1.6 Government Property Administration & Liability (FAR Part 45)
FAC-C Professional Contracting Certification Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Contracting System & FAR Foundations
1.1 FAC-C Professional Exam Logistics & Certification Path 1.2 FAR Structure, System Architecture & Authority 1.3 Ethics, Standards of Conduct & Conflict of Interest (FAR Part 3) 1.4 Protection of Privacy & Freedom of Information (FAR Part 24) 1.5 Foreign Acquisition, Buy American & Trade Agreements (FAR Part 25) 1.6 Government Property Administration & Liability (FAR Part 45)
2 Chapter 2: Acquisition Planning & Market Research
2.1 Acquisition Planning & Strategy Development (FAR Part 7) 2.2 Market Research Techniques & Commercial Determinations (FAR Part 10 & 12) 2.3 Describing Agency Needs & Performance Work Statements (FAR Part 11) 2.4 Publicizing Contract Actions & Synopsis Rules (FAR Part 5) 2.5 Competition Requirements & Justifications for Other Than Full and Open Competition (FAR Part 6) 2.6 Organizational Conflicts of Interest (OCI) Identification & Mitigation (FAR Subpart 9.5)
3 Chapter 3: Commercial & Simplified Acquisition
3.1 Commercial Products & Services Acquisition (FAR Part 12) 3.2 Simplified Acquisition Procedures (SAP) & Micro-Purchases (FAR Part 13) 3.3 Commercial Streamlined Evaluation & Award Protocols (FAR 12.6 & 13.106) 3.4 Governmentwide Commercial Purchase Card & Electronic Micro-Purchases (FAR 13.301) 3.5 Blanket Purchase Agreements, SF 44 & Imprest Funds 3.6 Fast Payment Procedures & Unpriced Purchase Orders (FAR 13.4 & 13.2)
4 Chapter 4: Solicitations, Contracting Methods & Contract Types
4.1 Sealed Bidding Procedures & Execution (FAR Part 14) 4.2 Contracting by Negotiation & Source Selection (FAR Part 15) 4.3 Fixed-Price Contract Types (FFP, FPIF, FPEA) (FAR Part 16) 4.4 Cost-Reimbursement Contract Types (CPFF, CPIF, CPAF) (FAR Part 16) 4.5 Indefinite-Delivery Contracts & Task/Delivery Orders (RFO Subpart 16.5) 4.6 Time-and-Materials, Labor-Hour & Letter Contracts (FAR Subpart 16.6)
5 Chapter 5: Cost & Price Analysis, Small Business & Negotiations
5.1 Proposal Evaluation & Competitive Range Determination (FAR 15.306) 5.2 Price Analysis Techniques & Commercial Pricing (FAR 15.404-1) 5.3 Cost Analysis, Certified Cost/Pricing Data & TAA (FAR 15.403 & 15.404) 5.4 Small Business Programs & Set-Aside Rules (FAR Part 19) 5.5 Pre-Negotiation Objectives & Competitive Negotiations (FAR 15.406) 5.6 Contract Financing & Advance/Progress Payments (FAR Part 32)
6 Chapter 6: Contract Administration, Modifications, Disputes & Protests
6.1 Post-Award Orientation, COR Delegation & Quality Assurance (FAR Part 42 & 46) 6.2 Contract Modifications, Scope & Change Orders (FAR Part 43) 6.3 Subcontract Management & Consent to Subcontract (FAR Part 44) 6.4 Contract Options, Extensions & Performance Evaluation (RFO Parts 17 & 42) 6.5 Contract Terminations for Convenience & Default (FAR Part 49) 6.6 Bid Protests, Disputes, Appeals & Contract Closeout (RFO Parts 33 & 4)
1.6 Government Property Administration & Liability (FAR Part 45)
Key Takeaways Explain This Topic AI
Government policy under FAR 45.102 mandates that contractors are ordinarily expected to furnish all property required for contract performance; Government property is provided only when specific statutory conditions are satisfied.
Government property is classified into Government-Furnished Property (GFP) and Contractor-Acquired Property (CAP), further categorized as Equipment, Material, Special Tooling (ST), Special Test Equipment (STE), or Real Property.
Under fixed-price contracts, the contractor generally assumes full risk of loss, damage, or destruction of government property, whereas under cost-reimbursement contracts, the Government assumes the risk under the self-insurance rule.
The Government's assumption of risk under cost-reimbursement contracts is voided if the loss of government property results from willful misconduct or lack of good faith by contractor managerial personnel.
Contractors must submit Standard Form 1428 (SF 1428 Inventory Disposal Schedule) to the Plant Clearance Officer (PLCO) to obtain disposition instructions for excess or scrap government property.
Last updated: July 2026
1.6 Government Property Administration & Liability (FAR Part 45)
Federal procurement policy establishes a strict baseline: contractors are ordinarily expected to furnish all property necessary to perform government contracts. FAR Part 45 (Government Property) prescribes policies and procedures for providing property to contractors, managing contractor property control systems, establishing risk of loss liability, and executing property disposition.
Policy Criteria for Providing Government Property (FAR 45.102)
Contracting Officers shall not provide property to contractors unless the CO documents a written Determination and Findings establishing that:
It is in the Government's best interest ;
The overall benefit to the acquisition significantly outweighs the administrative cost of managing the property;
Providing property does not create an unfair competitive advantage for the contractor; AND
Government requirements cannot otherwise be met .
Classifications of Government Property (FAR 45.101)
Government property includes all property owned by or leased to the Government, or acquired by the Government under a contract. It is divided into two primary acquisition origins and five functional categories:
Acquisition Origins
Government-Furnished Property (GFP): Property in the possession of or directly acquired by the Government and subsequently furnished to the contractor for contract performance.
Contractor-Acquired Property (CAP): Property acquired, fabricated, or otherwise provided by the contractor for contract performance, title to which vests in the Government under cost-reimbursement contracts.
Functional Categories
Equipment: Tangible items used in operations (e.g., machine tools, vehicles, test equipment).
Material: Property that may be consumed or expended during performance (e.g., raw stock, electronic components, hardware).
Special Tooling (ST): Specialized jigs, dies, fixtures, molds, and patterns crafted for single-purpose defense manufacturing.
Special Test Equipment (STE): Single or multipurpose integrated test units engineered to accomplish specialized testing.
Real Property: Land, buildings, structures, and utility systems.
Property Management System & Contractor Stewardship (FAR Subpart 45.105 & Clause 52.245-1)
Contractors holding government property must establish and maintain a compliant Property Management System across 10 lifecycle processes :
Acquisition: Verifying authority to acquire property.
Receipt: Inspecting and documenting received property.
Records: Maintaining detailed property records (tagging, serial numbers, location, value).
Physical Inventory: Conducting periodic physical counts.
Subcontract Control: Extending property oversight to subcontracts.
Reports: Issuing annual property accountability reports.
Discrepancies: Investigating and reporting loss, theft, damage, or destruction (LTDD).
Consumption: Tracking raw material usage against contract requirements.
Maintenance: Performing preventive maintenance and repair.
Property Closeout: Executing final inventory screening and disposition.
Government Property Roles
Property Administrator (PA): Authorized representative of the CO assigned to conduct Property Management System Analyses (PMSA) and audit contractor compliance.
Plant Clearance Officer (PLCO): Authorized representative of the CO assigned to screen, declare surplus, and direct final disposition of excess government property.
Risk of Loss & Liability Regimes (FAR 45.104 & Clause 52.245-1)
Liability for lost, stolen, damaged, or destroyed (LTDD) government property depends directly on the contract type:
Contract Type Government Property Liability Regime Exception to Rule
Fixed-Price Contracts Contractor Assumes Full Risk: Contractor is strictly liable for any loss, damage, or destruction of government property. None (unless government self-insurance option explicitly negotiated).
Cost-Reimbursement / T&M Contracts Government Assumes Risk (Self-Insurance): Government relieves contractor of liability for property loss/damage. Managerial Willful Misconduct Exception: Contractor is liable if loss results from willful misconduct or lack of good faith by contractor managerial personnel.
Managerial Willful Misconduct Exception
Under cost-reimbursement contracts, the Government's self-insurance rule is voided if property loss or destruction is caused by willful misconduct or lack of good faith on the part of contractor managerial personnel (corporate officers, directors, plant managers, or site superintendents). In such cases, the contractor is fully liable for repairing or replacing the damaged property at its own expense.
Property Disposition & Contract Closeout Procedures
When government property becomes excess to contract requirements, the contractor must submit Standard Form 1428 (SF 1428 Inventory Disposal Schedule) to the Plant Clearance Officer (PLCO).
The PLCO initiates plant clearance screening through the automated Plant Clearance Automated Reutilization Screening System (PCARSS).
Property disposition priorities follow a strict sequence: 1. Reutilization within agency; 2. Transfer to other federal agencies; 3. Donation to eligible state agencies; 4. Commercial public sale; 5. Scrap or destruction.
Upon completion of disposition, the PLCO issues relief of stewardship, allowing contract property closeout.
Property Management System Analysis (PMSA) & Loss Reporting Protocols
Under FAR 45.105, the Property Administrator (PA) periodically conducts a Property Management System Analysis (PMSA) to evaluate the effectiveness of the contractor property management control system. If the PA identifies systemic deficiencies in contractor property tracking, receipt, or physical inventory processes, the PA issues a formal written notification of system disapproval to the Contracting Officer. In the event of lost, stolen, damaged, or destroyed (LTDD) government property, the contractor must promptly submit a detailed incident report through the eTools / LTDD system . Under cost-reimbursement contracts, if the loss is determined to be the result of managerial willful misconduct or lack of good faith by corporate officers, the Contracting Officer issues a formal demand for financial restitution equal to the full replacement value of the lost asset.