Study guide
7.2 Reading Risk Assessment Reports and Selecting Control Options
EPA Lead Abatement Supervisor 40 CFR 745 Subpart L
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Exam Facts, Supervisor Role, and Certification Path
1.1 Current Exam Facts 1.2 Supervisor Role, Responsibilities, and On-Site Presence 1.3 Prerequisites, Interim Certification, and the Third-Party Exam
2 Chapter 2: Firm Certification, Recertification, and Enforcement
2.1 Firm Certification vs Individual Certification 2.2 Recertification, 8-Hour Refresher, and 3-Year vs 5-Year Cycles 2.3 Suspension, Revocation, TSCA Violations, and Inspections
3 Chapter 3: Title X, 40 CFR 745, State Programs, and HUD Guidelines
3.1 Title X, TSCA 402–406, and 40 CFR 745 Architecture 3.2 Target Housing, Child-Occupied Facilities, and the 1978 Ban 3.3 EPA-Administered vs Authorized State Programs (Subpart Q) and Reciprocity 3.4 HUD Guidelines and Other Documented Methodologies
4 Chapter 4: Lead Health Effects, Blood-Lead Benchmarks, and Liability
4.1 Lead Toxicology, Child and Adult Health Effects, and Blood-Lead Benchmarks 4.2 Liability, Insurance, and Contract Risk for Abatement Supervisors
5 Chapter 5: What Counts as Abatement
5.1 Abatement vs Interim Controls vs RRP 5.2 Lead-Based Paint Definition and Component Language 5.3 Paint-Lead, Dust-Lead, and Soil-Lead Hazard Definitions
6 Chapter 6: Lead Hazard Recognition in the Field
6.1 Deteriorated Paint and Paint in Poor Condition 6.2 Friction, Impact, and Chewable Surface Hazards 6.3 High-Risk Components, Common Areas, and Dust Pathways
7 Chapter 7: Interpreting Inspection and Risk Assessment Reports
7.1 Reading Inspection Reports, XRF Results, and Paint-Chip Data 7.2 Reading Risk Assessment Reports and Selecting Control Options 7.3 Lead Hazard Screens vs Full Risk Assessments
8 Chapter 8: Occupant Protection Plans
8.1 Occupant Protection Plan Requirements 8.2 Relocation, Isolation of Work Areas, and Sensitive Occupants 8.3 Re-Occupancy Criteria, Occupant Notice, and Access Control
9 Chapter 9: Project Notification and Work Plans
9.1 Five-Business-Day Notification Contents and Electronic Filing 9.2 Updated, Canceled, EBL, and Emergency Notifications 9.3 Work Plans, Method Selection Documentation, and Pre-Abatement Walkthrough
10 Chapter 10: Interior Containment Design
10.1 Critical Barriers, Warning Signs, and Regulated Areas 10.2 Negative Air Pressure and HEPA Air-Filtration Units 10.3 Three-Stage Decontamination Units and Worker Flow
11 Chapter 11: Exterior Containment and Site Control
11.1 Exterior Ground Sheeting, Vertical Containment, and Weather Limits 11.2 Daily Exterior Cleanup, Paint-Chip Control, and Occupied/Multi-Family Logistics
12 Chapter 12: Component Replacement, Enclosure, and Encapsulation
12.1 Component Replacement 12.2 Enclosure Systems and Mechanical Fastening 12.3 Encapsulation Products, Unsuitable Surfaces, and Maintenance Schedules
13 Chapter 13: Paint Removal and Restricted Practices
13.1 Wet Scraping, Chemical Removal, and Heat Guns Below 1100°F 13.2 Restricted and Prohibited Practices 13.3 Selecting Methods, Combining Methods, and Documenting Why
14 Chapter 14: Interior Dust Abatement and Cleaning
14.1 Interior Dust Cleanup Sequence 14.2 Pre-Clearance Visual Inspection and When Cleanup Is Not Done
15 Chapter 15: Soil and Exterior Dust Abatement
15.1 Soil-Lead Hazards and Sampling Interpretation for Supervisors 15.2 Soil Removal and Replacement 15.3 Permanent Covering vs Landscaping
16 Chapter 16: OSHA 1926.62 Worker Protection
16.1 PEL, Action Level, and Exposure Assessment 16.2 Respiratory Protection, PPE, and Hygiene Facilities 16.3 Biological Monitoring and Medical Removal Protection 16.4 OSHA Competent Person Duties vs EPA Certified Supervisor Duties
17 Chapter 17: RCRA Waste Management
17.1 Abatement Waste Streams 17.2 TCLP Characterization and D008 17.3 Manifests, TSDF, Accumulation, and the Household Exclusion
18 Chapter 18: Action Levels, Post-Abatement Testing, and Records
18.1 Dust-Lead Action Levels vs Reportable-Level Hazards 18.2 Post-Abatement Visual, Dust Sampling, Independence, and the 1-Hour Wait 18.3 Failed Samples, Reclean/Retest, Exterior Visual, and Multi-Family Random Sampling 18.4 Abatement Report, 2026 Hazard Statement, Owner Copies, and 3-Year Retention
7.2 Reading Risk Assessment Reports and Selecting Control Options
Key Takeaways Explain This Topic AI
A risk assessment may be conducted only by a certified risk assessor (40 CFR 745.227(d)(1)). It includes a visual for deteriorated paint and causes, background and occupant-use patterns for children under 6, testing of deteriorated friction/impact surfaces and all other deteriorated paint, dust on sills and floors in living areas those children use (plus extra common-area and COF samples), and bare soil in play areas, the rest of the yard, and dripline/foundation areas.
The RA report must describe the location, type, and severity of identified lead-based paint hazards and interim controls and/or abatement options for each hazard with a suggested prioritization. If an encapsulant or enclosure is recommended, the report must include a maintenance and monitoring schedule (745.227(d)(11)(xvii)–(xviii)).
The supervisor translates those options into a work plan that matches the contract design: replacement, enclosure, encapsulation, paint removal, and soil removal or permanent covering are abatement when designed as permanent elimination; paint stabilization, specialized cleaning, mulch, and monitoring are interim.
Do not ignore soil or play areas. A play-area soil-lead hazard is ≥ 400 ppm bare soil; rest-of-yard is ≥ 1,200 ppm (745.227(h)(4)). On or after January 12, 2026, a dust-lead hazard on floors or interior sills is any reportable level; abatement of dust-lead still completes only below the 5 / 40 / 100 µg/ft² action levels.
Supervisors cannot collect the RA's paint, dust, or soil samples and cannot collect clearance dust samples. Post-abatement testing is inspector or risk assessor only (745.227(e)(8), (f)).
Last updated: August 2026
The RA report is a control-option memo, not a bid
Quick Answer: A risk assessment may be conducted only by a certified risk assessor ( 40 CFR 745.227(d)(1) ). It finds lead-based paint hazards (paint, dust, and soil) and, in the report, must describe the location, type, and severity of identified hazards and interim controls and/or abatement options for each, with a suggested prioritization . If an encapsulant or enclosure is recommended, the report shall recommend a maintenance and monitoring schedule ( 745.227(d)(11)(xvii)–(xviii) ). The supervisor translates those options into a work plan that matches the contract design (Chapter 5): permanent elimination is abatement ; paint stabilization and specialized cleaning are interim . Do not ignore soil or play areas. Do not collect the RA's paint, dust, or soil samples, and do not collect clearance dust samples .
Inspection told you which films are LBP. The RA tells you which of those films — plus dust and soil — are hazards now , and what the control menu looks like. You still write the OPP , pick the methods you will actually use, notify EPA or the authorized state, and later prepare the abatement report . You do not become the risk assessor by rewriting the dust numbers.
What a full RA is required to look at
745.227(d)(2)–(8) is the fieldwork the report is summarizing:
RA step Regulatory requirement Supervisor read
Visual Locate deteriorated paint , assess extent and causes , and other potential LBP hazards Moisture, friction, impact, and ordinary failure should be named; causes drive method choice
Background / use Physical characteristics and occupant-use patterns that may expose children under 6 Living areas, play rooms, and chewable height are not optional color
Paint testing Each friction or impact surface with visibly deteriorated paint , and all other surfaces with visibly deteriorated paint , if they have a distinct painting history This is not the poor-condition screen gate. Full RA tests visibly deteriorated paint, not only 2 / 10 / 10%
Dust — dwelling Interior window sills and floors in living areas where children under 6 are most likely to contact dust (composite or single-surface) On or after January 12, 2026 , a dust-lead hazard on floors or interior sills is any reportable level
Dust — multi-family / COF Additional sill and floor dust in common areas adjacent to the sampled unit or COF and other common areas where children under 6 contact dust Halls, stairs, and lobby play corners belong in the plan
Dust — COF extra Each room, hallway, or stairwell used by children under 6, plus other common areas they use A daycare classroom cannot be represented by the office
Soil Bare soil in exterior play areas , the rest of the yard (non-play), and dripline/foundation areas 400 ppm play area / 1,200 ppm rest of yard ( 745.227(h)(4) )
All of that sampling uses documented methodologies with quality control ( 745.227(d)(9) ). Chips, dust, and soil go through (f) : inspector or risk-assessor collection, NLLAP analysis. HUD Guidelines are again an (a)(3) methodology for how those samples are typically taken.
Required RA-report contents you will actually use
745.227(d)(11) is long on purpose. Identifying information mirrors the inspection report: date, address, construction date, apartment number, owner, assessor name, signature, and certification , firm, and the recognized laboratory name, address, and telephone. Then the substance:
Results of the visual inspection
Paint-testing method, specific locations tested, on-site data including quality-control data and XRF serial number
- Laboratory results for paint, soil, and dust, and any other sampling
- Background and occupant-use information
- Previous inspections used in the hazard determination
- (xvii) Location, type , and severity of identified LBP hazards and other potential lead hazards
(xviii) Interim controls and/or abatement options for each identified LBP hazard, with a suggested prioritization . If encapsulant or enclosure is recommended, include a maintenance and monitoring schedule.
(xviii) is the supervisor's shopping list. A report that lists hazards but no options is incomplete. A report that recommends encapsulation with no monitoring schedule is incomplete. You do not invent a monitoring interval because the manufacturer ran a TV ad.
Translate options into a work plan
Chapter 5's design test still governs. The RA is allowed to offer both interim and abatement for the same hazard. The written contract chooses the rule. If the job is certified abatement , you select permanent methods from the abatement column. If the owner bought interim controls , you are not on this supervisor credential for that design.
RA finding (examples) Interim-control option you may see Abatement option you may see What a certified abatement work plan should not do
Friction-sash paint-lead hazard; sill dust reportable Paint stabilization, window-well cleaning, restrict sash use, monitor Component replacement of the window assembly; dust taken below action levels Strip and latex-paint an operable sash and call it permanent; encapsulate a grinding pair
Deteriorated LBP on living-room walls Wet-scrape, repair, repaint, monitor Encapsulation (true encapsulant) or enclosure , with the report's monitoring schedule , or paint removal Encapsulate and throw the monitoring schedule away
Dust-lead on bedroom floor (reportable; for example 18 µg/ft²) Specialized cleaning, furniture HEPA, occupant education Interior dust abatement and cleanup until dust is below action levels Treat a mop-down as abatement complete without inspector/RA testing
Play-area bare soil 850 ppm Mulch, grass, restrict play, monitor (temporary) Remove and replace with soil as close to local background as practicable, ≤ 400 ppm , and do not reuse as residential topsoil; or permanently cover (pavement/concrete — not grass/mulch) Ignore soil because the crew is a paint crew, or dump play-area dirt in the side yard
Rest-of-yard bare soil 600 ppm Usually not a soil-lead hazard (off-play-area hazard is 1,200 ppm ) No rest-of-yard soil abatement required by this number Apply the 400 ppm play-area number to the whole lot without reading the RA's play vs yard split
Dripline/foundation bare soil the RA classified as a hazard Temporary covering / restrict access Address as the RA prioritized (often remove or permanently cover) Leave a chip-loaded dripline because the windows were the bid
Dust numbers to keep straight (clearance mechanics are Chapter 18): on or after January 12, 2026 , dust-lead action levels are 5 µg/ft² floors, 40 µg/ft² interior window sills, 100 µg/ft² window troughs. A dust-lead hazard on floors or interior sills is any reportable level . Abatement of dust-lead is complete only below the action levels . A floor at 3 µg/ft² can still be a hazard if 3 is reportable, while 18 µg/ft² is both a hazard and above the floor action level. Do not use retired 40/250/400 or 10/100 figures as current.
Prioritization in the report is a suggested order, often: surfaces a child under 6 can mouth or grind (chewable, friction windows), interior dust in living areas, play-area soil , then lower-traffic films. You may re-sequence for logistics. You may not drop a prioritized play-area soil hazard because the paint bid is easier.
Worked example — one RA page into one work plan
A 1964 single-family RA (children under 6 in the home) lists:
Living-room windows: deteriorated LBP on sashes; sill dust reportable → options: replace assemblies (abatement, first priority) or stabilize and educate (interim).
Living-room walls: LBP, 12 ft² peeling → options: encapsulate with 6-month visual monitoring for two years, then annual (abatement) or paint stabilization (interim).
Bedroom floor dust 18 µg/ft² → specialized cleaning (interim) or full interior dust abatement to below 5 µg/ft² .
Play-area bare soil 850 ppm → mulch (interim) or remove/replace to ≤ 400 ppm or pave (abatement).
Rest of yard 600 ppm → not a rest-of-yard soil-lead hazard.
The owner signs a certified-abatement contract to permanently eliminate the identified hazards. The supervisor's work plan therefore replaces the living-room window assemblies (not stabilize); encapsulates the walls only with the specified system and copies the maintenance and monitoring schedule into the owner discussion and into the abatement report ( 745.227(e)(10)(vi) requires any suggested monitoring of encapsulants or enclosures); performs interior dust cleanup aimed at below action levels ; and removes/replaces or permanently covers the play-area soil. Planting rye grass over 850 ppm play-area soil is not soil abatement. Leaving the play area for a later phase while declaring the job complete is ignoring a listed hazard.
If the owner had instead bought interim controls , paint stabilization, specialized cleaning, and mulch could match the RA's other column — and you would not file this as Subpart L abatement. Mixing columns — abatement notice plus mulch as the soil method — is how reports and jobs stop matching.
What the supervisor still cannot do with an RA in hand
Cannot collect paint, dust, or soil samples to fill in a thin RA ( 745.227(f) ).
Cannot collect clearance dust samples. Post-abatement visual and dust testing is inspector or risk assessor ( 745.227(e)(8) ), at least 1 hour after final cleanup, compared to 5 / 40 / 100 .
Cannot treat encapsulant as fire-and-forget. The RA's monitoring schedule is part of the option; the abatement report must carry suggested monitoring forward.
Cannot skip soil because the crew's skill is interior paint. 745.227(e)(7) soil abatement is still remove-and-replace (≤ 400 ppm, no reuse as residential topsoil) or permanent cover as defined in 745.223 (pavement or concrete, not grass or mulch).
The RA is the input. The OPP, notice, method selection, and abatement report are the outputs. Section 7.3 is what happens when the document in the truck is only a lead hazard screen .