4.3 Fixed-Price Contract Types (FFP, FPIF, FPEA) (FAR Part 16)
FAC-C Professional Contracting Certification Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Contracting System & FAR Foundations
1.1 FAC-C Professional Exam Logistics & Certification Path 1.2 FAR Structure, System Architecture & Authority 1.3 Ethics, Standards of Conduct & Conflict of Interest (FAR Part 3) 1.4 Protection of Privacy & Freedom of Information (FAR Part 24) 1.5 Foreign Acquisition, Buy American & Trade Agreements (FAR Part 25) 1.6 Government Property Administration & Liability (FAR Part 45)
2 Chapter 2: Acquisition Planning & Market Research
2.1 Acquisition Planning & Strategy Development (FAR Part 7) 2.2 Market Research Techniques & Commercial Determinations (FAR Part 10 & 12) 2.3 Describing Agency Needs & Performance Work Statements (FAR Part 11) 2.4 Publicizing Contract Actions & Synopsis Rules (FAR Part 5) 2.5 Competition Requirements & Justifications for Other Than Full and Open Competition (FAR Part 6) 2.6 Organizational Conflicts of Interest (OCI) Identification & Mitigation (FAR Subpart 9.5)
3 Chapter 3: Commercial & Simplified Acquisition
3.1 Commercial Products & Services Acquisition (FAR Part 12) 3.2 Simplified Acquisition Procedures (SAP) & Micro-Purchases (FAR Part 13) 3.3 Commercial Streamlined Evaluation & Award Protocols (FAR 12.6 & 13.106) 3.4 Governmentwide Commercial Purchase Card & Electronic Micro-Purchases (FAR 13.301) 3.5 Blanket Purchase Agreements, SF 44 & Imprest Funds 3.6 Fast Payment Procedures & Unpriced Purchase Orders (FAR 13.4 & 13.2)
4 Chapter 4: Solicitations, Contracting Methods & Contract Types
4.1 Sealed Bidding Procedures & Execution (FAR Part 14) 4.2 Contracting by Negotiation & Source Selection (FAR Part 15) 4.3 Fixed-Price Contract Types (FFP, FPIF, FPEA) (FAR Part 16) 4.4 Cost-Reimbursement Contract Types (CPFF, CPIF, CPAF) (FAR Part 16) 4.5 Indefinite-Delivery Contracts & Task/Delivery Orders (RFO Subpart 16.5) 4.6 Time-and-Materials, Labor-Hour & Letter Contracts (FAR Subpart 16.6)
5 Chapter 5: Cost & Price Analysis, Small Business & Negotiations
5.1 Proposal Evaluation & Competitive Range Determination (FAR 15.306) 5.2 Price Analysis Techniques & Commercial Pricing (FAR 15.404-1) 5.3 Cost Analysis, Certified Cost/Pricing Data & TAA (FAR 15.403 & 15.404) 5.4 Small Business Programs & Set-Aside Rules (FAR Part 19) 5.5 Pre-Negotiation Objectives & Competitive Negotiations (FAR 15.406) 5.6 Contract Financing & Advance/Progress Payments (FAR Part 32)
6 Chapter 6: Contract Administration, Modifications, Disputes & Protests
6.1 Post-Award Orientation, COR Delegation & Quality Assurance (FAR Part 42 & 46) 6.2 Contract Modifications, Scope & Change Orders (FAR Part 43) 6.3 Subcontract Management & Consent to Subcontract (FAR Part 44) 6.4 Contract Options, Extensions & Performance Evaluation (RFO Parts 17 & 42) 6.5 Contract Terminations for Convenience & Default (FAR Part 49) 6.6 Bid Protests, Disputes, Appeals & Contract Closeout (RFO Parts 33 & 4)
4.3 Fixed-Price Contract Types (FFP, FPIF, FPEA) (FAR Part 16)
Key Takeaways Explain This Topic AI
Fixed-price contracts (FAR Subpart 16.2) place maximum financial risk and performance responsibility on the contractor, incentivizing cost control and minimizing administrative oversight.
Firm-Fixed-Price (FFP) contracts establish a price that is not subject to adjustment regardless of the contractor's actual performance costs.
Fixed-Price Incentive Firm (FPIF) contracts specify a Target Cost, Target Profit, Target Price, Ceiling Price, and Share Ratio to share cost overruns and underruns between the government and contractor.
The Point of Total Assumption (PTA) in an FPIF contract represents the exact cost level where the contractor absorbs 100% of all further cost overruns, calculated as PTA = Target Cost + [(Ceiling Price - Target Price) / Government Share Ratio].
Fixed-Price with Economic Price Adjustment (FPEA) contracts protect both parties against severe market volatility by adjusting prices based on established catalog/market prices, actual cost of labor/material, or published price indexes.
Last updated: July 2026
4.3 Fixed-Price Contract Types (FFP, FPIF, FPEA) (FAR Part 16)
FAR Part 16 describes the selection and administration of contract types. Fixed-Price Contracts (FAR Subpart 16.2) provide for a firm price—or, in appropriate cases, an adjustable price—for supplies or services. Fixed-price contracts place financial risk on the contractor to manage performance within the established price ceiling.
Risk Allocation & Contract Type Spectrum
Contract types fall along a continuous spectrum of risk allocation between the government and the contractor: [Firm-Fixed-Price (FFP)] ──► [FPEA] ──► [FPIF] ──► [CPIF] ──► [CPFF] ──► [Cost-Plus-Award-Fee (CPAF)]
- ◄── Maximum Contractor Risk Maximum Government Risk ──►
- ◄── Minimum Gov Admin Burden Maximum Gov Admin Burden ──►
- 1. Firm-Fixed-Price (FFP) Contracts (FAR 16.202)
A Firm-Fixed-Price contract establishes a price that is not subject to any adjustment on the basis of the contractor's cost experience in performing the contract. It places maximum risk and full responsibility for all costs and resulting profit or loss upon the contractor.
Mandatory Application Criteria
Contracting officers must prefer FFP contracts when:
- Acquiring commercial products or commercial services (FAR Part 12);
- Performance specifications are clear, complete, and stable;
- Detailed design or performance drawings exist;
Adequate price competition exists to establish price reasonableness.
2. Fixed-Price with Economic Price Adjustment (FPEA) (FAR 16.203)
An FPEA contract is a fixed-price contract that provides for upward and downward revision of the stated contract price upon the occurrence of specified contingencies. FPEA contracts protect both parties against extreme price volatility during extended performance periods.
Three Authorized Types of Adjustments (FAR 16.203-1)
Established Prices: Adjustments based on changes in the contractor's established catalog or market prices of specific items.
Actual Costs of Labor or Material: Adjustments based on actual increases or decreases in the unit costs of labor or materials experienced by the contractor during performance.
Cost Indexes of Labor or Material: Adjustments based on changes in labor or material cost standards or published indexes (e.g., Bureau of Labor Statistics Producer Price Index).
3. Fixed-Price Incentive Firm (FPIF) Target Contracts (FAR 16.204 & 16.403)
An FPIF contract is a fixed-price contract that provides for adjusting profit and establishing the final contract price by a formula based on the relationship of final negotiated total cost to total target cost.
Key Structural Elements of FPIF Contracts
Target Cost (TC): The baseline cost estimated for contract performance.
Target Profit (TP): The negotiated profit paid if actual costs equal Target Cost.
Target Price: Total of Target Cost plus Target Profit ( Target Price = T C + T P \text{Target Price} = TC + TP Target Price = TC + TP ).
Ceiling Price (CP): The maximum dollar amount the government will pay under the contract (expressed as a percentage of Target Cost, e.g., 120% or 125%). The contractor performs at its own risk above the ceiling price.
Share Ratio (Government % / Contractor %): The cost-sharing formula for overruns and underruns below the Point of Total Assumption (e.g., 70/30 or 80/20).
Mathematical Calculations & Formulas for FPIF
Core Equations Target Price = Target Cost + Target Profit \text{Target Price} = \text{Target Cost} + \text{Target Profit} Target Price = Target Cost + Target Profit Contractor Profit = Target Profit + [ Contractor Share % × ( Target Cost − Actual Cost ) ] \text{Contractor Profit} = \text{Target Profit} + [\text{Contractor Share \%} \times (\text{Target Cost} - \text{Actual Cost})] Contractor Profit = Target Profit + [ Contractor Share % × ( Target Cost − Actual Cost )] Final Contract Price = Actual Cost + Contractor Profit ( Capped at Ceiling Price ) \text{Final Contract Price} = \text{Actual Cost} + \text{Contractor Profit} \quad (\text{Capped at Ceiling Price}) Final Contract Price = Actual Cost + Contractor Profit ( Capped at Ceiling Price )
The Point of Total Assumption (PTA) Formula
The Point of Total Assumption (PTA) is the exact cost level where the contractor's profit drops enough that the final contract price hits the Ceiling Price. Beyond the PTA, the contractor bears 100% of all additional cost overruns . PTA = Target Cost + Ceiling Price − Target Price Government Share Ratio \text{PTA} = \text{Target Cost} + \frac{\text{Ceiling Price} - \text{Target Price}}{\text{Government Share Ratio}} PTA = Target Cost + Government Share Ratio Ceiling Price − Target Price
- Step-by-Step Numerical FPIF Examples
- Baseline Contract Parameters
- Target Cost (TC): $1,000,000
- Target Profit (TP): $100,000 (10% of target cost)
- Target Price: $1,100,000 ($1,000,000 + $100,000)
- Ceiling Price (CP): $1,200,000 (120% of target cost)
- Share Ratio: 80/20 (80% Government Share / 20% Contractor Share)
Step 1: Calculate the Point of Total Assumption (PTA) PTA = $ 1 , 000 , 000 + $ 1 , 200 , 000 − $ 1 , 100 , 000 0.80 = $ 1 , 000 , 000 + $ 100 , 000 0.80 = $ 1 , 000 , 000 + $ 125 , 000 = $ 1 , 125 , 000 \text{PTA} = \$1,000,000 + \frac{\$1,200,000 - \$1,100,000}{0.80} = \$1,000,000 + \frac{\$100,000}{0.80} = \$1,000,000 + \$125,000 = \$1,125,000 PTA = $1 , 000 , 000 + 0.80 $1 , 200 , 000 − $1 , 100 , 000 = $1 , 000 , 000 + 0.80 $100 , 000 = $1 , 000 , 000 + $125 , 000 = $1 , 125 , 000
Analysis: At an actual cost of $1,125,000, the contractor's profit is $75,000, and final price equals $1,200,000. At any actual cost above $1,125,000, the 80/20 share ratio no longer applies, and the contractor absorbs 100% of further overruns.
Step 2: Evaluate Underrun Scenario (Actual Cost = $900,000)
Cost Underrun: $1,000,000 - $900,000 = $100,000 savings.
Contractor Share of Underrun: 20% of $100,000 = $20,000 extra profit.
Total Contractor Profit: $100,000 + $20,000 = $120,000 .
Final Price to Government: $900,000 + $120,000 = $1,020,000 .
Result: Government saves $80,000; contractor earns $20,000 incentive bonus.
Step 3: Evaluate Moderate Overrun Scenario (Actual Cost = $1,100,000 — Below PTA)
Cost Overrun: $1,100,000 - $1,000,000 = $100,000 overrun.
Contractor Share of Overrun: 20% of $100,000 = $20,000 profit reduction.
Total Contractor Profit: $100,000 - $20,000 = $80,000 .
Final Price to Government: $1,100,000 + $80,000 = $1,180,000 (below $1,200,000 ceiling).
Step 4: Evaluate Severe Overrun Scenario (Actual Cost = $1,250,000 — Above PTA)
Actual Cost ($1,250,000) exceeds PTA ($1,125,000).
Final Price to Government is capped at Ceiling Price = $1,200,000 .
Total Contractor Profit / (Loss): Ceiling Price ($1,200,000) - Actual Cost ($1,250,000) = -$50,000 (Loss of $50,000) .