Study guide

14.4 Controlled Disassembly, Inspection & Reassembly

EASA Part-66 Module 07 — Maintenance Practices Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Safety Precautions — Electricity, Gases & Chemical Hazards

1.1 Electrical-System Hazards, Isolation & Protective Equipment 1.2 Compressed Gases, Pressure Vessels & Oxygen System Safety 1.3 Hazardous Chemicals, Solvents, Oils & Personal Protective Equipment

2 Chapter 2: Safety Precautions — Fire Protection, Confined Spaces & Emergency Response

2.1 Fire Classifications, Extinguishing Agents & Asphyxiation Risks 2.2 Confined-Space Entry, Fuel-Tank Safety & CDCCL Control 2.3 Emergency Response, Accident Remediation & Ballistic Recovery Systems

3 Chapter 3: Workshop Practices, Hand Tools & Precision Measurement

3.1 Workshop Housekeeping, Tool Control & Foreign Object Debris (FOD) 3.2 Engineering Dimensions, Allowances & Tolerances 3.3 Hand Tools, Powered Equipment & Operating Safety 3.4 Precision Measuring Instruments & Standards Traceability

4 Chapter 4: Fastener Torquing & Avionic Test Equipment

4.1 Torque Wrenches, Extension Calculations & Calibration Care 4.2 Multimeters, Megohmmeters & Insulation Testing 4.3 Bonding Testers, Milliohmmeters & Oscilloscopes

5 Chapter 5: Engineering Drawings, Standards & Fits

5.1 Orthographic Projections, Title Blocks & Revision Control 5.2 Drawing Line Conventions, Symbols & ATA Specification 100/iSpec 2200 5.3 Electrical Schematics, Wiring Interconnects & Component Location 5.4 Systems of Limits, Fits, Clearances & Shaft Alignment

6 Chapter 6: Electrical Wiring Interconnection System (EWIS)

6.1 EWIS Principles, Wire Types & Loom Routing Practices 6.2 Crimp Terminations, Connector Pin Insertion & Extraction Tooling 6.3 Electrical Bonding, Grounding Resistance & Electromagnetic Shielding

7 Chapter 7: Aircraft Riveting Practice

7.1 Solid and Blind Rivet Classifications, Materials & Head Markings 7.2 Rivet Spacing, Pitch, Edge Distance & Structural Layout 7.3 Countersinking, Dimpling Techniques & Rivet Installation 7.4 Rivet Joint Inspection, Failure Modes & Drill-Out Procedures

8 Chapter 8: Sheet Metal Working & Composite Materials

8.1 Sheet Metal Forming, Neutral Axis & Bend Allowance Calculations 8.2 Welding, Brazing, Soldering & Structural Adhesive Bonding 8.3 Composite Reinforcements, Pre-Preg Cold Storage & Clean Room Practice 8.4 Additive Manufacturing in Aircraft Maintenance

9 Chapter 9: Pipes, Flexible Hoses & Springs

9.1 Aircraft Rigid Tubing, Bending & 37-Degree Flaring Standards 9.2 Flexible Hoses, Installation Geometry & Serviceability 9.3 Aircraft Springs: Classifications, Rate Testing & Inspection

10 Chapter 10: Bearings & Mechanical Transmissions

10.1 Bearing Classifications, Load Types & Lubrication Practice 10.2 Bearing Defect Analysis: Spalling, Brinelling & Overheating 10.3 Gears, Gearboxes, Backlash Measurement & Belt/Chain Drives

11 Chapter 11: Flight Control Cables & Rigging

11.1 Aircraft Cable Construction, Sizing & Swaged Terminal Fittings 11.2 Cable Rigging, Turnbuckles & Temperature-Compensated Tensioning 11.3 Pulleys, Fairleads, Cable Inspection & Broken Strand Limits

12 Chapter 12: Aircraft Weight and Balance

12.1 Datum, Arm, Moment & Center of Gravity Principles 12.2 Aircraft Weighing Preparation, Equipment & Tare Deduction 12.3 Center of Gravity Calculations, Flight Limits & Ballast Adjustments

13 Chapter 13: Aircraft Handling, Storage & Winter Operations

13.1 Towing, Taxiing Protocols, Shear Pins & Wing Walkers 13.2 Jacking with Locking Collars, Chocking & Severe Weather Mooring 13.3 Ground De-icing and Anti-icing: Fluids, Clean Aircraft Concept & Holdover Times 13.4 Aircraft Parking, Protective Covers & Engine/Airframe Long-Term Preservation

14 Chapter 14: Inspection, Defect Assessment, Maintenance Procedures & Documentation

14.1 NDT Methods: Liquid Penetrant, Magnetic Particle, Eddy Current, Ultrasonic & Radiography 14.2 Corrosion Classifications, Mechanical Removal & Chemical Surface Treatments 14.3 Inspections After Lightning, Heavy Landing & Other Abnormal Events 14.4 Controlled Disassembly, Inspection & Reassembly 14.5 Troubleshooting, Defect Assessment & Repair Control 14.6 Maintenance Documentation, Work Reports & Shift Handover 14.7 Maintenance Planning, Stores Control, CRS & Occurrence Reporting

14.4 Controlled Disassembly, Inspection & Reassembly

Key Takeaways Explain This Topic AI

Plan disassembly from current approved data, aircraft condition, access needs, and controls for stored energy, contamination, and heavy components.

Mark, protect, cap, plug, segregate, and record parts so orientation, matched sets, configuration, and cleanliness are preserved.

Inspect during disassembly because wear patterns, witness marks, debris, and as-found position may be lost after cleaning.

Reassembly requires correct parts, consumables, fits, torque or preload method, locking devices, clearances, lubrication, and independent inspections.

Close-up occurs only after tool and loose-item control, system restoration, functional testing, and complete records.

Last updated: September 2026

14.4 Controlled Disassembly, Inspection & Reassembly

Disassembly is an information-gathering phase, not merely the reverse of assembly. Incorrect removal can erase evidence, contaminate a system, release stored energy, damage a matched surface, or make correct reassembly uncertain. Begin with current approved maintenance data, the work order, aircraft configuration, and a clear boundary for the task.

Preparation

Make the aircraft or component safe. Isolate electrical, hydraulic, pneumatic, fuel, spring, gravitational, thermal, and pressure energy as applicable. Support heavy or unbalanced items before removing their final attachment. Provide clean containers, caps and plugs, labels, protective covers, calibrated tooling, lifting equipment, and the specified consumables. Confirm replacement parts and mandatory one-time-use items are available before disturbing an installation that cannot safely remain open.

Record as-found condition where it may aid fault analysis: alignment marks, rigging position, leakage, witness marks, connector security, locking, contamination, and damage. Photographs and measurements supplement, rather than replace, required records.

Removal and segregation

Follow the stated sequence. Loosen fasteners progressively where distortion or stored load is possible. Do not lever against an unapproved surface or drive a part with an unsuitable tool. Protect threads, sealing faces, bearings, splines, wiring, pipes, and open ports immediately.

Identify parts whose location or orientation matters. Matched gears, bearing races, balance weights, shims, spacers, control rods, and fitted bolts must not be mixed. Separate serviceable, unserviceable, life-controlled, and quarantined material. Attach status information so an unattended item cannot be mistaken for an installable part.

Inspection while dismantling

Look before cleaning. Fretting debris, fluid tracks, heat discolouration, displaced lubricant, uneven contact, scoring, and fastener witness marks can show how a defect developed. Compare the finding with the inspection method and limits in approved data. Cleaning must use compatible materials and must not remove protective finishes or smear evidence into a crack.

Measure with suitable, in-calibration equipment at the specified locations and conditions. A value without its datum, temperature, method, or limit may be meaningless. When damage is outside published limits or data are unclear, stop and obtain an authorised disposition.

Reassembly

Verify part number, modification state, life status, release documentation, and condition. Install the stated seals, locking devices, fasteners, lubricants, compounds, and consumables. Looks equivalent is not interchangeability.

Observe orientation and assembly sequence. Apply torque, angle, stretch, preload, backlash, end float, clearance, or safetying by the method specified. Generic shop values do not override component instructions. Where friction affects torque, use the specified thread condition. Restore bonding, clamps, supports, drain paths, fire seals, and protective finishes.

Required independent inspections must occur while the feature is accessible. Do not close a panel and later sign an unseen critical step. Conduct tool and loose-item checks, remove caps and blanks at the planned point, and verify that controls and systems move through their required range without interference.

Functional proof and records

Restore isolated systems in the controlled sequence. Perform leak, operational, rigging, duplicate, or functional tests specified by the task. Investigate abnormal indications rather than repeating a test until it happens to pass. Record the work performed, data and revision used, parts and consumables as required, measurements, inspections, test results, and any deferred or additional defects.

A strong exam answer follows the whole chain: make safe, preserve configuration and evidence, protect and identify removed items, inspect against data, reassemble with specified parts and settings, independently inspect critical work, test, and record.

Cleanliness and human-factor controls

System cleanliness is part of configuration. Cap a hydraulic, fuel, pneumatic, oxygen, or oil opening with the approved clean protection rather than tape, rags, or an item that can shed material. Keep incompatible fluids and cleaning agents separate. If contamination enters an open system, record it and use the specified recovery process; hiding the event can create a delayed failure.

Plan the work area so removed fasteners and small items cannot migrate. Use parts trays, identification tags, and a tool-control count suited to the task. Pause points are valuable before the final attachment is removed, before a hidden lock or seal is covered, and before energy is restored. At each pause, compare physical condition with the work card rather than relying on memory.

Consider a pump removal involving two similar lines, a drive coupling, shims, and an electrical connector. The safe method identifies and protects each line, records shim location, supports the pump, checks the coupling during removal, and preserves the connector. Reassembly then verifies correct port identity, restores shims and coupling engagement, uses specified seals and torque, performs the required independent inspection, and completes leak and functional tests. The process prevents a plausible-looking but internally incorrect installation.

Stage-Gate Checklist

  • Gate Confirm before proceeding
  • Before removal Energy isolated, item supported, as-found condition recorded, caps and containers ready
  • During removal Parts identified and segregated, openings protected, evidence and damage recorded
  • Before assembly Eligibility, cleanliness, configuration, consumables and one-time items verified
  • Before close-up Torque or preload, locking, clearances, routing and independent inspections complete
  • Before release Tools accounted for, systems restored, required tests passed and records completed