6.3 Competition Requirements & JOFOCs (FAR Part 6)
DAWIA DoD Contracting Professional Certification CON 3990V
Track your progress as you read
Finished sections get a check mark.
1 Introduction & Exam Overview
1.1 Current Exam Facts & Logistics 1.2 Certification Path, Eligibility & Retakes 1.3 Closed-Book Study Strategy for CON 3990V
2 FAR System & Regulatory Map
2.1 FAR Structure, Authority & Hierarchy (Part 1) 2.2 Definitions & Key Terms (Part 2) 2.3 FAR Part Title Map for CON 3990V
3 Guiding Principles: Skills, Roles & Situational Assessment
3.1 Skills and Roles Across the Contract Lifecycle 3.2 Business Acumen for Contracting Decisions 3.3 Situational Assessment & Lessons Learned
4 Guiding Principles: Contract Principles
4.1 Core Contracting Principles 4.2 Competition, Integrity & Transparency Principles 4.3 Terms, Conditions & Contract Formation Fundamentals
5 Ethics, Teams & Communication
5.1 Standards of Conduct & Conflicts of Interest (FAR Part 3) 5.2 Team Dynamics in Acquisition Teams 5.3 Communication and Documentation Best Practices
6 Pre-Award: Plan Solicitation
6.1 Acquisition Planning (FAR Part 7) 6.2 Market Research (FAR Part 10) 6.3 Competition Requirements & JOFOCs (FAR Part 6)
7 Pre-Award: Sources, Commercial & Simplified
7.1 Publicizing Contract Actions (FAR Part 5) 7.2 Required Sources of Supplies and Services (FAR Part 8) 7.3 Commercial Acquisition & Simplified Procedures (Parts 12 & 13)
8 Pre-Award: Request Offers & Seller Awareness
8.1 Building the Solicitation Package 8.2 Requesting Offers: Methods, Evaluation Factors & Clauses 8.3 Seller Planning, Offer Preparation & DFARS Awareness
9 Socioeconomic Programs & Small Business
9.1 Small Business Programs & Set-Asides (FAR Part 19) 9.2 Socioeconomic Preferences & Rule of Two 9.3 Pre-Award Small Business Subcontracting Considerations
10 Award Foundations: Contract Types
10.1 Fixed-Price Contract Types (FAR Part 16) 10.2 Cost-Reimbursement & Hybrid Types 10.3 Selecting & Documenting Contract Type
11 Award: Price & Cost Analysis
11.1 Price Analysis Techniques 11.2 Cost Analysis, Certified Cost or Pricing Data & TINA/TCPD 11.3 Cost Realism & Fair and Reasonable Pricing
12 Award: Negotiation & Source Selection
12.1 Planning Negotiations & Pre-Negotiation Objectives 12.2 Source Selection Methods & Competitive Range (FAR Part 15) 12.3 Responsibility Determinations & Award Documentation (Part 9)
13 Award: Manage Disagreements
13.1 Bid Protests (FAR Part 33) 13.2 Size Status & Pre-Award Challenges 13.3 Managing Disagreements & Constructive Resolution
14 Post-Award: Administer & Quality
14.1 Contract Administration Fundamentals (FAR Part 42) 14.2 Quality Assurance & Surveillance (FAR Part 46) 14.3 Subcontract Management & Consent (FAR Part 44)
15 Post-Award: Changes, Claims & Disputes
15.1 Contract Modifications & Scope 15.2 Constructive Changes, REAs & Claims 15.3 Disputes Under the Contract Disputes Act
16 Terminations, Closeout & Exam Integration
16.1 Terminations for Convenience & Default (FAR Part 49) 16.2 Contract Closeout & Records (Parts 4 & Closeout) 16.3 Lifecycle Integration, High-Yield Traps & Exam Day
6.3 Competition Requirements & JOFOCs (FAR Part 6)
Key Takeaways Explain This Topic AI
FAR Part 6 establishes full and open competition as the default: all responsible sources are permitted to compete, using competitive procedures.
Competitive procedures include sealed bidding, competitive proposals, combination of competitive procedures, and other competitive procedures authorized in Part 6.
Other than full and open competition is allowed only under recognized circumstances (FAR 6.302 family themes such as only one responsible source, unusual and compelling urgency, industrial mobilization/expert services, international agreement, statute, national security, and public interest).
Justifications (JOFOCs) must document facts, market research linkage, and efforts to promote competition to the maximum extent practicable—even when an exception applies.
Sealed bidding and competitive proposals are different competitive methods: sealed bids emphasize public opening and price-focused award when conditions for bidding are met; competitive proposals allow negotiation and tradeoff when appropriate under Part 15 frameworks.
Last updated: August 2026
6.3 Competition Requirements & JOFOCs (FAR Part 6)
Quick Answer: FAR Part 6 requires full and open competition with competitive procedures unless a recognized other than full and open authority applies. Exceptions need justification and approval (JOFOC) themes: facts, market research, and maximizing competition. Prefer competition; never treat leadership preference as a statutory exception.
Competition is both a Guiding Principle (earlier chapters) and a hard Part 6 procedure set . Plan Solicitation competency expects you to convert market research and acquisition planning into a lawful competition strategy—or a defensible limited-competition path.
Full and open competition as the default
Full and open competition means all responsible sources are permitted to compete. The Contracting Officer must promote and provide for full and open competition in soliciting offers and awarding contracts unless a Part 6 exception (or another authorized pathway consistent with the FAR) applies.
Why the default exists:
- Policy goal Practical effect
- Best value / fair price Multiple offers discipline pricing and quality
- Innovation New entrants can propose better solutions
- Integrity / public trust Transparent access reduces favoritism appearance
- Socioeconomic opportunity Broader field includes small and diverse businesses
- Protest resilience Competitive processes are easier to defend when rules are followed
Exam mindset: If the stem does not clearly establish an exception, choose the answer that preserves or expands competition .
Competitive procedures (high level)
When providing for full and open competition, Part 6 recognizes competitive procedures such as:
Procedure Conceptual use
Sealed bids When sealed bidding conditions are met—public opening, award based on price and price-related factors to responsible bidder, sufficient time, etc. (ties to Part 14 concepts)
Competitive proposals When sealed bidding is not appropriate—negotiations, tradeoffs, and negotiation frameworks under Part 15 are typical
Combination of competitive procedures Multi-step or mixed approaches authorized for the situation
Other competitive procedures Additional competitive methods recognized in Part 6 (e.g., certain statutory competitive programs as applicable)
Sealed bid vs competitive proposal (exam-level contrast)
Factor Sealed bidding (concept) Competitive proposals (concept)
Opening Public bid opening tradition Proposals handled under source-selection rules, not classic public bid opening
Negotiations Generally not the sealed-bid model Negotiations may be held when appropriate
Award basis Price and price-related factors to responsible bidder when IFB conditions fit Tradeoff or LPTA-style models under Part 15 as planned
When preferred Clear specs, time for solicitation, award on price basis appropriate Need for technical tradeoffs, negotiations, or complex evaluation
You do not need to litigate every Part 14 vs 15 edge case on CON 3990V, but you must know: both can implement full and open competition , and choosing proposals is not automatically “less competitive” than bids when conditions call for negotiation.
Other than full and open competition — authority themes (FAR 6.302 family)
Part 6 permits contracting without providing for full and open competition only when a listed circumstance applies. Learn the themes (principle level). Exact statutory cross-cites matter less on a closed-book workforce exam than recognizing the category and the documentation duty:
Authority theme (FAR 6.302 family) Core idea
6.302-1 Only one responsible source Only one source can satisfy the requirement; supplies/services unique or highly specialized; follow-on / brand-name logic only when truly justified—not convenience
6.302-2 Unusual and compelling urgency Delay would cause serious injury; still solicit from as many sources as practicable; urgency does not equal permanent sole source
6.302-3 Industrial mobilization; engineering, developmental, or research capability; or expert services Maintain critical capability, essential R&D capacity, or expert services for litigation/disputes as framed in the FAR
6.302-4 International agreement Acquisition precluded from full and open competition by international agreement
6.302-5 Authorized or required by statute A statute expressly authorizes or requires other than full and open competition
6.302-6 National security Disclosure of agency need would compromise national security
6.302-7 Public interest Full and open competition not in public interest— narrow , high-level approval sensitivity; not a casual “we prefer not to compete” escape hatch
Critical limits on exceptions
Exceptions are exclusive categories. Leadership preference, incumbent familiarity, and poor planning are not independent authorities.
Urgency still requires maximizing competition practicable under the circumstances—single-source urgency awards need facts about why others could not be solicited.
Only one source demands market research that truly supports uniqueness; restrictive specifications can create artificial “only one” outcomes—and that is on the Government.
Public interest is not the everyday tool for routine buys; treat it as extraordinary.
- Statutory authority means an actual statute—not a local memo titled “policy.”
- JOFOC documentation themes (justification and approval)
When using other than full and open competition, the file needs a justification (often called a JOFOC—Justification for Other than Full and Open Competition) and approval at the level required by Part 6 / agency procedures based on dollar value and circumstance.
You should not invent precise approval-dollar ladders unless verified for the current FAR text, but you must know conceptual content themes justifications typically address:
- JOFOC theme What good documentation shows
- Description of supplies/services Clear statement of what is being acquired
- Authority cited Specific 6.302 circumstance (or other authorized basis)
- Demonstration of facts Why the authority applies—evidence, not slogans
- Market research Efforts to identify sources; results; why competition limited
- Unique qualifications / urgency facts Tied to the authority used
- Efforts to solicit offers from as many sources as practicable
- Fair and reasonable price determination approach How price will be determined fair and reasonable
- Actions to remove barriers to future competition Especially for follow-ons and urgency
- Technical/requirements certification as required
- Approvals Proper review chain before award
Insufficient JOFOC language: “Incumbent is doing a good job and changing vendors would be inconvenient.” Stronger pattern: Specific capability that others lack after documented market research; mission harm if delayed; steps taken to compete to the maximum extent practicable; plan to compete next time if barriers can be removed.
Approval culture (conceptual)
Higher dollar values and certain authorities demand higher-level approvals (competition advocates, senior procurement executives, or other designated officials under Part 6 structure). On the exam: do not award before required justification approval . If schedule pressure collides with approval lead time, escalate early—do not skip the signature.
Promoting competition even when limited
Part 6 is not binary “compete everything or sole source forever.” Even under exceptions:
Solicit multiple sources when practicable (especially urgency).
Avoid unnecessary brand-name-only or restrictive specs.
Structure follow-on acquisitions to restore competition (data rights, transition, modular contracting concepts at awareness level).
Use advance planning (Part 7) so urgency exceptions are rare rather than routine.
Competition advocates and similar roles exist in the FAR system to challenge barriers—exam scenarios may reward consulting them when sole-source pressure is unjustified.
Scenario drills (CON 3990V style)
Scenario A — Preference vs authority. A director orders “sole source to Company Z; they sponsor our conference.” Answer path: Refuse; preference and sponsorship are not Part 6 authorities; pursue full and open or a valid set-aside path; ethics concerns may also apply.
Scenario B — Urgency after poor planning. The requiring activity delayed the package six months and now claims 6.302-2 urgency the week before funds expire. Answer path: True urgency can exist, but self-inflicted delay is scrutinized; still maximize competition practicable; document facts carefully; leadership should own the schedule failure without inventing national-security language.
Scenario C — Only one source. Market research identifies three firms that sell equivalent commercial solutions; the program wants brand-name-only for comfort. Answer path: Not 6.302-1; compete using brand-name-or-equal or performance specs; if brand-name truly required, justify restrictiveness properly—do not skip competition.
Scenario D — Method choice. Specs are clear, award can be based on price to a responsible bidder, and time allows advertising. Someone insists on a complex Part 15 tradeoff “because we always negotiate.” Answer path: Consider whether sealed bidding conditions are met; competitive proposals are not automatically better or more “professional.”
Scenario E — JOFOC without research. A draft justification asserts only one source but attaches no market research. Answer path: Incomplete; complete Part 10 research and rewrite justification with facts—or compete.
Linking Parts 6, 7, and 10
- Input Output in competition strategy
- Part 7 plan States intended competition approach and milestones for synopsis/solicitation
- Part 10 research Evidence of capable sources, commerciality, and barriers
- Part 6 execution Full and open competitive procedure or justified limited competition with approvals
If research shows competition is available, the plan and JOFOC cannot honestly claim otherwise. If the plan promises full and open competition, the solicitation method must deliver it.
- Closed-book cues
- Stem about full and open , JOFOC , sole source , urgency exception , only one responsible source → Part 6
Stem about whether to use sealed bids vs negotiation at strategy level → Part 6 competitive procedures + later Part 14/15 detail
- Stem about documenting why not competed → justification content + market research linkage
- Stem about who must approve → higher-level approval concept tied to value/authority (agency implementation)
Bottom line: FAR Part 6 defaults to full and open competition via competitive procedures (sealed bids, competitive proposals, and other authorized competitive methods). Other than full and open requires a real 6.302-family circumstance, a fact-based JOFOC , proper approval , and maximum practicable competition even then. On CON 3990V, convenience, preference, and poor planning are not authorities— promote competition and document honestly when an exception truly applies.