2.1 Firm Certification vs Individual Certification
EPA Lead Abatement Supervisor 40 CFR 745 Subpart L
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Exam Facts, Supervisor Role, and Certification Path
1.1 Current Exam Facts 1.2 Supervisor Role, Responsibilities, and On-Site Presence 1.3 Prerequisites, Interim Certification, and the Third-Party Exam
2 Chapter 2: Firm Certification, Recertification, and Enforcement
2.1 Firm Certification vs Individual Certification 2.2 Recertification, 8-Hour Refresher, and 3-Year vs 5-Year Cycles 2.3 Suspension, Revocation, TSCA Violations, and Inspections
3 Chapter 3: Title X, 40 CFR 745, State Programs, and HUD Guidelines
3.1 Title X, TSCA 402–406, and 40 CFR 745 Architecture 3.2 Target Housing, Child-Occupied Facilities, and the 1978 Ban 3.3 EPA-Administered vs Authorized State Programs (Subpart Q) and Reciprocity 3.4 HUD Guidelines and Other Documented Methodologies
4 Chapter 4: Lead Health Effects, Blood-Lead Benchmarks, and Liability
4.1 Lead Toxicology, Child and Adult Health Effects, and Blood-Lead Benchmarks 4.2 Liability, Insurance, and Contract Risk for Abatement Supervisors
5 Chapter 5: What Counts as Abatement
5.1 Abatement vs Interim Controls vs RRP 5.2 Lead-Based Paint Definition and Component Language 5.3 Paint-Lead, Dust-Lead, and Soil-Lead Hazard Definitions
6 Chapter 6: Lead Hazard Recognition in the Field
6.1 Deteriorated Paint and Paint in Poor Condition 6.2 Friction, Impact, and Chewable Surface Hazards 6.3 High-Risk Components, Common Areas, and Dust Pathways
7 Chapter 7: Interpreting Inspection and Risk Assessment Reports
7.1 Reading Inspection Reports, XRF Results, and Paint-Chip Data 7.2 Reading Risk Assessment Reports and Selecting Control Options 7.3 Lead Hazard Screens vs Full Risk Assessments
8 Chapter 8: Occupant Protection Plans
8.1 Occupant Protection Plan Requirements 8.2 Relocation, Isolation of Work Areas, and Sensitive Occupants 8.3 Re-Occupancy Criteria, Occupant Notice, and Access Control
9 Chapter 9: Project Notification and Work Plans
9.1 Five-Business-Day Notification Contents and Electronic Filing 9.2 Updated, Canceled, EBL, and Emergency Notifications 9.3 Work Plans, Method Selection Documentation, and Pre-Abatement Walkthrough
10 Chapter 10: Interior Containment Design
10.1 Critical Barriers, Warning Signs, and Regulated Areas 10.2 Negative Air Pressure and HEPA Air-Filtration Units 10.3 Three-Stage Decontamination Units and Worker Flow
11 Chapter 11: Exterior Containment and Site Control
11.1 Exterior Ground Sheeting, Vertical Containment, and Weather Limits 11.2 Daily Exterior Cleanup, Paint-Chip Control, and Occupied/Multi-Family Logistics
12 Chapter 12: Component Replacement, Enclosure, and Encapsulation
12.1 Component Replacement 12.2 Enclosure Systems and Mechanical Fastening 12.3 Encapsulation Products, Unsuitable Surfaces, and Maintenance Schedules
13 Chapter 13: Paint Removal and Restricted Practices
13.1 Wet Scraping, Chemical Removal, and Heat Guns Below 1100°F 13.2 Restricted and Prohibited Practices 13.3 Selecting Methods, Combining Methods, and Documenting Why
14 Chapter 14: Interior Dust Abatement and Cleaning
14.1 Interior Dust Cleanup Sequence 14.2 Pre-Clearance Visual Inspection and When Cleanup Is Not Done
15 Chapter 15: Soil and Exterior Dust Abatement
15.1 Soil-Lead Hazards and Sampling Interpretation for Supervisors 15.2 Soil Removal and Replacement 15.3 Permanent Covering vs Landscaping
16 Chapter 16: OSHA 1926.62 Worker Protection
16.1 PEL, Action Level, and Exposure Assessment 16.2 Respiratory Protection, PPE, and Hygiene Facilities 16.3 Biological Monitoring and Medical Removal Protection 16.4 OSHA Competent Person Duties vs EPA Certified Supervisor Duties
17 Chapter 17: RCRA Waste Management
17.1 Abatement Waste Streams 17.2 TCLP Characterization and D008 17.3 Manifests, TSDF, Accumulation, and the Household Exclusion
18 Chapter 18: Action Levels, Post-Abatement Testing, and Records
18.1 Dust-Lead Action Levels vs Reportable-Level Hazards 18.2 Post-Abatement Visual, Dust Sampling, Independence, and the 1-Hour Wait 18.3 Failed Samples, Reclean/Retest, Exterior Visual, and Multi-Family Random Sampling 18.4 Abatement Report, 2026 Hazard Statement, Owner Copies, and 3-Year Retention
2.1 Firm Certification vs Individual Certification
Key Takeaways Explain This Topic AI
After March 1, 2000, a firm that performs or offers to perform any 40 CFR 745.227 lead-based paint activity must hold its own EPA firm certification — a certified supervisor does not certify the company.
The firm application attests two things: the firm will employ only appropriately certified employees, and the firm and those employees will follow 745.227 work practices; EPA has 90 days to approve or disapprove.
Lead-based paint activities firm certification and recertification each cost $550 every 3 years; a combined renovation plus LBP-activities firm application is also $550; a tribal firm pays $20.
A supervisor's individual fee is $410 (initial and recertification), the third-party exam is $70 per attempt, and a replacement identification card or certificate is $15.
Supervisor certification and firm certification are independent. A certified supervisor working for an uncertified firm is still a TSCA violation, and a certified firm using uncertified people is a separate ground for firm suspension or revocation.
Last updated: August 2026
Firm Certification vs Individual Certification
Quick Answer: After March 1, 2000, a company that performs or even offers to perform lead-based paint activities under 40 CFR 745.227 must hold its own EPA firm certification. A certified supervisor does not make the company legal. The firm attests it will hire only certified people and follow 745.227; EPA has 90 days to approve or disapprove. Firm certification and recertification each cost $550 every 3 years ($20 for a tribal firm). Combined renovation-plus-abatement firm applications also cost $550.
Two different pieces of paper have to be in force on an abatement job: the individual certificate (supervisor, worker, inspector, risk assessor, or project designer) and the firm certificate. 40 CFR 745.226 treats them as independent legal requirements. If either one is missing, the project is a TSCA violation even when the workmanship looks perfect.
Why EPA certifies the company, not just the people
A supervisor's card proves that one person completed an accredited course, passed the third-party exam, and met the experience prerequisite. It does not prove that the company will:
- employ only certified workers on every shift
- keep the 3-year records required by 745.227(i)
- file 5-business-day notifications before start
- refuse to send uncertified laborers to "help bag debris"
That is why 745.226(f)(1) requires all firms that perform or offer to perform any of the lead-based paint activities described in 745.227 after March 1, 2000 to be certified by EPA. "Offer to perform" is an exam favorite. Advertising abatement, bidding a HUD job, or signing a contract before the firm certificate arrives still counts. Waiting until the first day of containment is too late.
Individual certification is equally non-negotiable. 745.226(a)(5) makes it a TSCA violation for an individual to conduct any 745.227 activity after March 1, 2000 without being certified. The two rules sit side by side. Passing the supervisor exam does not absorb the firm duty, and paying the firm fee does not absorb the supervisor exam.
Application attestations and the 90-day clock
A firm seeking certification submits an electronic "Application for Firms" and the 745.238 fee. Under 745.226(f)(2) , that application attests two things:
The firm shall only employ appropriately certified employees to conduct lead-based paint activities.
The firm and its employees shall follow the work practice standards in § 745.227 .
From the date EPA receives the electronic application, EPA has 90 days to approve or disapprove ( 745.226(f)(3) ). Approval arrives as a certificate. Disapproval arrives as a letter describing the reasons. The firm must also maintain records under 745.227 ( 745.226(f)(4) ). EPA will not certify a firm that does not remit the fee ( 745.238(g) ).
Appropriately certified is discipline-specific. A certified worker cannot run the job as supervisor. A certified supervisor cannot collect the official post-abatement dust samples — that is inspector or risk assessor work. A firm that staffs the wrong discipline has employed people who are not certified for the task they are actually performing. The attestation is not a promise to "have some certified people around." It is a promise that every person doing a certified activity holds the matching discipline.
The "certified people, uncertified company" trap
Exam items love this fact pattern: a fully certified supervisor and a crew of certified workers start abatement for a painting contractor that never applied for firm certification. Every individual on site has a valid card. The job is still illegal.
Firm certification is an independent duty. A certified supervisor working for an uncertified firm is still a violation. The converse is also a classic item: a certified firm that sends an uncertified laborer to "just set poly" or "just run the HEPA vac" has performed certified work with uncertified individuals — a listed ground for suspending, revoking, or modifying the firm's certificate under 745.226(h)(1)(i) .
Treat the two certificates as a pair of locks on the same door. Unlocking one does not unlock the other.
Combined RRP + abatement firm application
Many contractors do both renovation (Subpart E / RRP) and abatement (Subpart L). EPA lets a firm file a combined renovation and lead-based paint activities firm application . The combined fee is still $550 — the same as a stand-alone LBP-activities firm — not $550 plus the $300 renovation-only fee. Recertification of the combined certificate is also $550 every 3 years. A combined tribal firm application is $20 .
Do not mix the two programs on the exam:
- Firm type Initial fee Recertification fee Cycle
- Renovation (RRP) only $300 $300 5 years
- Lead-based paint activities (abatement, inspection, risk assessment) $550 $550 3 years
- Combined renovation + LBP activities $550 $550 3 years
- Tribal firm (LBP or combined) $20 $20 Same cycle as the certificate type
- Tribal RRP-only firm $20 $20 5 years
The 3-year firm clock is a pay-the-fee recertification cycle under 745.226(f)(7) . The firm does not send its owners to an 8-hour refresher. That 3-year firm cycle is not the individual's 3-year versus 5-year recertification clock, and it is not the 6-month interim certificate that follows the initial supervisor course (Chapter 1).
Fees you must know by number
- Item Amount When it is paid Citation
- Firm LBP-activities certification $550 Initial application 40 CFR 745.238
- Firm LBP-activities recertification $550 Every 3 years 745.226(f)(7), 745.238
- Combined renovation + LBP-activities firm $550 Initial and every 3 years 745.238
- Tribal firm (LBP or combined) $20 Same cycles 745.238
- Individual supervisor certification $410 Initial 745.238
- Individual supervisor recertification $410 Individual 3- or 5-year cycle 745.238, 745.226(e)
- Tribal individual (each discipline) $10 Same as the individual cycle 745.238
- Third-party certification exam $70 Each attempt 745.238(c)(2)
- Replacement ID card or certificate $15 Lost or damaged 745.238(c)(3)
Worker individual certification is $310 ; inspector, risk assessor, supervisor, and project designer are $410 . Training-program accreditation fees are a different table and belong to the training-provider rules, not this chapter.
Applications and payments for firms and individuals are electronic ( 745.238(d) ). A firm that mails a paper check and waits is not "in process" under the current rule. EPA will not replace an identification card or certificate unless the $15 fee is paid ( 745.238(g)(2) ).
What firm certification does not replace
Firm certification does not :
- substitute for the supervisor's individual certificate or the third-party exam
- allow the firm to skip occupant protection plans, 5-business-day notification, or clearance under 745.227
- cover RRP work unless the firm also holds renovation certification or the combined certificate
travel automatically into an EPA-authorized state that runs its own firm program — check Subpart Q reciprocity (Chapter 3)
On a project you should be able to produce the firm's current EPA certificate, each person's current individual certificate, and proof of certification at the job site . Working without proof of certification is itself a ground for individual suspension under 745.226(g)(1)(iv), even if the card exists in a truck glove box across town.
Keep the fee numbers attached to the right person. $550 is the firm. $410 is the supervisor. $70 is each exam attempt. $15 is a replacement card. Mixing those four figures is one of the cheapest ways to miss a regulations item.