1 Introduction & Exam Overview

CSSGB Exam Facts & Logistics How to Study for an Open-Book ASQ Exam

2 Six Sigma Foundations

Value of Six Sigma & Quality Leaders Organizational Goals & Six Sigma Projects Organizational Drivers, KPIs & Scorecards

3 Lean Principles in the Organization

Lean Concepts Value Stream Mapping & Waste

4 Design for Six Sigma

DFSS Road Maps: DMADV & IDOV FMEA Basics & Risk Priority Number Design FMEA vs Process FMEA

5 Define: Project Identification

Project Selection & DMAIC Fit Process Elements & Boundaries Benchmarking Types SIPOC & Process Inputs/Outputs

6 Stakeholders & Voice of the Customer

Owners & Stakeholders Customer Identification Customer Data Collection CTQ, QFD & Kano

7 Project Management Core

Agile & Top-Down Project Methods Project Charter & Problem Statements Project Scope Tools Primary & Consequential Metrics

8 Planning, Risk & Closure

WBS, Gantt, CPM, PERT & Tollgates Project Documentation Project Risk Analysis & Management Project Closure & Lessons Learned

9 Management Tools & Business Results

Eight Management & Planning Tools DPU, RTY, CoPQ, DPMO & Sigma Level Organizational Communication

10 Team Dynamics & Performance

Team Stages & Negative Dynamics Six Sigma Roles & RACI Brainstorming, NGT & Multivoting Team Communication

11 Measure: Process & Probability

Process Maps & Documentation Basic Probability Concepts Central Limit Theorem

12 Distributions & Data Collection

Statistical Distributions Data Types & Measurement Scales Sampling & Data Collection Plans Descriptive Statistics

13 Graphical Methods & MSA

Graphical Methods Measurement System Analysis & Gage R&R Bias, Linearity, Stability & P/T

14 Process & Performance Capability

Process Performance vs Specifications Process Capability Studies Cp, Cpk, Pp, Ppk & Cpm Short-Term vs Long-Term Capability & Sigma Shift

15 Analyze: Exploratory Data Analysis

Multi-Vari Studies Correlation & Linear Regression

16 Hypothesis Testing

Hypothesis Testing Basics Tests for Means, Variances & Proportions

17 Gap & Root Cause Analysis

Gap Analysis Root Cause Analysis Tools

18 Design of Experiments

DoE Basic Terms Main Effects & Interaction Plots

19 Implementation Planning & Lean Tools

Implementation Planning & Pilots Waste Elimination Tools Cycle-Time Reduction & SMED Kaizen & Kaizen Blitz

20 Statistical Process Control

SPC Basics: Common vs Special Cause Rational Subgrouping Control Chart Selection & Construction

21 Sustaining Improvements & Lean Control

Control Plans Document Control, Training & Audits Plan-Do-Check-Act (PDCA) TPM & Visual Factory

Cp, Cpk, Pp, Ppk & Cpm

Key Takeaways Explain This Topic AI

Cp = (USL − LSL) / (6σ_within) measures potential capability from spread only; it ignores centering.

Cpk = min[(USL − μ)/(3σ_within), (μ − LSL)/(3σ_within)] measures capability allowing for off-center location; Cpk ≤ Cp always.

Pp and Ppk use overall (long-term) standard deviation instead of within-subgroup σ; they describe actual performance over the study period.

Cpm (Taguchi capability) penalizes deviation from target T: Cpm = (USL − LSL) / (6√(σ² + (μ − T)²)).

Short-term sigma level relates to distance to the nearest spec: Z_bench ≈ 3 × Cpk (using the matching σ); know how indices connect to sigma thinking.

Last updated: July 2026

Cp, Cpk, Pp, Ppk & Cpm (CSSGB BoK III.F.3 — Evaluate)

Quick Answer: Cp and Cpk use within-subgroup (short-term) σ; Pp and Ppk use overall (long-term) s. Cp/Pp ignore centering; Cpk/Ppk include it. Cpm further penalizes distance from target T. Green Belts must compute indices from given data, compare them, and link the nearest-spec distance to sigma level.

Shared Building Blocks

For a two-sided continuous characteristic:

  • Tolerance width = USL − LSL
  • Process mean μ (estimated by X̄)
  • Within-subgroup standard deviation σ_within (often from R̄/d₂ or S̄/c₄ on rational subgroups)
  • Overall standard deviation s_overall (sample SD of all individuals in the study period)

One-sided specs: use only the applicable half of Cpk/Ppk (CPU or CPL); Cp is not defined in the usual two-sided form without a full width.

Define the one-sided ratios:

  • CPU = (USL − μ) / (3σ)
  • CPL = (μ − LSL) / (3σ)
  • Cpk = min(CPU, CPL)

(same structure for Ppk with s_overall).

  • Cp — Potential Capability (Spread Only)
  • Cp = (USL − LSL) / (6 σ_within)

Cp asks: If the process were perfectly centered, would the natural 6σ spread fit inside the specs? It does not use μ. A process with huge Cp can still ship defects if the mean sits on one fence.

Interpretation guide (common industrial language, not a universal law):

  • Cp (centered ideal) Rough reading
  • < 1.0 Process spread wider than tolerance—incapable even if centered
  • = 1.0 6σ equals tolerance—no margin
  • ≥ 1.33 Often cited minimum in mature quality systems
  • ≥ 1.67 / 2.0 High capability / Six Sigma-oriented targets in some programs
  • Cpk — Actual Short-Term Capability (Spread + Location)
  • Cpk = min[ (USL − μ) / (3 σ_within) , (μ − LSL) / (3 σ_within) ]

Cpk uses the nearest specification. Always Cpk ≤ Cp . Equality holds when the process is centered between LSL and USL (for symmetric use of the same σ).

Worked example — Cp and Cpk:

  • LSL = 10.00, USL = 16.00, μ = 12.50, σ_within = 0.80
  • Cp = (16 − 10) / (6 × 0.80) = 6 / 4.8 = 1.25
  • CPU = (16 − 12.50) / (3 × 0.80) = 3.50 / 2.40 = 1.458
  • CPL = (12.50 − 10) / (3 × 0.80) = 2.50 / 2.40 = 1.042
  • Cpk = min(1.458, 1.042) = 1.04 (approx.)

Reading: Potential Cp = 1.25, but the mean is closer to LSL, so Cpk ≈ 1.04. Improvement priority: center upward toward mid-spec (13.0) and/or reduce σ.

Second worked example — centered:

  • Same specs, μ = 13.00, σ_within = 0.80
  • Cp = 1.25 still
  • CPU = CPL = (3.00) / 2.40 = 1.25
  • Cpk = 1.25 = Cp

Centering recovered the full potential.

  • Pp and Ppk — Performance with Overall Variation
  • Pp = (USL − LSL) / (6 s_overall)
  • Ppk = min[ (USL − μ) / (3 s_overall) , (μ − LSL) / (3 s_overall) ]

Use the same formulas as Cp/Cpk but replace σ_within with the overall standard deviation of all data points in the period. Overall s includes between-subgroup shifts, drifts, and longer-term noise, so typically:

s_overall ≥ σ_within ⇒ Pp ≤ Cp and Ppk ≤ Cpk (when mean estimates align).

  • Index Variation source Centers? Typical use
  • Cp Within (short-term) No Potential capability if centered
  • Cpk Within (short-term) Yes Short-term capability entitlement
  • Pp Overall (long-term) No Performance spread over the study
  • Ppk Overall (long-term) Yes Actual performance vs. specs

Worked example — Pp/Ppk:

  • LSL = 10, USL = 16, μ = 13.0, s_overall = 1.20 (σ_within was 0.80)
  • Pp = 6 / (6 × 1.20) = 6 / 7.2 = 0.83
  • Ppk = (3.0) / (3 × 1.20) = 3 / 3.6 = 0.83 (centered)

Short-term Cpk was 1.25; long-term Ppk is 0.83. The gap flags extra variation over time —investigate mean shifts, multiple streams, or unstable inputs—not just “operators need to try harder on each piece.”

Cpm — Taguchi / Target-Centered Capability

When the customer cares about closeness to target T , not only staying inside LSL–USL, use:

Cpm = (USL − LSL) / (6 √(σ² + (μ − T)²))

Here σ is the process standard deviation used for the study context (often overall or the σ specified by the method). The term (μ − T)² inflates the denominator when the mean misses the target—even if Cpk looks acceptable because the mean is still far from both fences.

When Cpm is used:

  • Target is not optional (fit, color, matching, calibrated outputs)
  • Loss increases as you move away from T (Taguchi loss thinking)
  • You need a single index that punishes both excess variation and target miss

Worked sketch: USL − LSL = 6, σ = 0.5, μ = T ⇒ √(σ² + 0) = 0.5 ⇒ Cpm = 6/(6×0.5) = 2.0 . If μ − T = 0.5 with same σ, √(0.25+0.25)=√0.5≈0.707 ⇒ Cpm ≈ 6/(6×0.707) ≈ 1.41 . Cpk might still be high if specs are wide; Cpm fell because of the target offset.

  • Relationships to Remember
  • Cpk ≤ Cp and Ppk ≤ Pp
  • Pp ≤ Cp and Ppk ≤ Cpk when overall variation exceeds within variation
  • Cpk ≈ Cp (and Ppk ≈ Pp ) when well centered
  • Large Cp − Cpk gap ⇒ centering problem
  • Large Cpk − Ppk gap ⇒ long-term / between variation problem
  • Cpm falls when μ moves from T even if still inside specs
  • From Capability to Sigma Level

Distance from the mean to the nearest specification, in sigma units:

Z_min = min[ (USL − μ)/σ , (μ − LSL)/σ ]

Because Cpk = Z_min / 3 when the same σ is used:

  • Z_min = 3 × Cpk (short-term when σ = σ_within)
  • Z_min = 3 × Ppk (long-term when σ = s_overall)

Worked example: Cpk = 1.33 ⇒ Z_min = 3 × 1.33 ≈ 4.0 . Under a normal model centered such that the nearest fence is 4σ away, short-term nonconformance in that tail is about Φ(−4) ≈ 0.0032% on that side (before any long-term shift discussion in III.F.4).

Many Six Sigma deployments convert long-term defect rates to a sigma level table (with or without a 1.5σ shift). For the exam, know the Z = 3 × Cpk (or Ppk) bridge and that higher indices mean more standard deviations of margin to the nearest spec.

  • Evaluation Pitfalls
  • Reporting Cp alone when the process is off-center
  • Mixing within and overall σ in the same formula
  • Treating Cpk as a percent yield without a distributional assumption
  • Comparing vendor Cpk to plant Ppk without matching definitions
  • Using Cpm without a meaningful customer target T
  • Bottom Line for III.F.3

Memorize the four core formulas, the Cpm target penalty, the inequalities among indices, and Z_min = 3 × Cpk/Ppk . Evaluate which index answers the question being asked: potential vs. actual, short-term vs. long-term, specs-only vs. target-focused.