Study guide

5.3 Cost Analysis, Certified Cost/Pricing Data & TAA (FAR 15.403 & 15.404)

FAC-C Professional Contracting Certification Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Contracting System & FAR Foundations

1.1 FAC-C Professional Exam Logistics & Certification Path 1.2 FAR Structure, System Architecture & Authority 1.3 Ethics, Standards of Conduct & Conflict of Interest (FAR Part 3) 1.4 Protection of Privacy & Freedom of Information (FAR Part 24) 1.5 Foreign Acquisition, Buy American & Trade Agreements (FAR Part 25) 1.6 Government Property Administration & Liability (FAR Part 45)

2 Chapter 2: Acquisition Planning & Market Research

2.1 Acquisition Planning & Strategy Development (FAR Part 7) 2.2 Market Research Techniques & Commercial Determinations (FAR Part 10 & 12) 2.3 Describing Agency Needs & Performance Work Statements (FAR Part 11) 2.4 Publicizing Contract Actions & Synopsis Rules (FAR Part 5) 2.5 Competition Requirements & Justifications for Other Than Full and Open Competition (FAR Part 6) 2.6 Organizational Conflicts of Interest (OCI) Identification & Mitigation (FAR Subpart 9.5)

3 Chapter 3: Commercial & Simplified Acquisition

3.1 Commercial Products & Services Acquisition (FAR Part 12) 3.2 Simplified Acquisition Procedures (SAP) & Micro-Purchases (FAR Part 13) 3.3 Commercial Streamlined Evaluation & Award Protocols (FAR 12.6 & 13.106) 3.4 Governmentwide Commercial Purchase Card & Electronic Micro-Purchases (FAR 13.301) 3.5 Blanket Purchase Agreements, SF 44 & Imprest Funds 3.6 Fast Payment Procedures & Unpriced Purchase Orders (FAR 13.4 & 13.2)

4 Chapter 4: Solicitations, Contracting Methods & Contract Types

4.1 Sealed Bidding Procedures & Execution (FAR Part 14) 4.2 Contracting by Negotiation & Source Selection (FAR Part 15) 4.3 Fixed-Price Contract Types (FFP, FPIF, FPEA) (FAR Part 16) 4.4 Cost-Reimbursement Contract Types (CPFF, CPIF, CPAF) (FAR Part 16) 4.5 Indefinite-Delivery Contracts & Task/Delivery Orders (RFO Subpart 16.5) 4.6 Time-and-Materials, Labor-Hour & Letter Contracts (FAR Subpart 16.6)

5 Chapter 5: Cost & Price Analysis, Small Business & Negotiations

5.1 Proposal Evaluation & Competitive Range Determination (FAR 15.306) 5.2 Price Analysis Techniques & Commercial Pricing (FAR 15.404-1) 5.3 Cost Analysis, Certified Cost/Pricing Data & TAA (FAR 15.403 & 15.404) 5.4 Small Business Programs & Set-Aside Rules (FAR Part 19) 5.5 Pre-Negotiation Objectives & Competitive Negotiations (FAR 15.406) 5.6 Contract Financing & Advance/Progress Payments (FAR Part 32)

6 Chapter 6: Contract Administration, Modifications, Disputes & Protests

6.1 Post-Award Orientation, COR Delegation & Quality Assurance (FAR Part 42 & 46) 6.2 Contract Modifications, Scope & Change Orders (FAR Part 43) 6.3 Subcontract Management & Consent to Subcontract (FAR Part 44) 6.4 Contract Options, Extensions & Performance Evaluation (RFO Parts 17 & 42) 6.5 Contract Terminations for Convenience & Default (FAR Part 49) 6.6 Bid Protests, Disputes, Appeals & Contract Closeout (RFO Parts 33 & 4)

5.3 Cost Analysis, Certified Cost/Pricing Data & TAA (FAR 15.403 & 15.404)

Key Takeaways Explain This Topic AI

Cost analysis under FAR 15.404-1(c) evaluates individual cost elements (direct labor, materials, indirect overhead) and profit to determine price reasonableness.

The statutory threshold for Certified Cost or Pricing Data under the Truthful Cost or Pricing Data Act (TINA) is $2,000,000 (FAR 15.403-4).

Statutory exceptions to certified cost or pricing data include adequate price competition, commercial items, prices set by law/regulation, and HCA waivers.

Cost realism analysis is mandatory for cost-reimbursement contracts under FAR 15.404-1(d) to establish the Most Probable Cost (MPC) for evaluation purposes.

The Trade Agreements Act (TAA) under FAR Subpart 25.4 waives Buy American Act restrictions for designated country end products exceeding threshold limits.

Last updated: July 2026

5.3 Cost Analysis, Certified Cost/Pricing Data & TAA (FAR 15.403 & 15.404)

When price analysis alone cannot verify a proposed price to be fair and reasonable—or when required by statute—the Government performs cost analysis under FAR 15.404-1(c) . Cost analysis involves the detailed evaluation of separate cost elements (such as direct labor, material, subcontracts, and indirect overhead pools) and proposed profit or fee in an offeror's cost proposal.

Truthful Cost or Pricing Data Act (TINA) (FAR 15.403-4)

The Truthful Cost or Pricing Data Act (formerly known as the Truth in Negotiations Act or TINA, 10 U.S.C. 3702 and 41 U.S.C. 3502) requires contractors to submit certified cost or pricing data for high-dollar negotiated contracts.

Key TINA Parameters

Statutory Threshold: $2,000,000 (FAR 15.403-4(a)(1)). Appreciates to non-exempt negotiated contract awards, subcontracts, and contract modifications exceeding $2,000,000.

Definition of Cost or Pricing Data: All facts that prudent buyers and sellers would reasonably expect to affect price negotiations significantly as of the date of price agreement.

Certificate of Current Cost or Pricing Data (FAR 15.406-2): The contractor must execute a formal certificate stating that, to the best of its knowledge and belief, the cost or pricing data submitted are accurate, complete, and current as of the date agreement on price was reached. [Negotiations Complete / Agreement Reached] ➔ [Contractor Executes Certificate (FAR 15.406-2)] ➔ [Data Certified as Accurate, Complete & Current]

Statutory Exceptions to Certified Cost or Pricing Data (FAR 15.403-1(b))

Under FAR 15.403-1(b) , the Contracting Officer shall NOT request or require certified cost or pricing data if any of the following five statutory exceptions apply:

Exception Category FAR Citation Statutory Basis & Application Rules

Adequate Price Competition FAR 15.403-1(b)(1) Two or more responsible offerors submitting competitive proposals.

Prices Set by Law or Regulation FAR 15.403-1(b)(2) Pronouncements of law/reg setting fixed prices (e.g., regulated utility tariffs).

Commercial Product / Service FAR 15.403-1(b)(3) Acquisition of commercial items satisfying FAR 2.101 definition.

HCA Waiver Granted FAR 15.403-1(b)(4) Waiver granted by Head of Contracting Activity in writing (exceptional cases).

Modification of Commercial Contract FAR 15.403-1(b)(5) Modification to contract for commercial items where commercial character retained.

Cost Realism Analysis & Most Probable Cost (MPC) (FAR 15.404-1(d))

Cost realism analysis is the process of independently reviewing and evaluating specific cost elements in an offeror's proposal to determine whether the proposed costs:

  • Are realistic for the work to be performed;
  • Reflect a clear understanding of contract requirements; and

Are consistent with the unique methods of performance described in the technical proposal.

Application Rules by Contract Type

Cost-Reimbursement Contracts: Cost realism analysis is MANDATORY for all competitive cost-reimbursement contracts (FAR 15.404-1(d)(2)). The results of cost realism analysis must be used to adjust the offeror's proposed costs to determine the Most Probable Cost (MPC) . The MPC represents the Government's estimate of the realistic cost of performance and must be used for evaluation purposes to evaluate best value. (However, the contract is awarded at the proposed target cost, not the MPC).

Fixed-Price Contracts: Cost realism analysis may be performed on competitive fixed-price contracts (e.g., when evaluating performance risk or unreasonableness of low bids), but proposed prices SHALL NOT be adjusted as a result of cost realism analysis (FAR 15.404-1(d)(3)).

Defective Pricing & Government Remedies (FAR 15.407-1)

If the Government subsequently discovers that a contractor submitted cost or pricing data that were inaccurate, incomplete, or noncurrent prior to the date of price agreement, the contract price is considered defective .

Government Defective Pricing Remedies

Price Reduction Clause (FAR 52.215-10 / 52.215-11): The Government is entitled to an equitable price reduction, including profit or fee, in the amount by which the evaluation was over-stated due to defective data.

Interest Payment: The Government is entitled to interest on any overpayments made to the contractor as a result of defective pricing.

Penalties: If the contractor knowingly submitted defective cost or pricing data, the CO may assess penalty damages equal to the amount of the overpayment.

Trade Agreements Act (TAA) Compliance (FAR Subpart 25.4)

The Trade Agreements Act (TAA) (19 U.S.C. 2501 et seq.) authorizes the President to waive Buy American Act restrictions for eligible products from countries that have entered into trade agreements with the United States.

  • TAA Statutory Dollar Thresholds
  • Supply Contracts Threshold: $174,000
  • Construction Contracts Threshold: $6,683,000
  • The Substantial Transformation Test (FAR 25.001(c))

Under the TAA, an end product is evaluated based on its country of origin. If a product contains components manufactured in non-designated countries, it satisfies TAA compliance only if it undergoes substantial transformation in the United States or a TAA designated country:

Substantial Transformation: A process resulting in a new and different article of commerce having a distinctive name, character, or use different from that of the pre-existing raw materials or components.