14.2 Submission Requirements & the EDGE Checklist
GBCI EDGE Expert Certification Exam Study Guide Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: EDGE System Overview & Certification Levels
1.1 EDGE Fundamentals & IFC/GBCI Ecosystem 1.2 The EDGE Standard & Baseline Methodology 1.3 Certification Levels: EDGE Certified, Advanced & Zero Carbon
2 Chapter 2: EDGE App & Software Methodology
2.1 EDGE App Setup, Project Navigation & Inputs 2.2 Energy, Water & Materials Calculator Tabs 2.3 Financial Outputs, Payback & Methodology Reporting
3 Chapter 3: Bioclimatic & Passive Design Strategies
3.1 Climate-Responsive Building Orientation & Massing 3.2 Natural Ventilation, Cross-Ventilation & Ceiling Fans 3.3 Daylighting, Glazing Ratio & Shading Devices
4 Chapter 4: Energy Efficiency Measures & HVAC Systems
4.1 Building Envelope Thermal Performance 4.2 HVAC Systems, Cooling Efficiency & Controls 4.3 Lighting Efficiency & Smart Controls 4.4 Renewable Energy & Water Heating Systems
5 Chapter 5: Water Efficiency & Conservation Measures
5.1 Indoor Water Fixtures & Low-Flow Technologies 5.2 Rainwater Harvesting & Greywater Recycling Systems 5.3 Outdoor Irrigation & Blackwater Treatment
6 Chapter 6: Materials & Embodied Carbon Optimization
6.1 Embodied Energy & Embodied Carbon Fundamentals 6.2 Floor, Roof & External Wall Material Selection 6.3 Windows, Insulation & Customized Materials
7 Chapter 7: Certification Process, Roles & Verification
7.1 Professional Roles: EDGE Expert vs EDGE Auditor 7.2 Preliminary (Design) Certification Workflow 7.3 Post-Construction (As-Built) Certification & Zero Carbon
8 Chapter 8: Protocols, Governance, Ethics & Professional Conduct
8.1 EDGE Certification Protocols & Standard Guidelines 8.2 Professional Ethics, Conflict of Interest & Transparency 8.3 Stakeholder Communication & Client Advisory
9 Chapter 9: Green Building Fundamentals, Comfort & the Business Case
9.1 Thermal Comfort Fundamentals 9.2 Climate, Comfort & Bioclimatic Response 9.3 How Green Measures Interact Across Energy, Water & Materials 9.4 The Business Case for Green Buildings
10 Chapter 10: EDGE Building Types & Type-Specific Measures
10.1 EDGE Typologies, Sub-Typologies & Choosing the Right One 10.2 Type-Specific Base Cases & Saving Measures 10.3 Subprojects, Clustering & Non-Typical Projects
11 Chapter 11: Local Market Conditions, Regulation & the Base Case
11.1 Base Case Assumptions & the Standards Behind the Model 11.2 Climate, Resources & Adding a City Not in EDGE 11.3 Regulatory Authorities & Country-Specific Requirements 11.4 EDGE, Building Permits & Other Regulatory Systems
12 Chapter 12: EDGE Software Deep Dive — Comfort, Demand, Water & Outputs
12.1 Virtual Energy for Comfort 12.2 Overall Energy Demand: Delivered Energy, Fuels & End Uses 12.3 Base Case Water Use by Building Type & Matching Water Quality to Use 12.4 Default Data, Saving & Sharing Projects, Output Files & Feedback
13 Chapter 13: Professional Practice, Contracts & Accountability
13.1 Contracts Between the Client, Certifier, Expert & Auditor 13.2 Auditor Quality, Non-Performance & Certification Challenges 13.3 Maintaining EDGE Professional Status & Pricing Your Services
14 Chapter 14: Certification Logistics — Fees, Checklists & Records
14.1 Registration, Certification Fees & Means of Payment 14.2 Submission Requirements & the EDGE Checklist 14.3 Project Stages, Skipping Preliminary Certification & Pricing Iterations 14.4 Documentation Records, Retention & Certification Renewal
14.2 Submission Requirements & the EDGE Checklist
Key Takeaways Explain This Topic AI
Supporting documentation must be submitted for each subsection in the Design Tab and for each claimed measure in the Energy, Water and Materials tabs.
During the Design Audit the Auditor marks each measure through the EDGE software as approved, not approved, or pending further information — the working form of the EDGE checklist.
The design and construction stages mirror each other, with the key difference that a site audit is required at the construction stage.
GBCI suggests project teams return clarifications to the Auditor within 20–25 business days of receiving comments, and audits begin only once all required documentation has been provided.
Zero Carbon submissions require additional documentation about fuels, entered with supporting evidence in the Zero Carbon Calculator on the Operations tab of each subproject.
Last updated: August 2026
14.2 Submission Requirements & the EDGE Checklist
Exam Focus: Sub-topics 6.7 "EDGE checklist" and 6.8 "Submission requirements at the design and construction stage and format of submission" are both named in Domain 6.0. The material is procedural, so questions tend to be precise about who does what and when.
What Must Be Submitted
The scope rule is broader than candidates expect. It is not only the claimed measures:
Supporting documentation shall be submitted for each subsection in the Design Tab and the claimed measures in the Energy, Water, and Materials tabs.
So the submission has two parts:
Design Tab evidence — the parameters that establish the project and its base case: location, typology and sub-typology, gross internal area, storeys, operating hours, occupancy, air-conditioned area, and the area and loads breakdown.
Measure evidence — for every measure claimed in the three calculator tabs, the documentation that measure requires.
A team that documents its measures meticulously but leaves the Design Tab parameters unevidenced has submitted half a package. The base case is derived from those parameters, so they are as auditable as the measures.
The User Guides are the authority on what each measure requires. GBCI directs teams to them for detailed information on each EDGE measure and the documentation information required, and it is the Expert's job to work from the User Guide version governing the project rather than from memory.
The EDGE Checklist in Practice
The checklist is not a static PDF; it is the live approval state of every claimed measure inside the EDGE software. During the initial review of the Design Audit:
Your Auditor will check your application for completeness and compliance with the EDGE Standard requirements. Through the EDGE software, the Auditor will indicate which measures are approved, not approved, or are pending further information.
Those three states are the working checklist, and each has a distinct correct response:
- State What it means Correct response
- Approved Evidence satisfies the measure requirement Leave it alone; do not resubmit and reopen it
Pending further information The measure may qualify but the evidence is incomplete Supply exactly what was asked for, promptly
Not approved The measure does not qualify as evidenced Decide: supply qualifying evidence, change the design, or remove the measure and recover the savings elsewhere
The savings arithmetic behind the checklist
Every not approved measure removes its savings from the model. This is why an Expert tracks not just the count of open items but the percentage headroom above each threshold. A project sitting at 20.4% energy cannot afford to lose a single measure; a project at 27% can lose several. Knowing which of the two you are managing determines how hard you fight each item.
Design Stage and Construction Stage
EDGE certification has two stages, and GBCI describes their relationship precisely: each stage mirrors the other, except that a site audit is required at the construction stage. The cost of certification covers both stages.
Design (Preliminary) Construction (Final)
Evidence type Drawings, specifications, calculations, manufacturer datasheets, schedules As-built drawings, delivery and purchase records, installed-product datasheets, commissioning records, site photographs
- Verification Design Audit — documentation review Site Audit — documentation review plus a physical site visit
- Output Preliminary Certificate EDGE Certificate
Question answered Will the design meet the Standard? Does the built building include the measures claimed?
The Site Audit exists because designs change. GBCI is explicit that a building must be reviewed again at post-construction in case any changes have been implemented during the construction process . Any specification substituted during construction must be reflected in the model before the Site Audit, not defended during it.
Sequencing rules that gate each audit
The team must provide all the post-construction stage documentation to the Auditor before the Site Audit can begin.
The Site Audit must take place within 12 months of the project's practical completion for new construction projects.
Audits begin only after the project team has provided all required documentation. Partial packages delay the audit, not the Auditor.
Turnaround Expectations Both Ways
GBCI publishes expectations for both sides, and an Expert should manage the client to them:
Auditor: 5 business days for the Design Audit initial review; 5 for the second review and recommendation; the same pattern for the Site Audit after the site visit.
Project team: GBCI suggests submitting clarifications to the Auditor as soon as possible after receiving comments — within 20–25 business days is recommended.
GBCI: approximately 10 business days for the quality-check decision, after fees clear.
Special Cases in Evidence
Existing buildings. Where documents normally required are unavailable, other evidence of construction details — existing building drawings or photographs — may be submitted. The requirement adapts to what can reasonably exist for an older asset.
Plant outside the project boundary. Where the cooling plant is outside the EDGE boundary or not controlled by the client, a contract with, or letter from, the management company in charge of the plant stating the efficiency of the system must be provided in the post-construction documentation.
Zero Carbon. Project teams shall submit additional documentation about the fuels for Zero Carbon certification. The data and supporting documentation are entered in the Zero Carbon Calculator, located in each subproject's "Operations" tab in the EDGE App; the file is then submitted for review and GBCI is emailed to confirm submission.
The Pre-Submission Quality Check
GBCI instructs teams to perform a rigorous quality check of the entire application before submitting for review. In practice that means four passes:
Model versus drawings — every Design Tab parameter matches the issued drawings (Section 12.4).
Measure versus User Guide — every claimed measure meets its stated requirement, in full, not partially.
Evidence versus measure — every claimed measure has its required document attached and legible.
Headroom check — record the margin above 20% in each category, so you know in advance which measures you can afford to lose.