July 2026

DPU, RTY, CoPQ, DPMO & Sigma Level (CSSGB BoK II.E.1 — Analyze)

Quick Answer: DPU = defects ÷ units. RTY multiplies successive process yields to estimate end-to-end first-pass success. CoPQ monetizes failure and poor quality. DPMO = (defects ÷ (units × opportunities)) × 1,000,000 and converts to a sigma level . Capability indices compare variation to specs. Green Belts calculate these metrics, trend them, and use them to prioritize and validate improvements.

BoK II.E.1 is at the Analyze level: compute metrics from given numbers, interpret what they mean for the business, and avoid confusing defects with defectives or short-term with long-term sigma.

Why Process Performance Metrics Matter

Champions fund projects that move business results . Process performance metrics translate process pain into numbers leaders understand—defect load, yield loss, quality cost, and sigma capability. They also let teams compare before/after states with a common language.

Metric Question it answers

DPU How many defects per unit on average?

RTY What fraction of units make it through all steps without rework/scrap paths?

CoPQ How much money does poor quality cost?

DPMO / sigma How capable is the process when normalized by opportunities?

Cp/Cpk (overview) How does process spread and centering compare to specifications?

Defects, Defectives, Opportunities

A defect is a single nonconformance to a requirement (scratch, missing field, late milestone).

A defective is a unit that has one or more defects (a bad unit).

An opportunity is a chance for a defect to occur—defined consistently (e.g., each critical characteristic on a part, each data field on a form).

Never mix definitions mid-project. If Measure defines five CTQ opportunities per order, Control must use the same five when computing DPMO.

DPU — Defects Per Unit DPU = Total number of defects Total number of units \text{DPU} = \frac{\text{Total number of defects}}{\text{Total number of units}} DPU = Total number of units Total number of defects ​

DPU can exceed 1.0 when units often have multiple defects.

Worked example (DPU)

Inspection of 200 circuit boards finds 46 defects (some boards had several issues). DPU = 46 200 = 0.23 \text{DPU} = \frac{46}{200} = 0.23 DPU = 200 46 ​ = 0.23

Interpretation: on average, 0.23 defects per board . If 38 boards were defective, the defective rate is 38/200 = 19%, which is not the same as DPU.

Throughput Yield and Rolled Throughput Yield (RTY)

Throughput yield (TY) at a step is the proportion of units that pass that step without rework or scrap (first-pass yield for the step).

Rolled throughput yield (RTY) for a multi-step process is the product of the step yields when steps are sequential and independent in the yield sense: RTY = Y 1 × Y 2 × ⋯ × Y n \text{RTY} = Y_1 \times Y_2 \times \cdots \times Y_n RTY = Y 1 ​ × Y 2 ​ × ⋯ × Y n ​

When average DPU for a process (or step) is known and defects follow a Poisson model, a common approximation is: Y ≈ e − DPU Y \approx e^{-\text{DPU}} Y ≈ e − DPU

Worked example (RTY)

A three-step process has first-pass yields:

  • Step 1: 95% (0.95)
  • Step 2: 90% (0.90)

Step 3: 98% (0.98) RTY = 0.95 × 0.90 × 0.98 = 0.8379 ≈ 83.8 % \text{RTY} = 0.95 \times 0.90 \times 0.98 = 0.8379 \approx 83.8\% RTY = 0.95 × 0.90 × 0.98 = 0.8379 ≈ 83.8%

Even though each step looks “pretty good,” only about 84% of units traverse all three steps defect-free on the first pass. Hidden factory rework is the rest. For 1,000 starts, roughly 162 units experience at least one failure path—strong justification for a project.

Exam tip: Multiplying yields (RTY) is stricter than averaging them. Average yield (0.95+0.90+0.98)/3 = 94.3% overstates end-to-end performance.

Cost of Poor Quality (CoPQ)

CoPQ (and the broader cost of quality model) monetizes quality-related costs. Classic categories:

  • Category Examples
  • Internal failure Scrap, rework, re-inspection, downtime from defects
  • External failure Warranty, returns, complaints, lost customers, penalties
  • Appraisal Inspection, testing, audits
  • Prevention Training, mistake-proofing, process design, SPC

Many deployments treat failure costs (internal + external) as the primary CoPQ target for DMAIC projects; prevention and appraisal investments often rise short-term to drive failure costs down long-term.

Simple CoPQ framing example

Monthly: scrap $40,000; rework labor $25,000; warranty $18,000; expedited freight for quality escapes $7,000. Monthly CoPQ (failure) = 40,000 + 25,000 + 18,000 + 7,000 = $ 90,000 \text{Monthly CoPQ (failure)} = 40{,}000 + 25{,}000 + 18{,}000 + 7{,}000 = \$90{,}000 Monthly CoPQ (failure) = 40 , 000 + 25 , 000 + 18 , 000 + 7 , 000 = $90 , 000

Annualized ≈ $1.08M . A project that cuts failure CoPQ 30% with verified Control is a clear business case—tie charter savings to these line items, not vague “efficiency.”

DPMO and Sigma Level

Defects Per Million Opportunities (DPMO) : DPMO = ( Number of defects Number of units × Opportunities per unit ) × 1,000,000 \text{DPMO} = \left(\frac{\text{Number of defects}}{\text{Number of units} \times \text{Opportunities per unit}}\right) \times 1{,}000{,}000 DPMO = ( Number of units × Opportunities per unit Number of defects ​ ) × 1 , 000 , 000

DPMO enables comparison across products with different complexity.

  • Worked example (DPMO)
  • Units inspected: 1,000
  • Opportunities per unit: 5 (five critical fields or characteristics)
  • Defects found: 25

Total opportunities = 1,000 × 5 = 5,000 DPMO = 25 5,000 × 1,000,000 = 5,000 \text{DPMO} = \frac{25}{5{,}000} \times 1{,}000{,}000 = 5{,}000 DPMO = 5 , 000 25 ​ × 1 , 000 , 000 = 5 , 000

Sigma level (conceptual mapping)

Sigma level links process performance to DPMO using the normal distribution (often with a 1.5σ shift convention in Six Sigma tables for long-term performance). Memorize landmark pairs for the exam:

  • Approx. long-term sigma (with 1.5σ shift convention) DPMO (order of magnitude)
  • 3σ ~66,800
  • 4σ ~6,210
  • 5σ ~233
  • 6σ ~3.4

A DPMO of 5,000 sits near the ~4σ region on common tables—far from world-class 6σ (~3.4 DPMO). Report both DPMO and sigma; leaders often recognize “four sigma” faster than “five thousand DPMO.”

Yield-to-sigma shortcuts on the exam: high first-pass yield does not automatically mean high sigma if opportunities are many and defects are undercounted. Always honor the opportunity definition.

Capability Indices — Overview (Link to Measure)

Process performance metrics above count defects and costs. Capability indices compare the process distribution to specification limits (details deepen in BoK III.F):

  • Index Focus
  • Cp Potential capability (spread only; assumes centering)
  • Cpk Actual capability (spread + centering vs. nearest limit)
  • Pp / Ppk Overall/long-term performance analogs using overall variation

Rough intuition: higher Cpk means fewer defects relative to specs if the process is stable and approximately normal. DPMO/sigma from attribute counts and Cpk from continuous data should tell a consistent story ; investigate when they do not (wrong opportunities, unstable process, non-normal data, measurement error).

Using Metrics to Drive Decisions

Baseline in Measure: DPU, RTY, DPMO/sigma, and CoPQ before changes.

Prioritize: High CoPQ + low RTY steps often beat vanity metrics.

Validate Improve: Show statistically and practically better DPU/DPMO/RTY—and dollar impact.

Control: Dashboard the few metrics that detect backsliding; link to control plans.

Avoid gaming: Changing opportunity counts or inspection rigor to “improve” DPMO without real process change is not Six Sigma.

Exam checklist: defects ≠ defectives; DPU can exceed 1; RTY multiplies step yields; DPMO needs opportunities; CoPQ must map to real cost buckets; sigma tables often assume the 1.5σ shift—read the stem for which convention is implied.