6.3 Subcontract Management & Consent to Subcontract (FAR Part 44)
FAC-C Professional Contracting Certification Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Contracting System & FAR Foundations
1.1 FAC-C Professional Exam Logistics & Certification Path 1.2 FAR Structure, System Architecture & Authority 1.3 Ethics, Standards of Conduct & Conflict of Interest (FAR Part 3) 1.4 Protection of Privacy & Freedom of Information (FAR Part 24) 1.5 Foreign Acquisition, Buy American & Trade Agreements (FAR Part 25) 1.6 Government Property Administration & Liability (FAR Part 45)
2 Chapter 2: Acquisition Planning & Market Research
2.1 Acquisition Planning & Strategy Development (FAR Part 7) 2.2 Market Research Techniques & Commercial Determinations (FAR Part 10 & 12) 2.3 Describing Agency Needs & Performance Work Statements (FAR Part 11) 2.4 Publicizing Contract Actions & Synopsis Rules (FAR Part 5) 2.5 Competition Requirements & Justifications for Other Than Full and Open Competition (FAR Part 6) 2.6 Organizational Conflicts of Interest (OCI) Identification & Mitigation (FAR Subpart 9.5)
3 Chapter 3: Commercial & Simplified Acquisition
3.1 Commercial Products & Services Acquisition (FAR Part 12) 3.2 Simplified Acquisition Procedures (SAP) & Micro-Purchases (FAR Part 13) 3.3 Commercial Streamlined Evaluation & Award Protocols (FAR 12.6 & 13.106) 3.4 Governmentwide Commercial Purchase Card & Electronic Micro-Purchases (FAR 13.301) 3.5 Blanket Purchase Agreements, SF 44 & Imprest Funds 3.6 Fast Payment Procedures & Unpriced Purchase Orders (FAR 13.4 & 13.2)
4 Chapter 4: Solicitations, Contracting Methods & Contract Types
4.1 Sealed Bidding Procedures & Execution (FAR Part 14) 4.2 Contracting by Negotiation & Source Selection (FAR Part 15) 4.3 Fixed-Price Contract Types (FFP, FPIF, FPEA) (FAR Part 16) 4.4 Cost-Reimbursement Contract Types (CPFF, CPIF, CPAF) (FAR Part 16) 4.5 Indefinite-Delivery Contracts & Task/Delivery Orders (RFO Subpart 16.5) 4.6 Time-and-Materials, Labor-Hour & Letter Contracts (FAR Subpart 16.6)
5 Chapter 5: Cost & Price Analysis, Small Business & Negotiations
5.1 Proposal Evaluation & Competitive Range Determination (FAR 15.306) 5.2 Price Analysis Techniques & Commercial Pricing (FAR 15.404-1) 5.3 Cost Analysis, Certified Cost/Pricing Data & TAA (FAR 15.403 & 15.404) 5.4 Small Business Programs & Set-Aside Rules (FAR Part 19) 5.5 Pre-Negotiation Objectives & Competitive Negotiations (FAR 15.406) 5.6 Contract Financing & Advance/Progress Payments (FAR Part 32)
6 Chapter 6: Contract Administration, Modifications, Disputes & Protests
6.1 Post-Award Orientation, COR Delegation & Quality Assurance (FAR Part 42 & 46) 6.2 Contract Modifications, Scope & Change Orders (FAR Part 43) 6.3 Subcontract Management & Consent to Subcontract (FAR Part 44) 6.4 Contract Options, Extensions & Performance Evaluation (RFO Parts 17 & 42) 6.5 Contract Terminations for Convenience & Default (FAR Part 49) 6.6 Bid Protests, Disputes, Appeals & Contract Closeout (RFO Parts 33 & 4)
6.3 Subcontract Management & Consent to Subcontract (FAR Part 44)
Key Takeaways Explain This Topic AI
An ordinary subcontractor lacks direct privity with the Government for a CDA claim; a legally valid prime-sponsored claim may be available. Protest standing and subcontract-award jurisdiction require separate analysis.
Consent follows RFO 44.201 and the actual 52.244-2 clause. Approved purchasing systems still require consent for specifically identified subcontracts; fixed-price primes have the clause's unpriced-action limitation.
Advance notification is distinct from consent. Civilian cost-reimbursement contracts other than NASA/Coast Guard retain specified statutory notification requirements even with an approved purchasing system.
RFO 44.301-2 makes CPSR need depend on risk factors; it does not set a universal $25 million trigger. Following a decision to conduct a CPSR, reassess its need at least every three years.
Subcontracting plans generally apply over $900,000, or $2 million for construction of a public facility, when subcontracting possibilities exist and no exception applies. Missing a goal alone does not automatically establish lack of good faith.
Commercial-subcontract flow-downs depend on the current 52.244-6 table and each included clause's own applicability; commercial status is not a blanket exemption.
Last updated: October 2026
6.3 Subcontract Management & Consent to Subcontract
The October 2026 exam FAQ uses RFO-updated FAR and DFARS. This section uses current RFO Part 44 and related clauses ; actual acquisitions also require the applicable agency deviations and contract terms.
1. Privity, claims and protests
An ordinary prime/subcontract relationship has a Government–prime contract and a separate prime–subcontractor contract. Government consent to subcontract does not create a direct Government–subcontractor contract. Government <-- prime contract --> Prime contractor
- |
- subcontract
- |
- Subcontractor
- Ordinarily, no direct Government–subcontractor contract
Under 41 U.S.C. 7101(7) , a CDA contractor is a party to the Federal Government contract. An ordinary subcontractor without privity generally cannot bring a direct CDA claim on the prime contract. A valid prime-sponsored claim may be available, subject to sponsorship, certification and other legal requirements; consult counsel. This is not a rule that every person called a subcontractor is barred in every legal circumstance. CBCA Allred , pages 2–4, discusses the narrow agency/privity issue; CBCA Smith Management , pages 6–7, recognizes the sponsored appeal on its specific facts.
Bid protests have separate standing rules. Under 4 CFR 21.0(a) , GAO's ordinary interested-party test concerns an actual or prospective bidder or offeror with direct economic interest. Subcontractor status alone does not confer standing to challenge the prime award. Under 4 CFR 21.5 , GAO generally does not review subcontract awards except an agency request under 21.13, and contract administration is generally outside bid-protest review. Do not turn these qualified rules into a universal ban on all subcontractor claims or protests in every forum.
2. Consent and advance notification
Consent is the CO's written approval to enter a particular subcontract. Read RFO 44.201 together with the actual 52.244-2 clause and its schedule entries.
Approved purchasing system: Consent remains required for the subcontracts specifically identified in clause paragraph (d).
No approved system: Paragraph (c) covers cost-reimbursement, T&M and labor-hour subcontracts, plus fixed-price subcontracts meeting its dollar tests.
Fixed-price prime: Paragraph (b) limits consent to unpriced contract actions, including unpriced modifications or delivery orders, and only when (c) or (d) requires it. A cost-type subcontract under any fully priced fixed-price prime is not automatically subject to this clause's consent rule.
For fixed-price subcontracts under paragraph (c), the test is the greater of SAT or 5% of total estimated prime cost for DoD, Coast Guard and NASA awards. For other civilian agencies, it is either SAT or 5% . Use the SAT on the subcontract-award date; the two tests are not interchangeable.
Advance notification is distinct from consent. Under RFO 44.201-2, a cost-reimbursement prime must notify before a CPFF subcontract or a qualifying fixed-price subcontract. For DoD, Coast Guard and NASA, approved-system status provides the stated exception and the fixed-price test uses the greater threshold. For other civilian agencies, notification applies even with an approved system and uses the either-threshold test. Clause Alternate I implements the latter requirement.
Unless expressly stated otherwise, consent or purchasing-system approval does not determine acceptability of subcontract terms or price, cost allowability, or relieve the prime of performance responsibility. RFO 44.201-4 prohibits, among other things, consenting to cost-plus-percentage-of-cost subcontracts or terms making a private subcontract dispute binding on the Government.
3. Contractor purchasing system review
A CPSR assesses purchasing efficiency, effectiveness and compliance, supporting approval, withholding or withdrawal of purchasing-system approval.
RFO 44.301-2 requires the responsible CO to decide whether a CPSR is needed based on such factors as past performance and the volume, complexity and dollar value of subcontracts. The current text has no universal $25 million sales trigger. Once the CO determines to conduct a CPSR, the CO must reassess whether one is needed at least every three years ; that is not an automatic requirement to conduct a new full review every three years.
Approval can reduce routine consent requirements, but specifically identified subcontracts remain subject to consent and applicable notification remains. If approval is withdrawn, apply the contract's rules for an unapproved system; withdrawal does not create a blanket requirement for consent to every subcontract regardless of type, price or prime-contract conditions.
4. Small-business plans, reporting and good faith
Under RFO 19.109 , acquisitions expected to exceed $900,000 , or $2 million for construction of a public facility , generally require the selected offeror to submit an acceptable subcontracting plan when subcontracting possibilities exist. Exceptions include small-business concerns, personal-services contracts and contracts or modifications performed entirely outside the United States and its outlying areas. Threshold alone is insufficient.
RFO 19.206-1 distinguishes:
- Plan Coverage
- Individual One contract, including options, with separate goals for the base and options
Master Plant/division-wide elements except goals; effective for three years after approval and incorporated into an individual plan
Commercial The contractor's fiscal year; covers relevant commercial production/services and Government contracts while effective
A commercial plan is a method of compliance, not a blanket commercial-contract exemption. RFO 19.302-2 requires monitoring and reports in the prescribed SPR within 45 days after the report ending date . Follow the current clause and reporting instructions rather than assuming legacy paper forms or a superseded platform.
Under 52.219-16 , missing a goal alone does not automatically establish failure to make a good-faith effort. Before a final decision, the CO gives written notice, permits the contractor to demonstrate good faith and discuss the matter, and considers pertinent evidence. If the CO finds lack of good faith under the clause, liquidated damages correspond to the actual dollar shortfall in each goal, measured against actual subcontracting dollars; a commercial plan uses the Government-attributable pro rata share. The decision is subject to the Disputes clause.
5. Applicable flow-down clauses
52.244-6 governs subcontracts for commercial products and commercial services. If a listed clause is included in the prime contract, insert it and flow down its requirements as the individual clause directs. Examples include applicable veterans/disability employment requirements, anti-trafficking and accelerated small-business payment provisions. Each clause's conditions still matter.
Include the terms of 52.244-6, including its lower-tier requirement, as directed by paragraph (c). Noncommercial subcontract requirements also depend on their individual prescriptions and conditions. Do not treat every FAR, CAS, pricing-data or domestic-preference requirement as universally applicable to every noncommercial subcontract.
Consent, purchasing-system approval, small-business plans and flow-downs answer different questions. Satisfying one does not automatically satisfy the others.